POLO A. PLUMBING & HEATING VS. CONRAIL DEVELOPERS LIMITED LIABILITY COMPANY (L-3656-16, MIDDLESEX COUNTY AND STATEWIDE)

CourtNew Jersey Superior Court Appellate Division
DecidedAugust 3, 2020
DocketA-0171-18T2
StatusUnpublished

This text of POLO A. PLUMBING & HEATING VS. CONRAIL DEVELOPERS LIMITED LIABILITY COMPANY (L-3656-16, MIDDLESEX COUNTY AND STATEWIDE) (POLO A. PLUMBING & HEATING VS. CONRAIL DEVELOPERS LIMITED LIABILITY COMPANY (L-3656-16, MIDDLESEX COUNTY AND STATEWIDE)) is published on Counsel Stack Legal Research, covering New Jersey Superior Court Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
POLO A. PLUMBING & HEATING VS. CONRAIL DEVELOPERS LIMITED LIABILITY COMPANY (L-3656-16, MIDDLESEX COUNTY AND STATEWIDE), (N.J. Ct. App. 2020).

Opinion

NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION This opinion shall not "constitute precedent or be binding upon any court ." Although it is posted on the internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.

SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION DOCKET NO. A-0171-18T2

POLO A. PLUMBING & HEATING, INC.,

Plaintiff-Respondent,

v.

CONRAIL DEVELOPERS LIMITED LIABILITY COMPANY, a New Jersey Limited Liability Company,

Defendant-Appellant/ Third-Party Plaintiff,

and

WELLNESS and BEAUTY INC., d/b/a MOSAIC WELLNESS and BEAUTY and EKATERINA ST. ONGE,

Third-Party Defendants. ________________________________

Submitted May 11, 2020 – Decided August 3, 2020

Before Judges Messano and Ostrer. On appeal from the Superior Court of New Jersey, Law Division, Middlesex County, Docket No. L-3656-16.

Shamy, Shipers & Lonski, PC, attorneys for appellant (Darren M. Pfeil, of counsel; Robert J. MacNiven, on the briefs).

Robbins and Robbins, LLP, attorneys for respondent (Spencer B. Robbins, on the brief).

PER CURIAM

Defendant Conrail Developers, LLC, is a general contractor that

subcontracted with plaintiff, Polo A. Plumbing & Heating, Inc., to perform

plumbing work at a construction project in Woodbridge. Originally, defendant's

principal, Ralph Mocci, also the principal of the property's corporate owner,

envisioned commercial spaces on the first floor of the proposed building and

office space on the second. However, third-party defendant Ekaterina St. Onge,

who owned and ran several day spas, decided to lease the second floor to operate

a spa and salon of her design.

It is undisputed that plaintiff prepared two contracts, both dated June 6,

2012, to supply labor for the necessary plumbing, and the parties executed both

contracts. The first, executed on July 5, 2012, was for a total of $14,000 , and

contained a payment schedule that tracked plaintiff's completion of certain work

items after an initial deposit of $3000. The second contract, executed more than

A-0171-18T2 2 six months later on January 29, 2013, was for a total of $32,000, and contained

significantly more work items. Defendant was to pay a $5000 deposit, and,

again, the balance of payment was tied to plaintiff's completion of various stages

of the work. The contracts excluded all plumbing fixtures, any cutting, repairing

or removal of the concrete slab for both floors, and any natural gas piping.

Plaintiff did not begin work until after the second contract was executed .

In February 2013, defendant made two separate payments to plaintiff of $3000

and $5000, the deposit amounts under each contract. Defendant made additional

payments of $2000, the amount due upon completion of the "slab" under the first

contract, and $6000, the amount due upon completion of the slab under the

second contract, on May 16 and May 22, 2013, respectively.

Plaintiff claimed that it continued to work in accordance with the two

contracts. Its principal, Anthony Polonio, testified there were delays in the

project attributable to defendant, such that plaintiff could not continue its work

after March 2014. This was corroborated to some degree by St. Onge. She

testified that after plaintiff had installed the rough plumbing, other contractors

working for defendant installed wall studs that were "crooked" and misplaced.

New cuts in the slab had to be made to address the situation.

A-0171-18T2 3 In June 2014, defendant tendered two checks, partial payments for the

next amounts due under each contract "after rough" plumbing was complete.

