Plateq Corporation v. MacHlett Laboratories, Inc.

456 A.2d 786, 189 Conn. 433, 35 U.C.C. Rep. Serv. (West) 1162, 1983 Conn. LEXIS 459
CourtSupreme Court of Connecticut
DecidedMarch 8, 1983
Docket10598
StatusPublished
Cited by11 cases

This text of 456 A.2d 786 (Plateq Corporation v. MacHlett Laboratories, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Plateq Corporation v. MacHlett Laboratories, Inc., 456 A.2d 786, 189 Conn. 433, 35 U.C.C. Rep. Serv. (West) 1162, 1983 Conn. LEXIS 459 (Colo. 1983).

Opinion

Peters, J.

In this action by a seller of specially manufactured goods to recover their purchase price from a commercial buyer, the principal issue is *435 whether the buyer accepted the goods before it attempted to cancel the contract of sale. The plaintiff, Plateq Corporation of North Haven, sued the defendant, The Machlett Laboratories, Inc., to recover damages, measured by the contract price and incidental damages, arising out of the defendant’s allegedly wrongful cancellation of a written contract for the manufacture and sale of two lead-covered steel tanks and appurtenant stands. The defendant denied liability and counterclaimed for damages. After a full hearing, the trial court found for the plaintiff both on its complaint and on the defendant’s counterclaim. The defendant has appealed.

The trial court, in its memorandum of decision, found the following facts. On July 9, 1976, the defendant ordered from the plaintiff two lead-covered steel tanks to be constructed by the plaintiff according to specifications supplied by the defendant. The parties understood that the tanks were designed for the special purpose of testing x-ray tubes and were required to be radiation-proof within certain federal standards. Accordingly, the contract provided that the tanks would be tested for radiation leaks after their installation on the defendant’s premises. The plaintiff undertook to correct, at its own cost, any deficiencies that this post-installation test might uncover. 1 The plaintiff had not previously constructed such tanks, nor had the defendant previously designed tanks for this purpose. The contract was amended on August 9, *436 1976, to add construction of two metal stands to hold the tanks. All the goods were to be delivered to the defendant at the plaintiff’s place of business. 2

Although the plaintiff encountered difficulties both in performing according to the contract specifications and in completing performance within the time required, the defendant did no more than call these deficiencies to the plaintiff’s attention during various inspections in September and early October, 1976. By October 11, 1976, performance was belatedly but substantially completed. On that date, Albert Yannello, the defendant’s engineer, noted some remaining deficiencies which the plaintiff promised to remedy by the next day, so that the goods would then be ready for delivery. Yannello gave no indication to the plaintiff that this arrangement was in any way unsatisfactory to the defendant. Not only did Yannello communicate general acquiescence in the plaintiff’s proposed tender but he specifically led the plaintiff to believe that the defendant’s truck would pick up the tanks and the stands within a day or two. Instead of sending its truck, the defendant sent a notice of total cancellation which the plaintiff received on October 14, 1976. That notice failed to particularize the grounds upon which cancellation was based. 3

On this factual basis, the trial court, having concluded that the transaction was a contract for the sale of goods falling within the Uniform Commer *437 cial Code, General Statutes §§42a-2-101 et seq., considered whether the defendant had accepted the goods. The court determined that the defendant had accepted the tanks, primarily by signifying its willingness to take them despite their non-conformities, in accordance with General Statutes § 42a-2-606 (1) (a), 4 and secondarily by failing to make an effective rejection, in accordance with General Statutes § 42a-2-606 (1) (b). 5 Once the tanks had been accepted, the defendant could rightfully revoke its acceptance under General Statutes § 42a-2-608 6 only by showing substantial impairment of their value to the defendant. In part because the defendant’s conduct had foreclosed any post-installation inspection, the court concluded that such impairment had not been proved. Since the tanks were not readily resaleable on the open market, the plaintiff was entitled, upon the defendant’s wrongful revocation of acceptance, to recover their contract price, minus salvage value, plus interest. General Statutes §■§ 42a-2-703; 7 42a-2-709 *438 (1) (b). 8 Accordingly, the trial court awarded the plaintiff damages in the amount of $14,837.92.

