This text of 194 F.2d 859 (Plotnick v. Pennsylvania Smelting & Refining Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Plotnick v. Pennsylvania Smelting & Refining Co., 194 F.2d 859, 1952 U.S. App. LEXIS 2852 (3d Cir. 1952).

Opinion

HASTIE, Circuit Judge.

This litigation arises out of an installment contract for the sale of quantities of battery lead by a Canadian seller to- a Pennsylvania buyer. The seller sued for the price of a carload of lead delivered but not paid for. The buyer counterclaimed for damages caused by the seller’s failure to deliver the remaining installments covered by the contract. The district court sitting without a jury allowed recovery on both claim and counterclaim. This is an appeal by the seller from the judgment against him on the counterclaim. The ultimate question is whether the buyer had committed such a breach of contract as constituted a repudiation justifying recission by the seller.

Suit was brought in the District Court for the Eastern District of Pennsylvania. Federal jurisdiction is based on diversity of citizenship. Consequently, the conflict of laws rules of the forum, Pennsylvania, are invoked to solve the choice of law problem. Klaxon Co. v. Stentor Electric Mfg. Co., 1941, 313 U.S. 487, 61 S.Ct. 1020, 85 L.Ed. 1477. This involves no difficulty since familiar conflict of laws doctrine accepted generally and in Pennsylvania tells us that legal excuse for the non-performance or avoidance of a contract is to be determined in accordance with the law of the place of performance. Restatement, Conflict of Laws, Pa. Annot. § 358 (1936). Beyond this, the parties agree, and correctly so, that Pennsylvania is the place of performance in this case. Therefore, we apply the substantive law of Pennsylvania, particularly the Uniform Sales Act, to determine the legal consequences of the operative facts.

Uncontested findings of fact show that the contract in question was the last of a series of agreements, several of them installment contracts, entered into by the parties between June and October, 1947. Under these contracts, numerous shipments of lead were made by the seller in Canada to the buyer in Philadelphia. The seller frequently complained, and with justification, that payments were too long delayed. On the other hand, several shipments were not made at the times required by the contracts. However, by the end of March 1948, all contracts other than the one in suit had been fully performed by both parties. In this connection, it was the unchallenged finding of the district court that both parties waived the delays which preceded the buyer’s breach involved in this suit. The earlier delays are relevant only insofar as they may reasonably have influenced either party in its interpretation of subsequent conduct of the other party.

The contract in suit was executed October 23, 1947 and called for deliveries aggregating 200 tons of battery lead to- be completed not later than December 25, 1947. The agreed price was 8.1 cents per pound, or better if quality warranted. The court found that it was the understanding of the parties that at least 63 percent of the price should be paid shortly after each shipment was delivered and the balance within four weeks after that delivery. This finding is not contested.

Under this contract a first carload was delivered November 7, 1947. About 75 percent of the price was paid six days later. A. second carload was received January 8, and about 75 percent of the price was paid 10 days later. Final adjustments and payments of small balances due on these two carloads were completed March 30, and these shipments are not now in dispute. The earliest shipment immediately involved in this litigation, the third under the contract, was a carload of lead received by the buyer on March 23, 1948. This delivery followed a March 12 conference of the parties. They disagree on what transpired at that conference. However, about 290,-000 pounds of lead were then still to be delivered under the contract which stated December 25, 1947 as the agreed time for the completion of performance. And shortly after the conference, one carload of 43,-000 pounds was delivered. No part of the *862 price of this third carload has been paid. It is not disputed that plaintiff is entitled to the price of this shipment and his recovery on his claim in this suit vindicates that right.

On April 7, the buyer, who had been prodding the seller for more lead for some time, notified the seller that unless the balance of the lead should be delivered within thirty days he would buy in the open market and charge the seller any cost in excess of 8.1 cents per pound. On April 10, the seller replied refusing to ship unless the recently delivered third carload should be paid for. On May 12, buyer’s attorney threatened suit unless the undelivered lead should be shipped promptly and at the same time promised to pay on delivery 75 percent of the price of this prospective shipment together with the full price of the third installment already received. Seller’s solicitor replied on May 22 that seller regarded the contract as “cancelled” ás a result of buyer’s failure to pay for lead already delivered. At the same time the letter stated the seller’s willingness to deliver at the originally agreed price if the overdue payment should be made by return mail and a letter of credit established to cover the price of the lead not yet shipped. Buyer’s attorney replied on May 25 that buyer had withheld the price of the third carload “only as a set-off by reason of the failure of your client to deliver” and that buyer would place the overdue payment in escrow and would accept the remaining lead if shipped to Philadelphia “sight draft attached for the full invoice price of each car”. On May 27, seller’s solicitors reiterated the position stated in their March 22 letter and on June 2 seller notified buyer that the Canadian government had imposed export control on lead. The district court found, and it is here admitted, that between October 1947 and May 1948 the market price of battery lead increased from 8.1 cents to 11 Yz cents per pound.

The court concluded that the failure of defendant to make a down payment of at least 63 percent of the price of the third carload constituted a breach of contract but “not such a material breach of the contract as to justify plaintiff in refusing to ship the balance due under the contract within the meaning of section 45 of The Sales Act”. This was the decisive conclusion of law which the seller has challenged.

Section 45 of the Sales Act as in force in Pennsylvania provides in relevant part as follows: “Where there is a contract to sell goods to be delivered by stated instalments, which are to be separately paid for, and * * * the buyer neglects or refuses to * * * . pay for one or more instalments, it depends in each case on the terms of the contract, and the circumstances of the case, whether the breach of contract is so material as to justify the injured party in refusing to proceed further * * * or whether the breach is sever-able, giving rise to a claim for compensation', but not to a right to treat the whole contract as broken.” Pa.Stat.Ann.Tit. 69, § 255 (Purdon, 1931).

We are dealing, therefore, with a situation in which the controlling statute explicitly makes the circumstances of the particular case determine whether failure to pay the price of one shipment delivered under an installment contract justifies the seller in treating his own obligation with reference to future installments as ended. Our problem is how to determine the legal effect of non-payment in a particular case.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
194 F.2d 859, 1952 U.S. App. LEXIS 2852, Counsel Stack Legal Research, https://law.counselstack.com/opinion/plotnick-v-pennsylvania-smelting-refining-co-ca3-1952.