POLO A. PLUMBING & HEATING VS. CONRAIL DEVELOPERS LIMITED LIABILITY COMPANY (L-3656-16, MIDDLESEX COUNTY AND STATEWIDE)
Opinion
NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION This opinion shall not "constitute precedent or be binding upon any court ." Although it is posted on the internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.
SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION
DOCKET NO. A-0171-18T2
POLO A. PLUMBING & HEATING, INC.,
Plaintiff-Respondent,
v.
CONRAIL DEVELOPERS LIMITED LIABILITY COMPANY, a New Jersey Limited Liability Company,
Defendant-Appellant/
Third-Party Plaintiff,
and
WELLNESS and BEAUTY INC., d/b/a MOSAIC WELLNESS and BEAUTY and EKATERINA ST. ONGE,
Third-Party Defendants.
Submitted May 11, 2020 – Decided August 3, 2020 Before Judges Messano and Ostrer.
On appeal from the Superior Court of New Jersey, Law Division, Middlesex County, Docket No. L-3656-16.
Shamy, Shipers & Lonski, PC, attorneys for appellant (Darren M. Pfeil, of counsel; Robert J. MacNiven, on the briefs).
Robbins and Robbins, LLP, attorneys for respondent (Spencer B. Robbins, on the brief).
PER CURIAM Defendant Conrail Developers, LLC, is a general contractor that subcontracted with plaintiff, Polo A. Plumbing & Heating, Inc., to perform plumbing work at a construction project in Woodbridge. Originally, defendant's principal, Ralph Mocci, also the principal of the property's corporate owner, envisioned commercial spaces on the first floor of the proposed building and office space on the second. However, third-party defendant Ekaterina St. Onge, who owned and ran several day spas, decided to lease the second floor to operate a spa and salon of her design.
It is undisputed that plaintiff prepared two contracts, both dated June 6, 2012, to supply labor for the necessary plumbing, and the parties executed both contracts. The first, executed on July 5, 2012, was for a total of $14,000 , and contained a payment schedule that tracked plaintiff's completion of certain work items after an initial deposit of $3000. The second contract, executed more than
A-0171-18T2
six months later on January 29, 2013, was for a total of $32,000, and contained significantly more work items. Defendant was to pay a $5000 deposit, and, again, the balance of payment was tied to plaintiff's completion of various stages of the work. The contracts excluded all plumbing fixtures, any cutting, repairing or removal of the concrete slab for both floors, and any natural gas piping.
Plaintiff did not begin work until after the second contract was executed .
In February 2013, defendant made two separate payments to plaintiff of $3000 and $5000, the deposit amounts under each contract. Defendant made additional payments of $2000, the amount due upon completion of the "slab" under the first contract, and $6000, the amount due upon completion of the slab under the second contract, on May 16 and May 22, 2013, respectively.
Plaintiff claimed that it continued to work in accordance with the two contracts. Its principal, Anthony Polonio, testified there were delays in the project attributable to defendant, such that plaintiff could not continue its work after March 2014. This was corroborated to some degree by St. Onge. She testified that after plaintiff had installed the rough plumbing, other contractors working for defendant installed wall studs that were "crooked" and misplaced. New cuts in the slab had to be made to address the situation.
A-0171-18T2
In June 2014, defendant tendered two checks, partial payments for the next amounts due under each contract "after rough" plumbing was complete. Ultimately, plaintiff sought assurances that defendant would make full payment on the outstanding balances on the two contracts, $8000, plus extra charges of $1750 for roof drains plaintiff already installed, before plaintiff would return to the job site.
The record reveals a series of emails and letters exchanged between plaintiff and defendant in attempts to reach an accommodation. The testimony at trial from Polonio and Mocci diverged. Defendant contended the partial payment was made because plaintiff gave assurances it would return to the site and complete all the rough plumbing, and, there were documents in the record supporting plaintiff's commitment. Polonio claimed he wanted assurances the outstanding balance for work already done would be promptly paid before he sent a work crew back to the site. He asserted that defendant still did not have all the necessary supplies available to complete the job.
On July 24, 2014, defendant's attorney sent plaintiff a letter acknowledging there were two "contracts total[ing] $51,150[] and payments
A-0171-18T2
totaling $29,150[] ha[d] already been made."1 Counsel advised plaintiff that it would be paid upon completion of the rough plumbing in accordance with the contracts and established procedure, but not in advance of its return to the site. Counsel told plaintiff unless it returned to the jobsite within two days, defendant would declare a breach of the contracts. When plaintiff failed to return, counsel sent a second letter terminating the contracts.
Plaintiff filed suit. It claimed that defendant owed $9750 for work that plaintiff completed for which defendant had not paid. Defendant answered and counterclaimed, alleging that it incurred additional expense to fix substandard work plaintiff had already performed and to complete work that remained unfinished. Defendant filed a third-party complaint against St. Onge and her business entities, seeking contribution and indemnification against plaintiff's claim.
The case was tried without a jury. A critical issue at trial was whether there were two separate contracts, as plaintiff contended, or whether the second contract replaced the first, as defendant argued. Another point of contention
1 Polonio claimed there might have been extras that accounted for this difference from the sum of the original contract amounts, but except for $1750 for roof drains, he could not specifically recall. Defense counsel's letter accurately reflected the amount of money defendant had paid to plaintiff.
A-0171-18T2
was whether plaintiff had performed all the work under both contracts to that point and was due payment for having completed the "rough" plumbing.
Defendant asserted there was only one contract and that plaintiff breached the contract by failing to perform. Defendant introduced evidence that it paid other contractors more than $30,000 to correct plaintiff's unprofessional work.
The judge issued an oral opinion in plaintiff's favor and entered judgment for plaintiff in the amount of $7250, plus pre-judgment interest. She also dismissed defendant's counterclaim and third-party complaint against St. Onge. 2 The judge subsequently denied defendant's motion for reconsideration, and this appeal followed. 3 Before us, defendant contends the verdict was "clearly against the weight of the evidence." Defendant also contends that it established plaintiff breached the contract and failed to mitigate defendant's damages. Defendant urges us to vacate the judgment and remand the matter for a new trial. We have considered these arguments and affirm.
2 Defendant does not appeal the dismissal of its third-party complaint.
3 We only have defendant's notice of motion for reconsideration, which did not request oral argument, and the judge's order denying the motion. The order contains no written statement of reasons.
A-0171-18T2
Rule 2:10-1 provides: "In both civil and criminal actions, the issue of whether a jury verdict was against the weight of the evidence shall not be cognizable on appeal unless a motion for a new trial on that ground was made in the trial court." (Emphasis added). A challenge to a verdict as being against the weight of the evidence is inapplicable to a bench trial. Fanarjian v. Moskowitz, 237 N.J. Super. 395, 406 (App. Div. 1989).
Instead, we review defendant's argument using the proper standard of review following a non-jury trial.
Free access — add to your briefcase to read the full text and ask questions with AI
POLO A. PLUMBING & HEATING VS. CONRAIL DEVELOPERS LIMITED LIABILITY COMPANY (L-3656-16, MIDDLESEX COUNTY AND STATEWIDE) (POLO A. PLUMBING & HEATING VS. CONRAIL DEVELOPERS LIMITED LIABILITY COMPANY (L-3656-16, MIDDLESEX COUNTY AND STATEWIDE)) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.