Polizzi v. Thibodeaux

35 So. 2d 660, 1948 La. App. LEXIS 488
CourtLouisiana Court of Appeal
DecidedJune 7, 1948
DocketNo. 18795.
StatusPublished
Cited by7 cases

This text of 35 So. 2d 660 (Polizzi v. Thibodeaux) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Polizzi v. Thibodeaux, 35 So. 2d 660, 1948 La. App. LEXIS 488 (La. Ct. App. 1948).

Opinion

This suit involves a claim by plaintiff, who is a building contractor, against the defendants, Mr. and Mrs. M.B. Thibodeaux, on a contract whereby plaintiff undertook to perform certain construction to and repairs on the property of the defendants, located at 4426 Flamingo Street in the Parish of Jefferson. The amount of the contract is $2,590. Plaintiff was paid the sum of $1,500, and the suit is for the alleged balance due of $1,090.

The petition alleges that plaintiff complied with the terms of his contract and completed the work, and that notwithstanding amicable demand the balance due him under the contract has not been paid.

Mrs. Thibodeaux interposed an exception of no right or cause of action which was maintained by the lower court, and she was dismissed from the suit.

Thibodeaux, who will be referred to hereafter as "defendant," made answer in which he denied that the job was fully completed, and alleged that the work which had been performed was not done in a workmanlike manner in accordance with the contractual stipulations.

Defendant assumed the position of plaintiff in reconvention and alleged in that capacity that the cost of completing the contract by a third party would amount to the sum of $2,000, and that deducting therefrom the balance claimed by plaintiff to be due, he, the plaintiff in reconvention, is entitled to a judgment for the difference, or for $910.

After a trial on the merits in the Twenty-Fourth Judicial District Court for the Parish of Jefferson, plaintiff's demands were dismissed, and there was judgment in reconvention in favor of Thibodeaux for the sum of $910. Plaintiff has appealed.

[1] It is well settled that a contractor is entitled to recover for the value of work substantially done by him, even though such work be unfinished or defective, the owner being relegated to a reduction of the price to an amount necessary to correct or complete the work. See Brandin Slate Co. v. Bannister, La. App., 30 So.2d 877, and authorities therein cited.

The contract forming the basis of this suit contains seventeen numbered items, plus the installation of an electric light *Page 662 and switch on the front porch, and also the installation of a feeder line from the butane gas tank to the house, which plaintiff agreed to perform to defendant's building that had been removed from another lot to its present location. Plaintiff obligated himself to furnish all labor and materials in connection with the work.

[2] At the outset, suffice it to say that the plaintiff, notwithstanding the allegation that he had performed his contract, admitted that the job is unfinished and there are several items which he has not performed, and others which, while performed, were not in accordance with the contract. Specifically, he admitted that the contract called for a Johns-Manville hexagonal rubberoid externit asbestos roof, but that he substituted another roof of a different type, which was installed by the Brandin Slate Company. There is a dispute between the parties as to whether defendant agreed to this substitution, but that is of little importance, as there is no question that the defendant, who accepted the substituted roof, is entitled to a credit for the difference in the price of the roof which should have been applied under the contract, and the cost of the substituted roof. Delaney v. John O. Chisolm Co.,166 La. 406, 117 So. 443.

The only testimony in the record which tends to show such difference in the cost between the two roofs is that of Albert Posecai, a carpenter, who testified as a witness for defendant, and his estimation is that the difference in price would be between $40 and $50. On this particular item Posecai's testimony is so vague that we cannot determine therefrom what the exact difference is, and his evidence is not helpful in a determination of the matter.

Polizzi freely admitted on the witness stand that he had quit the job before completion of the contract. He states that Mrs. Thibodeaux "ran" him off the job, hence the noncompletion. On the other hand, Mrs. Thibodeaux testified that Polizzi quit the job because she would not advance him any more money, as he was already overdrawn on the contract. Polizzi first stated that the job could be completed at a cost of $70, but at another point his testimony is that it would cost between $70 and $80.

