Port Arthur Steam Energy, L.P. v. Oxbow Calcining LLC

Court of Appeals of Texas·Decided March 30, 2021·No. 01-20-00606-CV·Published

Opinion

Order issued March 30, 2021

In The

Court of Appeals For The

First District of Texas ———————————— NO. 01-20-00606-CV ——————————— PORT ARTHUR STEAM ENERGY, L.P., Appellant V. OXBOW CALCINING LLC, Appellee

On Appeal from the 270th District Court Harris County, Texas Trial Court Case No. 2020-18313

ORDER ON MOTION TO REVIEW SUPERSEDEAS BOND

Pursuant to Texas Rule of Appellate Procedure 24.4, appellant, Port Arthur

Steam Energy, L.P. (“PASE”), requests that this Court review and vacate or

reverse the trial court’s order requiring a $1,207,282.97 bond to supersede

execution of an arbitration award that was confirmed by the trial court. PASE also requests that the bond amount to be set at no more than $138,574.28. We deny

PASE’s Motion to Review Supersedeas Order.1

Background

PASE owns a waste heat recovery facility in Port Arthur, Texas. Appellee,

Oxbow Calcining LLC (“Oxbow”), owns and operates an adjacent coke-calcining

plant in Port Arthur. PASE and Oxbow’s predecessor entered into a Heat

Exchange Agreement (“HEA”),2 the alleged breach of which caused the parties to

engage in arbitration.

On March 17, 2020, an arbitration panel issued an arbitration award in favor

of Oxbow. The arbitration award was confirmed by the trial court in a July 23,

2020 final judgment.3 The arbitration panel found, among other things, that PASE

breached the HEA4 and that Oxbow had no liability to PASE. The arbitration

award ordered PASE to pay the following:

1 PASE filed a combined Motion to Review Supersedeas Order and Emergency Motion to Stay. On January 7, 2021, the Court granted the portion of PASE’s motion requesting a stay of the trial court proceedings pending this Court’s disposition of the motion to review supersedeas order. We now address the remaining portion of PASE’s combined motion. 2 According to the arbitration award, “Broadly speaking, Oxbow provided waste heat generated by the calcining process to PASE.” 3 The final judgment granted Oxbow’s motion to confirm the arbitration award and denied PASE’s motion to vacate the arbitration award. 4 The arbitration panel found that PASE breached the HEA by bringing an action in state court and by failing to fund an escrow account.

2 • $500,000 in escrow plus interest at five percent from August 31, 2019 in the amount of $68.49 per day until March 17, 2020, the date of the arbitration award;

• An annual escrow deposit of $500,000 every August 31, beginning on August 31, 2020, until the balance equals $2,000,000;5

• $44,425.00 in American Arbitration Association administrative fees;

• $244,798.57 in compensation and expenses of the arbitrators;

• $138,574.278 in reimbursement to Oxbow for the amount it had deposited with the American Arbitration Association; and

• Interest at the rate of five percent per year post award and post judgment until fully paid.

On April 4, 2020, Oxbow propounded post-judgment discovery on PASE.

On August 7, 2020, Oxbow filed a motion to compel PASE’s post-judgment

discovery responses.

On August 21, 2020, PASE posted a bond of $138,574.28 to suspend

enforcement of the trial court’s final judgment pending appeal. PASE filed a

notice of appeal the next day.6 On October 14, 2020, Oxbow filed a motion to

increase the amount of security, asserting that the bond was insufficient to

5 The escrow payments “relate[] to PASE’s ongoing obligation under the HEA and [the arbitration award] to ‘expeditious[ly]’ dismantle and remove its Steam Production Facility (which adjoins Oxbow’s Port Arthur facility).” 6 PASE states in its motion that it is appealing the arbitration panel’s escrow ruling “on multiple grounds.”

3 supersede the judgment of $1,185,345.99.7 In its motion, Oxbow asked the trial

court to order PASE to post an additional bond of $1,046,771.71. PASE filed a

response, and the motion to increase the amount of security was heard on

November 18, 2020. On November 24, 2020, the trial court signed an Order

Increasing Amount of Security to Supersede Judgment (the “supersedeas order”),

stating in pertinent part:

The security [PASE] must post to supersede the [j]udgment is increased by the amount of $1,068,708.69 and the deadline to supersede the [j]udgment with this increased amount shall be March 1, 2021. The amount of the supersedeas bond shall increase by $500,000.00 on August 31, 2021, and by $500,000.00 on August 31, 2022.

