Platypus Marine, Inc. v. Glacier Guides, Inc., Alaska Legacy LLC

CourtDistrict Court, D. Alaska
DecidedNovember 4, 2025
Docket1:22-cv-00006
StatusUnknown

This text of Platypus Marine, Inc. v. Glacier Guides, Inc., Alaska Legacy LLC (Platypus Marine, Inc. v. Glacier Guides, Inc., Alaska Legacy LLC) is published on Counsel Stack Legal Research, covering District Court, D. Alaska primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Platypus Marine, Inc. v. Glacier Guides, Inc., Alaska Legacy LLC, (D. Alaska 2025).

Opinion

1 UNITED STATES DISTRICT COURT 2 DISTRICT OF ALASKA 3 PLATYHPUS MARINE, INC., Case No.: 1:22-cv-00006-APG

4 Plaintiff Findings of Fact and Conclusions of Law 5 v.

6 GLACIER GUIDES, INC., ALASKA LEGACY LLC, 7 Defendants 8 9 I conducted a bench trial June 30 through July 3, 2025. Below are my findings 10 and conclusions, as required under Federal Rule of Civil Procedure 52(a). 11 I. FINDINGS OF FACT 12 Platypus Marine, Inc. operates a shipyard in Port Angeles, Washington. One of 13 its core businesses is the repair and servicing of commercial vessels. 14 Glacier Guides, Inc. is an Alaska-based provider of luxury yacht tours, guided 15 hunting expeditions, charter fishing, and whale watching, among other services. Glacier 16 uses the ALASKAN GRANDEUR (the Vessel) for its services. Defendant Alaska 17 Legacy, LLC, an affiliate of Glacier, owns the Vessel.1 Both Glacier and the Vessel are 18 controlled by Alisha and Zach Decker. For convenience, I refer to the defendants 19 collectively as Glacier. 20

1 There is some confusion about this. Platypus alleges that defendant Alaska Legacy, 21 LLC owns the Vessel. ECF No. 18 at 2. The defendants admit this in their answer to the second amended complaint and admit that Legacy entered into the subject contracts with 22 Platypus. ECF No. 23 at 2-3. But the contracts name Zach and Alisha Decker as owners of the Vessel. Exhs. 2, 3. And in their proposed findings and conclusions, both parties 23 contend the Vessel is owned by Alaska Grandeur, LLC. ECF Nos. 147 at 2, 149 at 3. But Alaska Grandeur, LLC is not a named defendant. 1 Platypus occasionally provided repair and renovation services for the Vessel since 2 2005. In September 2021, Platypus contacted Glacier asking whether the Vessel needed 3 maintenance and repair services over the coming winter (the Project). Glacier responded 4 yes and the parties began coordinating the logistical aspects of the Project.

5 In early November 2021, Glacier tendered a $5,000.00 refundable deposit to 6 Platypus, and the parties prepared a preliminary scope of work for the Project. On 7 December 2, 2021, the Vessel arrived in Port Angeles. The next day, Platypus pulled the 8 Vessel from the water and moved it to Platypus’s work facility. The parties entered into 9 a contract which consisted of a Vessel Haul-out Agreement & Yard Policies (Exh. 22) 10 and Vessel Repair Terms and Conditions and Authorization for Work Performed (Exh. 3) 11 (collectively, the Contract). 12 Shortly after the Vessel was pulled from the water, Zach Decker and Platypus 13 representative Nick Burgett inspected it to determine the scope of work. On December 14 23, 2021, Burgett sent several Work Orders to Glacier. Glacier accepted and signed

15 Customer Work Orders 1-6 and 10-12 but rejected Work Orders 7-9. Some of the work 16 Glacier rejected was later rolled into Work Order 13, which Glacier approved. 17 During the Project, Platypus invoiced Glacier (through Zach and Alisha Decker) 18 on a regular basis. Exh. 4. The invoices included color-coded “Captain’s Reports” that 19 identified the work being done and whether it was being charged on a fixed price, a bid, 20 or a “time and materials” basis. Glacier reviewed the invoices and Captain’s Reports as 21 they were received. Prior to the final invoice, Glacier did not object to any work 22 identified as “Time and Materials” on the Captain’s Report, did not refuse to pay any of 23

2 References to exhibits are to the numbers used during the trial. 1 the invoices, and did not request any clarification of work performed or terms listed in the 2 invoices. Zach did, however, ask for and receive a discount on some of the labor rates. 3 Zach was on-site—and on the Vessel—several times during the Project, often for 4 days at a time, working on various items on the Vessel. Glacier also had other employees

