Pootz v. Quinn

28 N.W.2d 886, 318 Mich. 496, 1947 Mich. LEXIS 424
CourtMichigan Supreme Court
DecidedJune 27, 1947
DocketDocket No. 54, Calendar No. 43,687.
StatusPublished

This text of 28 N.W.2d 886 (Pootz v. Quinn) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pootz v. Quinn, 28 N.W.2d 886, 318 Mich. 496, 1947 Mich. LEXIS 424 (Mich. 1947).

Opinion

Butzel, J.

Plaintiffs are partners in the restaurant business in the city of Grand Rapids. In Octo *498 ber, 1945, plaintiff Norma Werner acquired certain property in that city upon which was located an old house and a streetcar diner. Plaintiffs desired to convert the premises into a cafeteria and, accordingly, they entered into negotiations for the necessary repairs and alterations with the defendant, a contractor and a personal friend of plaintiff Werner. On November 9, 1945, a written contract was signed by defendant and Norma Werner wherein the defendant agreed to perform the necessary Work and supply the required materials for a “total cash price” of $2,350. The contract was prepared on a form bearing the letterhead of defendant and was written in defendant’s own hand. The blank lines of a provision reading, “To be paid by you according to the following terms-,” were not filled in, nor was any other provision made therein as to the time or terms of payment. It is undisputed that certain additional items were requested by plaintiffs after tbe signing of this contract as the result of which the parties agreed on November 16, 1945, to increase the total contract price by $150.

Defendant undertook to do the necessary work and from time to time, as the work progressed, requested advances of money from plaintiffs. Prom November 13, 1945, to December 26, 1945, six payments were made totaling $2,457. Subsequently, defendant informed plaintiffs that he would be unable to complete the project at the contract price. After some discussion, a supplemental agreement was entered into on December 29, 1945, the purpose of which was to include in one overall sum the balance remaining on the old contract plus the,price of certain additional items requested by plaintiffs since the previous readjustment. At that time plaintiffs paid defendant the sum of $259. The *499 supplemental agreement, which was drawn by plaintiff Werner on the back of a menu card and signed by defendant, contained the following:

“Disregard money balance on old contract
Total finish (sic) job, everything included, the above mentioned and according to old contract is $700 Seven Hundred Dollars.
Balance $450.
Signed,
12/29/1945 Ray Quinn. ’ ’

An additional $250 was paid defendant on January 4, 1946, leaving a final balance of $200. On January 10, 1946, defendant requested that plaintiffs advance him the further sum of $200 with which to meet his payroll. Upon plaintiffs’ refusal to advance this sum, defendant walked off the job taking some construction materials with him. On January 11, 1946, plaintiffs obtained a temporary injunction restraining defendant from removing any more materials from the premises. They also filed the bill of complaint in the instant suit seeking to have the temporary injunction made permanent, asking damages for defendant’s failure to complete the job, and further requesting that the court order defendant to pay wages due workingmen employed by him on this project.

Defendant filéd an answer and cross bill, claiming that although the contract was silent as to the time and terms of payment, nevertheless, it was agreed that plaintiffs were to advance the necessary funds to carry on the job; that he was ready and willing to complete the work, but that plaintiffs breached the contract by refusing to' advance the sum of money requested of them on January 10, 1946; and that plaintiffs further prevented him from completing- the job by locking him out of the premises. He *500 admitted that he owed wages to his carpenters for work performed on the project but stated that this had resulted from plaintiffs’ refusal to make payments to him as promised. Pie asked that the injunction be quashed, that he be permitted to obtain possession of his own property on the premises, and that plaintiffs be required to pa'y whatever sum the court should determine w*as due him.

Plaintiffs testified that after the supplemental agreement of December 29, 1945, was entered into, they made no requests of defendant for further changes or alterations. This is denied by the defendant. Plaintiff Pootz testified that it had been necessary to spend more than $600 to prepare the premises for occupancy after defendant abandoned the job. The contractor who had been engaged by plaintiffs to complete the' work testified that in his opinion an additional $240 would be required to finish the job properly. On cross-examination defendant made the following statement:

“It is possible that if I had finished the job it would have taken more than $200 tp do it. After I had used this $200 I contemplated getting more money from her to finish the job. I don’t know what I would have done if she hadn’t paid me more money than was agreed to at the time I entered into this second contract of $700. I didn’t get that far. I went off this job because she did not do as she had agreed to — to furnish money for everything that was needed.”

Defendant further testified that he had since paid off all of the carpenters and that there were no lumber bills outstanding.

The trial court found that the parties, by their conduct, had placed their own interpretation upon the agreement and that 'the evidence established that it was agreed before the work was started that the necessary funds would be furnished by plaintiffs *501 to carry on the job. The court held that plaintiffs had breached their agreement with the defendant by failing to advance the sum of $200, requested by defendant on January 10, 1946; that defendant was therefore justified in quitting the job, and that by so doing he did not lose his right to recover under the agreement with plaintiffs, nor was he liable for the added cost of completing the job. The court further found that at plaintiffs’ request defendant had installed certain glass in the dining car which was not included in the agreement and which had cost defendant $75. A decree was entered dismissing plaintiffs’ bill of complaint and awarding defendant the sum of $279 (the court apparently intended $275). The decree directed plaintiffs to surrender to defendant any and all items of defendant’s personal property in their possession. Plaintiffs appeal from that decree.

It is defendant’s contention on appeal that this Court is without jurisdiction in the case because appellants did not procure and file a certificate of the court stenographer and, further, that there was no extension of time within 20 days following notice of entry of the decree. The court rule provides that:

‘ ‘ The party desiring an extension shall produce a transcript of the testimony necessary to the preparation of a bill of exceptions or a settled case, or a certificate from the stenographer of the trial court stating that appellant has ordered a transcript of the testimony necessary for the preparation of a bill of exceptions or settled case, that payment therefor has been made or secured, and that the same will be furnished as soon as possible by said stenographer.” Court Eule No. 66, § 2 (1945).

In Andres v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Michigan Bean Co. v. Burrell Engineering & Construction Co.
11 N.W.2d 12 (Michigan Supreme Court, 1943)
Andres v. Washtenaw Circuit Judge
283 N.W. 630 (Michigan Supreme Court, 1938)
Wallace v. Sortor
17 N.W. 794 (Michigan Supreme Court, 1883)
Brevoort v. Wayne Circuit Judge
169 N.W. 224 (Michigan Supreme Court, 1918)
Reynick v. Saginaw Circuit Judge
178 N.W. 40 (Michigan Supreme Court, 1920)

Cite This Page — Counsel Stack

Bluebook (online)
28 N.W.2d 886, 318 Mich. 496, 1947 Mich. LEXIS 424, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pootz-v-quinn-mich-1947.