The order also required PASE to respond to certain post-judgment discovery. On

December 31, 2020, PASE filed in this Court its Motion to Review Supersedeas

Order.

In its motion, PASE asserts that the $138.574.28 bond it posted was a

sufficient bond because (1) Oxbow was not awarded compensatory damages in the

trial court’s judgment, (2) the security amount bears no relationship to any

potential loss Oxbow could incur while PASE’s appeal is pending, and (3) ordering

the additional security will cause PASE substantial economic harm and hinder its

7 Oxbow asserts that the trial court’s judgment comprises the $500,000 escrow payment due on August 31, 2019, the $500,000 escrow payment due on August 31, 2020, $13,629.51 in pre-award interest on the $500,000 August 31, 2019 escrow payment, $138,574.28 in arbitration administrative fees and expenses and compensation, and $33,142.40 in post-award and post-judgment interest.

4 ability to pursue its appeal and other litigation with Oxbow. PASE also asserts that

it should not have to respond to the requested post-judgment discovery. In

response to PASE’s motion, Oxbow asserts that (1) the escrow-payment awards

are compensatory damages and therefore the trial court’s supersedeas order

correctly required PASE to pay an additional $1,068,708.69 to supersede the

court’s judgment, (2) even if the escrow payments are not compensatory damages,

requiring security for them is still proper, (3) the supersedeas order is not excessive

and does not cause PASE substantial economic harm, and (4) this Court lacks

jurisdiction over PASE’s appeal of the trial court’s post-judgment discovery ruling.

Standard of Review

A trial court’s ruling on the amount of supersedeas bond is reviewed for an

abuse of discretion. Eagle Oil & Gas Co. v. Shale Expl., LLC, 510 S.W.3d 92, 94

(Tex. App.—Houston [1st Dist.] 2016, order); EnviroPower, L.L.C. v. Bear,

Stearns & Co., Inc., 265 S.W.3d 1, 2 (Tex. App.—Houston [1st Dist.] 2008, order).

To survive an abuse-of-discretion challenge, the evidence must be legally and

factually sufficient to support the trial court’s ruling. G.M. Houser, Inc. v.

Rodgers, 204 S.W.3d 836, 840 (Tex. App.—Dallas 2006, no pet.). “The test for

whether a trial court abused its discretion is whether the trial court acted arbitrarily

or unreasonably in light of all the circumstances of the case.” EnviroPower, 265

S.W.3d at 2. Upon a finding that the trial court abused its discretion, this Court has

5 the authority to order the amount of the security increased or decreased, but if

increased, it must be an amount not to exceed the lesser of fifty percent of the

judgment debtor’s net worth or $25,000,000. TEX. CIV. PRAC. & REM. CODE ANN.

§ 52.006; TEX. R. APP. P. 24.2, 24.4.

Discussion

Free access — add to your briefcase to read the full text and ask questions with AI

Port Arthur Steam Energy, L.P. v. Oxbow Calcining LLC, (Tex. Ct. App. 2021).

Port Arthur Steam Energy, L.P. v. Oxbow Calcining LLC (Port Arthur Steam Energy, L.P. v. Oxbow Calcining LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Flores v. Millennium Interests, Ltd.
185 S.W.3d 427 (Texas Supreme Court, 2005)
G.M. Houser, Inc. v. Rodgers
204 S.W.3d 836 (Court of Appeals of Texas, 2006)
ENVIROPOWER, LLC v. Bear, Stearns & Co., Inc.
265 S.W.3d 1 (Court of Appeals of Texas, 2008)
Smith v. Texas Farmers Insurance Co.
82 S.W.3d 580 (Court of Appeals of Texas, 2002)
In re Nalle Plastics Family Ltd. Partnership
406 S.W.3d 168 (Texas Supreme Court, 2013)
Wal-Mart Stores, Inc. v. Forte
497 S.W.3d 460 (Texas Supreme Court, 2016)
Eagle Oil & Gas Co. v. Shale Exploration, LLC
510 S.W.3d 92 (Court of Appeals of Texas, 2016)
Huff Energy Fund, L.P. v. Longview Energy Co.
510 S.W.3d 479 (Court of Appeals of Texas, 2014)