In its appeal, the defendant raises four principal claims of error. It maintains that the trial court erred: (1) in invoking the “cure” section, General Statutes § 42a-2-508, 9 when there had been no tender by the plaintiff seller; (2) in concluding, in accordance with the acceptance section, General Statutes § 42a-2-606 (1), that the defendant had “signified” to the plaintiff its willingness to take the contract goods; (3) in misconstruing the defendant’s statutory and contractual rights of inspection; and (4) in refusing to find that the defendant’s letter of cancellation was occasioned by the plaintiff’s breach. "We find no error.

Upon analysis, all of the defendant’s claims of error are variations upon one central theme. The *439 defendant claims that on October 11, when its engineer Yannello conducted the last examination on the plaintiff’s premises, the tanks were so incomplete and unsatisfactory that the defendant was rightfully entitled to conclude that the plaintiff would never make a conforming tender. From this scenario, the defendant argues that it was justified in cancelling the contract of sale. It denies that the seller’s conduct was sufficient to warrant a finding of tender, or its own conduct sufficient to warrant a finding of acceptance. The difficulty with this argument is that it is inconsistent with the underlying facts found by the trial court. Although the testimony was in dispute, there was evidence of record to support the trial court’s findings to the contrary. The defendant cannot sustain its burden of establishing that a trial court’s findings of fact are clearly erroneous; Practice Book § 3060D; Pandolphe’s Auto Parts, Inc. v. Manchester, 181 Conn. 217, 221-22, 435 A.2d 24 (1980); by the mere recitation in its brief of conflicting testimony entirely unsupported by reference to pages of the transcript. Practice Book § 3060F (b). There is simply no fit between the defendant’s claims and the trial court’s finding that, by October 11, 1976, performance was in substantial compliance with the terms of the contract. The trial court further found that on that day the defendant was notified that the goods would be ready for tender the following day and that the defendant responded to this notification by promising to send its truck to pick up the tanks in accordance with the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

FIRST NAT. BANK OF LITCHFIELD v. Miller
939 A.2d 572 (Supreme Court of Connecticut, 2008)
Dunleavey v. Paris Ceramics USA, Inc.
819 A.2d 945 (Connecticut Superior Court, 2002)
Jefflee Enterprise v. Crimestopper Sec., No. Cv 97-0403661 (Nov. 17, 1999)
1999 Conn. Super. Ct. 15411 (Connecticut Superior Court, 1999)
Bardon Tool Mfg. v. the Torrington, No. Cv 96-0473455 S (Oct. 31, 1996)
1996 Conn. Super. Ct. 7585 (Connecticut Superior Court, 1996)
L W Supply Corp. v. Corvino, No. Cv91 0283179 (Apr. 26, 1993)
1993 Conn. Super. Ct. 4041 (Connecticut Superior Court, 1993)
Papagorgiou v. Anastopoulous
613 A.2d 853 (Connecticut Appellate Court, 1992)
Latham & Associates, Inc. v. William Raveis Real Estate, Inc.
589 A.2d 337 (Supreme Court of Connecticut, 1991)
J.A.N. Industries v. Axton-Cross Co., No. 26 03 61 (Jan. 28, 1991)
1991 Conn. Super. Ct. 254 (Connecticut Superior Court, 1991)
County Fire Door Corp. v. C. F. Wooding Co.
520 A.2d 1028 (Supreme Court of Connecticut, 1987)
Barco Auto Leasing Corp. v. House
520 A.2d 162 (Supreme Court of Connecticut, 1987)
Franklin Quilting Co., Inc. v. Benjamin Orfaly
470 A.2d 1228 (Connecticut Appellate Court, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
456 A.2d 786, 189 Conn. 433, 35 U.C.C. Rep. Serv. (West) 1162, 1983 Conn. LEXIS 459, Counsel Stack Legal Research, https://law.counselstack.com/opinion/plateq-corporation-v-machlett-laboratories-inc-conn-1983.