Plymouth Manufacturing Co. v. United States

86 F. Supp. 134, 114 Ct. Cl. 616, 1949 U.S. Ct. Cl. LEXIS 92
CourtUnited States Court of Claims
DecidedOctober 3, 1949
DocketCongressional No. 17852
StatusPublished
Cited by1 cases

This text of 86 F. Supp. 134 (Plymouth Manufacturing Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Plymouth Manufacturing Co. v. United States, 86 F. Supp. 134, 114 Ct. Cl. 616, 1949 U.S. Ct. Cl. LEXIS 92 (cc 1949).

Opinion

LittletoN, Judge,

delivered the opinion of the court:

The claim of plaintiff herein, for the payment of which a bill H. E. 6499 had been introduced, was referred to this court under 28 U. S. C. 1492, by Eesolution No. 606 of the House of Eepresentatives of the Congress, for a report of the facts and our conclusions thereon “sufficient to inform the Congress of the nature and character of the demand, as a claim legal or equitable, against the United States, and the amount, if any, legally or equitably due from the United States to the claimant.”

Plaintiff corporation has its plant and principal place of busines at McColl, South Carolina. It is and at all times mentioned in the findings was engaged in manufacturing light cotton fabrics, consisting principally of bag sheeting for use in making various kinds of bags.

Pursuant to authority of the National Defense Act of June 3, 1916, as amended by the Act of June 4, 1920 (10 U. S. C. 1193), a representative of the Quartermaster Corps, U. S. Army, made a survey of plaintiff’s plant in January 1940, as described in findings 5 to 11, inclusive. This was a [635]*635part of a general survey of the manufacturing industry for the purposes mentioned in the Acts above referred to, to-wit, the procurement of military supplies in the event of a national emergency. Inspection of plaintiff’s plant was made by Major George C. Wynne, Zone Quartermaster, at Atlanta, Georgia. This inspection covered a period of about two hours during which Wynne was taken over the plant. He talked with plaintiff’s superintendent and Eobert F. Bowe, manager of the gray-goods department of Hesslein & Company, plaintiff’s selling agent (finding 7). The Hesslein Company owned all of plaintiff’s stock.

As set forth in finding 4, Eeeves Brothers, Inc., entered into a contract with the War Department on November 12, 1940, agreeing to furnish 300,000 linear yards of cotton khaki uniform cloth 36 inches wide, known as Army twill, at 30.8 cents per linear yard. Through the activities of Mr. Bowe of Hesslein & Company, as shown in finding 12, the plaintiff, on November 15,1940, entered into a subcontract with Eeeves Brothers in which plaintiff agreed to manufacture and furnish 140,000 yards of this cloth in accordance with the specifications of Eeeves Brothers’ prime contract with the Government. Subsequently, on November 26, 1940, this subcontract was increased to 335,000 yards. Subsequently, on December 2, 1940, Eeeves Brothers entered into another contract with the Government to furnish an additional amount of 310,000 linear yards of 36-inch uniform cloth at 35.41 cents per linear yard, and immediately thereafter, and on the same day, Hesslein & Company, acting for plaintiff, entered into another subcontract with Eeeves Brothers, which cancelled and superseded the subcontract of November 26. In this subcontract of December 2, the amount of cloth which plaintiff agreed to manufacture and furnish Eeeves Brothers was increased to 685,000 linear yams (see findings 3 and 4). The prime contracts between Eeeves Brothers and the Government required that deliveries be made within certain specified periods and provided for the payment of liquidated damages for delay in making such deliveries.

Plaintiff commenced producing the cloth during January 1941, and by March 26, 1941, it had made shipments aggregating 164,000 yards of Army twill to the finishing plant at [636]*636Greenville, South Carolina, for processing. Finding 13. The first shipment containing about 30,000 yards was made about six weeks after the commencement of production. The cloth was inspected by plaintiff’s inspectors at its plant before being shipped to the bleachery at Greenville, and was inspected at Greenville by defendant’s inspectors. Plaintiff’s inspectors determined that from 10 to 12 percent of the cloth manufactured did not meet the specification requirements and such material was taken out and rejected prior to shipment. After the cloth reached the bleachery at Greenville, about 88.5 percent of that received was rejected by defendant’s inspectors because of its failure to meet the specification requirements. Of a total of 467,801 yards shipped by plaintiff to the bleachery at Greenville, only 53,973 yards were accepted. Finding 15.

For the reasons set forth in findings 16 to 22, inclusive, plaintiff was unable to manufacture cloth that would meet the specifications of its subcontract with Reeves Brothers. As a result of plaintiff’s inability to manufacture cloth meeting the requirements of the specifications, Reeves Brothers, the prime contractor, obtained such cloth elsewhere at a cost in excess of the contract price at which plaintiff agreed to manufacture and deliver such cloth. Plaintiff’s total loss as a result of its undertaking to manufacture the Army twill, after allowance of amounts received by plaintiff from the sale of rejected material on hand, amounted to $73,048.46. This amount includes the excess cost paid by plaintiff to Reeves Brothers, the prime contractor, through plaintiff’s parent company, Hesslein & Company, of $36,373.30, and liquidated damages paid to Reeves Brothers by plaintiff in the sum of $36,675.16. As shown in finding 23, Reeves Brothers conditionally waived payment by plaintiff to it of $6,483 of the total liquidated damages which it (Reeves Brothers) had to pay to the Government. This last mentioned amount of $6,483 is included by plaintiff in its claim here by reason of the terms and conditions of its settlement agreement with Reeves Brothers.

Plaintiff’s claim is not within the general jurisdiction of this court for the reason that there was no privity of contract between the defendant and the plaintiff, a subcontractor.

[637]*637We are of opinion, from the facts disclosed by the evidence of record, that plaintiff does not have a legal or equitable claim against the United States for the payment of all or any part of the loss sustained by it under its subcontracts with Reeves Brothers, Inc. Plaintiff predicates its claim that Congress should reimburse it for its total loss of $79,531.46, primarily upon the ground that the defendant, through Major George C. Wynne, an authorized and designated officer, represented to plaintiff in the letter schedule of production, dated August 27,1940 (set forth in finding 9), that plaintiff’s plant could manufacture a herringbone twill cloth of carded cotton thread woven two up and one down, and otherwise described in said letter schedule. In other words, plaintiff alleges misrepresentations by the defendant that plaintiff’s plant was equipped and capable of manufacturing the Army twill fabric called for in the prune contracts of Reeves Brothers with the Government. In our opinion the record does not support this claim of the plaintiff. The facts show that Major Wynne had had no experience in textile manufacturing and was not an expert on the capacity of looms in the manufacture of cotton fabric, and plaintiff had no reasonable cause to believe that he was representing or making a decision that plaintiff’s plant was capable of satisfactorily manufacturing the herringbone twill fabric referred to by him at the time of his inspection of plaintiff’s plant, and in the letter of August 27,1940.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Florida Power Corp. v. United States
33 Fed. Cl. 107 (Federal Claims, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
86 F. Supp. 134, 114 Ct. Cl. 616, 1949 U.S. Ct. Cl. LEXIS 92, Counsel Stack Legal Research, https://law.counselstack.com/opinion/plymouth-manufacturing-co-v-united-states-cc-1949.