Polk v. Bartlett

1961 OK 230, 365 P.2d 987, 1961 Okla. LEXIS 438
CourtSupreme Court of Oklahoma
DecidedOctober 3, 1961
Docket39007
StatusPublished
Cited by5 cases

This text of 1961 OK 230 (Polk v. Bartlett) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Polk v. Bartlett, 1961 OK 230, 365 P.2d 987, 1961 Okla. LEXIS 438 (Okla. 1961).

Opinion

WELCH, Justice.

Plaintiff, L. A. Bartlett, d/b/a Bartlett Electric Company, submitted a bid to W. E. Polk, d/b/a Polk Construction Company, defendant, which was accepted. The material portions of said bid reads as follows:

“We wish to submit our figure for the elementary school building, Shidler-Webb City School District, in accordance with the plans and specifications as drawn by W. H. Elliott, Jr. Architect.
“We propose to install the electrical equipment as specified, on a time and material basis not to exceed $8,000.00. All invoices submitted by our office on time and material will be figured as follows: the cost of material plus 10%. overhead and 10% profit, the cost of labor on the same basis.
“The above price of $8,000.00 does not include any intercommunication, public address, or clock system, as the specifications do not cover this phase of the installation. However, on receipt of the information needed to complete the installation of the above mentioned items, we propose to install this equipment on the same basis as mentioned in the above paragraph.
“We hope that this proposal will meet with your approval, and if awarded *989 the contract we shall commence work within a weeks time.
“Respectfully submitted,
Bartlett Electric Company, Inc.
/s/ B. J. Lokey
For L. A. Bartlett.”

Within a few days thereafter plaintiff commenced his work under the terms of sub-contract based on said bid, and in due time the work was completed. The final estimate was paid by defendant’s check, which with three previous payments, totaled exactly $8,000. At about the time of this final estimate, or shortly thereafter, plaintiff submitted to defendant a statement for extras in the amount of $1,032.13 for installation of intercommunication system, P. A. System, or clock system, and the sum of $86.52 for two unit heaters. Defendant refused to pay these sums and as a result this action was filed in the Court of Common Pleas of Tulsa County. It is the contention of the defendant that these installations were included in the contract, and therefore payment for installation was included in the $8,000 payment. Plaintiff contends they were not included in or under the terms of the contract, since they were not included in his bid. Upon examination of the bid, which was the basis of the contract, it was concluded by the trial court that the same was ambiguous and the true intent of the parties could not be determined from the written instrument. As a result thereof extrinsic evidence on behalf of both parties was admitted, and the case was submitted to a jury on its merits. A verdict was returned by the jury for plaintiff against defendant in the sum of $1,032.13, and judgment rendered accordingly. It is from said adverse judgment that defendant prosecutes this appeal.

Defendant’s argument for reversal is presented in his brief under three separate propositions:

First, that the trial court did not have jurisdiction to render a judgment for the reason that plaintiff did not prove or offer any evidence of compliance with the intangible tax laws of the State of Oklahoma.

Second, that the trial court should have construed and interpreted the contract between the parties, and such a construction would have necessarily resulted in the dismissal of plaintiff’s petition. Therefore defendants were entitled to have their demurrer to the evidence sustained, and a directed verdict sustained, or their motion, notwithstanding the verdict, sustained after the verdict.

Third, that the judgment should be reversed for the reason that there is no reasonable evidence tending to support the verdict.

We cannot agree with the argument presented under the second proposition. The first and second paragraphs of the written bid submitted provides that the figure submitted is for installation of electrical equipment in accordance with the plans and specifications as drawn by the architect. Should one ignore the third paragraph it would have been a simple matter of examining the plans and specifications to determine whether the extras were included. However, the third paragraph of said written bid provides that the price of $8,000 quoted did not include any inter-communication, public address or clock system, as the specifications did not cover that phase of the installation. It further provided for installation on basis mentioned in above paragraph. We should construe that to mean on a time and material basis which was a cost plus 10% or 20% basis.

It is apparent to us from the contention of the defendant that he apparently construed the plans and specifications to include the extras referred to, but the plaintiff did not so construe them at the time the bid was made and accepted. Each party offered evidence to support his contention.

Therefore, we are of the opinion the trial court was justified in admitting extrinsic evidence and submitting the case to a jury.

We have consistently held that where the meaning of an ambiguous written contract is in dispute, evidence of extrinsic facts are admissible, and construction of contract then becomes a mixed ques *990 tion of law and fact and should be submitted to a jury under proper instructions. Brogden v. Perryman, 176 Okl. 505, 56 P.2d 398; Swift v. McMurray, 133 Okl. 104, 271 P. 635, and Kershaw v. Reynolds, 124 Okl. 174, 254 P. 713.

Herein plaintiff testified that defendant was orally advised at the time the latter accepted the bid that the bid did not include installation of the system, and defendant said “that is right, we will take that up later.” This evidence, together with consideration of the third paragraph of the written bid, and the reasonable inferences that may be drawn therefrom, is sufficient evidence to justify submitting question to a jury. Allied Reserve Life Insurance Company v. Cunningham, Okl., 355 P.2d 564.

We will not weigh evidence on appeal and where same reasonably tends to prove essential facts the verdict and judgment based thereon will be sustained. Cities Service Oil Company v. Billen, Okl., 347 P. 2d 637.

Therefore, we find defendant’s argument under his third proposition without merit.

We are of the opinion that the argument presented by defendant under his first proposition is meritorious. Plaintiffs in their argument supporting trial court’s holding that proof of payment of intangible tax was unnecessary rely on our holding in the cases of Lumbermen’s Supply Co. v. Neal, 189 Okl. 544, 119 P.2d 1017; Cole v. Harvey, 200 Okl. 564, 198 P.2d 199, and Gasper v. Mayer, 171 Okl. 457, 43 P.2d 467.

We find that these cases are clearly distinguishable from the case at bar. The Gasper case does not involve the intangible tax law, but turns on the question of accord and satisfaction.

In the Lumbermen’s case the plaintiff Neal was employed as store manager of Lumbermen’s at a stated monthly salary, plus 10% of the net earnings of the company to be computed after deducting costs of production, operating expenses, overall costs of doing business and all income taxes and other taxes, etc.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Askins Properties, L.L.C. v. Oklahoma County Assessor
2007 OK 25 (Supreme Court of Oklahoma, 2007)
Harris v. Snell
1967 OK 8 (Supreme Court of Oklahoma, 1967)
Altshuler v. Malloy
1963 OK 243 (Supreme Court of Oklahoma, 1963)
Marten v. Credit Adjustment Service, Inc.
1963 OK 9 (Supreme Court of Oklahoma, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
1961 OK 230, 365 P.2d 987, 1961 Okla. LEXIS 438, Counsel Stack Legal Research, https://law.counselstack.com/opinion/polk-v-bartlett-okla-1961.