5 (particularly Todd Boughner) performing work on the Vessel at times. During the 6 Project, Zach asked for the plans to be modified and work to be performed or deleted, 7 including expanding the flooring area and flybridge. See, e.g., ECF No. 164 at 34-35. 8 The parties discussed how those changes would impact the final cost, and many of them 9 were made. Zach and Alisha worked directly with some of the vendors, designers, and 10 subcontractors, including the flooring and stone suppliers. Zach and his crew performed 11 some work on their own, with Platypus’s consent. Several times during the Project, Zach 12 and Platypus representatives walked the Vessel to inspect the work. Glacier pointed out 13 items for Platypus to correct, which was done. Glacier did not raise any significant 14 objections to the quality of Platypus’s work.

15 Although the Project was supposed to be completed in mid-to-late February 2022, 16 delays dragged it out through the end of March 2022. Causes for the delays included 17 labor and supply-chain problems related to the COVID-19 pandemic and Glacier’s 18 changes to the Project’s scope. 19 As the Project stretched into March, Glacier became concerned that the Vessel 20 would not be re-delivered in time to outfit and sail it to Alaska to meet Glacier’s charter 21 deadlines. Platypus explained that if the Vessel was launched early, some work 22 (particularly painting) would not be completed and properly cured, which would void 23 Platypus’s warranty of its work. Ultimately, the parties agreed to launch the boat by 1 April 4, 2022. Glacier acknowledged that its crew would need to complete some of the 2 repair tasks during the return trip to Alaska. 3 As the launch date approached, Zach, Alisha, and their crew came to Platypus’s 4 yard to inspect the Vessel and outfit and prepare it for the return trip to Alaska. On

5 March 31, Platypus issued a final invoice for $292,253.74. Glacier was surprised by that 6 amount. On April 4, Platypus representatives Chris Feffer, Jud Linnabary, and Nick 7 Burgett met with the Deckers to discuss the final bill. The Deckers disputed a number of 8 the charges. Linnabary (who was Platypus’s President at the time) did not want to 9 discuss many of the details of the Deckers’ complaints. The meeting lasted about 45 10 minutes. Shortly after it ended, Platypus deducted $15,000 from the final invoice as a 11 compromise. The deduction was based on Platypus’s best estimate of materials that were 12 not used and anticipated corrected prices from its subcontractors.3 After applying the 13 deduction and Glacier’s earlier $5,000 deposit, the new invoice amount was $272,253.74. 14 The final Project cost was $492,253.75. Exh. 11 at 10. Burgett texted Zach that he

15 “should see our updated statement with the discount applied any minute.” 16 After viewing the updated invoice, Zach responded to Burgett that “[w]e are on r 17 way over[;] that won’t work.” Burgett replied that he would be at lunch until 12:30. 18 Zach then briefly spoke on the phone with Burgett, who stated Platypus would offer no 19 further discount. Shortly after the phone call, Zach texted Burgett that “I guess you can 20 come pick up the check[.]” 21 “The check” ended up being two checks, both dated April 4, 2022. Check No. 22

3 It was common for Platypus to issue a revised final invoice days or weeks after 23 completing work on a boat, after its subcontractors had submitted their final bills. That did not happen here because of this dispute. 1 756 was for $104,242.56 and Check No. 757 was for $168,011.18. Exh. 9. In the memo 2 field of each check, Alisha wrote: “Platypus Invoice AGR003-16,” which matches 3 Platypus’s invoice number. Id. The amount of Check No. 757 was based on Glacier’s 4 belief that Platypus had overcharged by that amount.4 The Deckers wrote that check with

5 the intent to stop payment on it as soon as the Vessel left Platypus’s yard.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Northwest Motors, Ltd. v. James
822 P.2d 280 (Washington Supreme Court, 1992)
Multicare Medical Center v. Department of Social & Health Services
790 P.2d 124 (Washington Supreme Court, 1990)
Evans v. Columbia International Corp.
478 P.2d 785 (Court of Appeals of Washington, 1970)
Perez v. Pappas
659 P.2d 475 (Washington Supreme Court, 1983)
Paopao v. STATE, DSHS
185 P.3d 640 (Court of Appeals of Washington, 2008)
Toyota of Puyallup, Inc. v. Tracy
818 P.2d 1122 (Court of Appeals of Washington, 1991)
Royal Insurance Co. of America v. Southwest Marine
194 F.3d 1009 (Ninth Circuit, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
Platypus Marine, Inc. v. Glacier Guides, Inc., Alaska Legacy LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/platypus-marine-inc-v-glacier-guides-inc-alaska-legacy-llc-akd-2025.