CHARLES R. JONES, Judge.

|, This matter is before the Court pursuant to an order of remand by the Supreme Court dated November 5, 2010. The order directs this Court to reconsider the merits of these1 writ applications in view of the district court’s May 26, 2010 order granting approval of a settlement class. After a review of the issues herein, we reverse and remand with instructions.

The facts underlying this matter are discussed at length in appeal No. 2008-CA-1486.2 The scope of our review in the appeal concerned the judgment of the district court denying class certification in this toxic tort case. The denial of class certification by the district court was based on the recommendations made by the Special Master, who was appointed by the district court. Ultimately, this Court affirmed the judgment of the district court denying class certification on January 28, 2010.

|2On February 19, 2010, an emergency writ application, No. 2010-C-0250, also entitled Leo Pollard, et al v. Alpha Technical, et al., was filed by the Earl Adams, et al., plaintiffs (the Adams plaintiffs) in reference to the same toxic tort litigation. The Adams plaintiffs alleged therein that the district court, on January 11, 2010, rendered judgment granting the motion for Preliminary Approval of Class Settlement urged by the Plaintiffs’ Management Committee (the respondents) which purported to include certain litigants. Particularly, in the writ application, we were presented with a disputed preliminary class settlement, but there was no “class,” as determined by the district court and affirmed by this Court on appeal. However, as reflected in the January 11, 2010 ex parte order attached to the writ application, the district court had in fact approved a class settlement that had been requested by the Plaintiffs’ Management Committee. We also noted that while the district court purportedly approved the motion for Preliminary Approval of Class Settlement on January 11, 2010, the district court had been clearly divested of jurisdiction. In our disposition, this Court: (1) granted a stay of proceedings related to the rendering of judgment granting the motion for Preliminary Approval of Class Settlement pending the finality of the appeal, and (2) vacated the district court’s rulings on the motion for new trial and remanded the matter for the district court’s reconsideration.

Subsequently, in the instant consolidated writ applications, 2010-C-0788, and 2010-C-0805, the Adams plaintiffs (and the Mitchell plaintiffs, respectively) alleged that while the motion for new trial was before the district court for reconsideration, counsel for the Plaintiffs’ Management Committee re-urged the identical motion for Preliminary Approval of Class Settlement and, that same was |sonce again approved by the district court via written [75]*75judgment and reasons dated May 26, 2010, followed by the detailed order dated May 28, 2010.

In its May 26, 2010, judgment and written reasons, the district court wrote in pertinent part:

JUDGMENT AND REASONS FOR JUDGMENT
This matter came for hearing on May 26, 2010 on the Motion for New Trial filed on behalf of Defendant Intracoastal Tubular Service, on Motion for New Trial with Motion to Set Aside, Vacate and Annul Preliminary Order filed on behalf of Earl Adams, et al. Plaintiffs, and on Motion to Set Aside Judgment and for New Trial filed on behalf of Pamela Mitchell, Melvin Lewis, Rose Benjamin, Rev. Johnny McKinnis, Rev. Calton Lewis and Rev. Jerry Davis, Sr. Additionally, the Court heard argument on the Plaintiff Management Committee and Settling Defendants Joint Motion to Re-Urge Joint Motion for Preliminary Approval of Settlement and Certification of Settlement Class and to Amend January 11, 2010 Order to Re-Set Deadlines, Objections to Preliminary Approval of the Settlement and Certification of the Settlement, and Supplemental Objections to Motion to Re-Urge Preliminary Approval of Settlement Class and to Amend Deadlines for Opting Out.
⅜ ⅜ ⅜ ⅜ ⅜ ⅜
The Court after considering the law, evidence and argument of counsel, renders judgment as follows:
IT IS ORDERED, ADJUDGED AND DECREED that Intracostal Tubular Service’s Motion for New Trial is DENIED.
IT IS ORDERED, ADJUDGED AND DECREED that Plaintiffs Pamela Mitchell, Melvin Lewis, Rose Benjamin, Rev. Johnny McKinnis, Rev. Calton Lewis, and Rev. Jerry Davis, Sr.’s Motion For New Trial is DENIED.
IT IS ORDERED, ADJUDGED AND DECREED that Earl Adams, et al. Plaintiffs’ Motion for New Trial with Motion to Set Aside, Vacate and Annul Preliminary Order on the Grounds of ill Practice, Denial of Due Process and Fraud Upon the Court is DENIED.
|JT IS ORDERED, ADJUDGED AND DECREED that Earl Adams, et al Plaintiffs’ Objections to Preliminary Approval of Settlement and Certification of Settlement Class are DENIED.
IT IS ORDERED, ADJUDGED AND DECREED that Earl Adams, et al Plaintiffs’ Supplemental Objections to the Motion To Re-Urge Preliminary Approval of the Settlement Class and to Amend Deadlines for Opting out is DENIED.
IT IS ORDERED, ADJUDGED AND DECREED that Plaintiff Management Committee and Settling Defendants’ Joint Motion to Re-Urge Joint Motion for Preliminary Approval of Settlement and Certification of Settlement Class and to Amend January 11, 2010 Order to Re-Set Deadlines is GRANTED.
The two-step approach for approval of a settlement class is laid out in Gates v. Rohm & Haus [Haas] Co., 248 F.R.D. 434, 438-489 (E.D.Pa.2008), Armstrong v. B.Q. [Board] of School Dirs., 616 F.2d 305, 314 (7 Cir.1980), overruled on other grounds by Felzen v. Andreas, 134 F.3d 873 (7 Cir.1998); In re Mid-Atlantic Toyota Antitrust Litig., 564 F.Supp. 1379, 1384 (D.Md.1983); Horton v. Merrill Lynch, Pierce Fenner & Smith, Inc., 855 F.Supp. 825, 827 (E.D.N.C.1994). First, the Court issues a preliminary approval of the settlement, where the court reviews the proposed settlement [76]*76for obvious deficiencies, schedules a fairness hearing, and provides the class with notice of the proposed settlement and hearing. Second, the court considers the final approval of the proposed settlement at a formal fairness hearing during which arguments and evidence are presented in support of and in opposition to the proposed settlement.
On a motion for preliminary approval the Court need only ascertain whether there is “probable cause” to notify the class members of the proposed settlement and to proceed with a fairness hearing. Mid-Atlantic Toyota, 564 F.Supp. at 1384. When making the preliminary determination of fairness of the settlement, the standard is not whether the settlement was the best of all possible deals, but rather, “whether it is fair, adequate, and free from collusion.” Hunlon [Hanlon] v. Chrysler Corp., 150 F.3d 1011, 1027 (9 Cir.1988) [(9 Cir.1998) ]. When a proposed settlement appears to fall within the range of possible approval, it is appropriate to issue preliminary approval | ¿and direct notice to members of the settlement class. Horton, 855 F.Supp. [825] at 827. Thus, for these reasons the Court preliminarily approves the proposed settlement class.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
102 So. 3d 71, 2011 WL 3587482, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pollard-v-alpha-technical-lactapp-2011.