Ultimately, plaintiff sought assurances that defendant would make full payment

on the outstanding balances on the two contracts, $8000, plus extra charges of

$1750 for roof drains plaintiff already installed, before plaintiff would return to

the job site.

The record reveals a series of emails and letters exchanged between

plaintiff and defendant in attempts to reach an accommodation. The testimony

at trial from Polonio and Mocci diverged. Defendant contended the partial

payment was made because plaintiff gave assurances it would return to the site

and complete all the rough plumbing, and, there were documents in the record

supporting plaintiff's commitment. Polonio claimed he wanted assurances the

outstanding balance for work already done would be promptly paid before he

sent a work crew back to the site. He asserted that defendant still did not have

all the necessary supplies available to complete the job.

On July 24, 2014, defendant's attorney sent plaintiff a letter

acknowledging there were two "contracts total[ing] $51,150[] and payments

A-0171-18T2 4 totaling $29,150[] ha[d] already been made."1 Counsel advised plaintiff that it

would be paid upon completion of the rough plumbing in accordance with the

contracts and established procedure, but not in advance of its return to the site.

Counsel told plaintiff unless it returned to the jobsite within two days, defendant

would declare a breach of the contracts. When plaintiff failed to return, counsel

sent a second letter terminating the contracts.

Plaintiff filed suit. It claimed that defendant owed $9750 for work that

plaintiff completed for which defendant had not paid. Defendant answered and

counterclaimed, alleging that it incurred additional expense to fix substandard

work plaintiff had already performed and to complete work that remained

unfinished. Defendant filed a third-party complaint against St. Onge and her

business entities, seeking contribution and indemnification against plaintiff's

claim.

The case was tried without a jury. A critical issue at trial was whether

there were two separate contracts, as plaintiff contended, or whether the second

contract replaced the first, as defendant argued. Another point of contention

1 Polonio claimed there might have been extras that accounted for this difference from the sum of the original contract amounts, but except for $1750 for roof drains, he could not specifically recall. Defense counsel's letter accurately reflected the amount of money defendant had paid to plaintiff. A-0171-18T2 5 was whether plaintiff had performed all the work under both contracts to that

point and was due payment for having completed the "rough" plumbing.

Defendant asserted there was only one contract and that plaintiff breached

the contract by failing to perform. Defendant introduced evidence that it paid

other contractors more than $30,000 to correct plaintiff's unprofessional work.

The judge issued an oral opinion in plaintiff's favor and entered judgment

for plaintiff in the amount of $7250, plus pre-judgment interest. She also

dismissed defendant's counterclaim and third-party complaint against St. Onge. 2

The judge subsequently denied defendant's motion for reconsideration, and this

appeal followed. 3

Before us, defendant contends the verdict was "clearly against the weight

of the evidence." Defendant also contends that it established plaintiff breached

the contract and failed to mitigate defendant's damages. Defendant urges us to

vacate the judgment and remand the matter for a new trial. We have considered

these arguments and affirm.

2 Defendant does not appeal the dismissal of its third-party complaint.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mountain Hill, LLC v. Tp. of Middletown
945 A.2d 59 (New Jersey Superior Court App Division, 2008)
Cesare v. Cesare
713 A.2d 390 (Supreme Court of New Jersey, 1998)
State v. Locurto
724 A.2d 234 (Supreme Court of New Jersey, 1999)
Matter of Trust Created by Agreement Dated December 20, 1961
944 A.2d 588 (Supreme Court of New Jersey, 2008)
Fanarjian v. Moskowitz
568 A.2d 94 (New Jersey Superior Court App Division, 1989)
State v. Barone
689 A.2d 132 (Supreme Court of New Jersey, 1997)
New Jersey Division of Youth & Family Services v. M.M.
914 A.2d 1265 (Supreme Court of New Jersey, 2007)
Seidman v. Clifton Savings Bank
14 A.3d 36 (Supreme Court of New Jersey, 2011)
Lisa Llewelyn v. James Shewchuk
111 A.3d 1132 (New Jersey Superior Court App Division, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
POLO A. PLUMBING & HEATING VS. CONRAIL DEVELOPERS LIMITED LIABILITY COMPANY (L-3656-16, MIDDLESEX COUNTY AND STATEWIDE), Counsel Stack Legal Research, https://law.counselstack.com/opinion/polo-a-plumbing-heating-vs-conrail-developers-limited-liability-company-njsuperctappdiv-2020.