Several of the contractual items are drawn into dispute. Item 5 covers the construction of a front porch. Polizzi admitted that the porch was not ceiled. Jeffcoat, a carpenter, who appeared as a witness for defendant, estimated it would cost $175 to ceil the porch, while Posecai's estimate was "around $250.00 or $300.00." This latter witness estimated that the porch was only about fifty per cent completed. Posecai, later in his testimony, said that $200.00 would suffice to complete the porch, and in another statement said he did not remember what the cost would be. Mr. and Mrs. Thibodeaux both testified that the screen work on the porch was not done in accordance with the contract, as there were no columns erected and the screens were nailed onto studs without cross pieces. Thibodeaux also claims that the porch has buckled and that a person traversing it could get his shoes caught in the planks.

Item 8 embraces the construction and installation of a cess pool, and plumbing in the house. Jeffcoat's statement is that the installation of a lavatory bowl was incomplete, and M.B. Thibodeaux, Jr., defendant's son, testified that no trap for the bathroom had been installed and that the toilet was stopped up. This latter witness stated that he completed this work himself at a cost of $2.25 for materials.

Item 11 ("Insulate with brick masonite missing pieces over exposed wood work only") and item 16 ("Repair all defected spots on outside of building and porch") may be considered together. Polizzi admits that about three squares of wallhide siding were not installed over exposed woodwork, and that he has not completed this detail. His estimation is that three squares of siding are necessary on the outside of the house. Vincent, who appeared for plaintiff, testified that the job is completed with the exception of three squares of wallhide shingles around the bottom of the house, and that the porch has to be ceiled. Jeffcoat testified that the missing pieces over the exposed woodwork were not installed, and his estimate was that it would cost about $65 to complete it. Mrs. Thibodeaux further complains *Page 663 that no fascia boards were installed. Posecai observed that the siding on the outside was not completed, and he estimated that it would take five squares of siding to do so, but he could not remember how much the cost would be. Thibodeaux, Jr., stated that the brick siding on the outside is incomplete, and that under the contract Polizzi was supposed to place a layer of felt first to protect the wood, and that the siding was to be nailed over the felt.

All parties agree that item 12 ("Renail masonite around building") was not done, and the only estimate as to the cost of completion was given by Jeffcoat, who said it would be around $75.

Under item 13 the contractor was to install a door on the front porch, and the uncontradicted evidence is that the door was installed wrong-side-out, and is now hanging on one hinge as the screws in the other hinge became loose. However, there is no indication whatever as to the cost of correcting the defective door.

Item 14 contemplated the installation of a double window, and Polizzi admits that the sash was never supplied or installed. The only estimate as to cost is by Jeffcoat, whose opinion is that it would take $45 or $50 to complete it.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sherill Smith Bares v. Warren Overton Bares
Louisiana Court of Appeal, 2009
Duplechian v. Sba Network Services, Inc.
980 So. 2d 907 (Louisiana Court of Appeal, 2008)
Terry v. Terry
954 So. 2d 790 (Louisiana Court of Appeal, 2007)
Price v. Huey Childs Builder, Inc.
426 So. 2d 398 (Louisiana Court of Appeal, 1983)
Rathe v. Maher
184 So. 2d 256 (Louisiana Court of Appeal, 1966)
U-Finish Homes, Inc. v. Michel
183 So. 2d 101 (Louisiana Court of Appeal, 1965)
Baker v. Stamps
82 So. 2d 858 (Louisiana Court of Appeal, 1955)
Poche v. Landry
57 So. 2d 808 (Louisiana Court of Appeal, 1952)

Cite This Page — Counsel Stack

Bluebook (online)
35 So. 2d 660, 1948 La. App. LEXIS 488, Counsel Stack Legal Research, https://law.counselstack.com/opinion/polizzi-v-thibodeaux-lactapp-1948.