Plastic Omnium Auto Inergy Industrial SA de CV v. MCC Development, Inc.

CourtDistrict Court, E.D. Michigan
DecidedAugust 15, 2023
Docket2:21-cv-11141
StatusUnknown

This text of Plastic Omnium Auto Inergy Industrial SA de CV v. MCC Development, Inc. (Plastic Omnium Auto Inergy Industrial SA de CV v. MCC Development, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Michigan primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Plastic Omnium Auto Inergy Industrial SA de CV v. MCC Development, Inc., (E.D. Mich. 2023).

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF MICHIGAN SOUTHERN DIVISION

PLASTIC OMNIUM AUTO INERGY INDUSTRIAL SA de DV,

Plaintiff, Case No. 21-11141 v. Honorable Nancy G. Edmunds Magistrate Judge Elizabeth A. Stafford MCC DEVELOPMENT, INC., and ANTHONY BUFFA,

Defendants. _______________________________/

ORDER GRANTING PLAINTIFF’S MOTION FOR TEMPORARY RESTRAINING ORDER [144]

Before the Court is Plaintiff Plastic Omnium Auto Inergy Industrial SA de CV’s Motion for Temporary Restraining Order. The Court did not require a response to Plaintiff’s motion and no response has been received as of this time.1 The Court, being familiar with the facts and circumstances of this case, finds that a hearing is not necessary. See E.D. Mich. L.R. 7.1(f)(2). For the reasons that follow, Plaintiff’s motion is GRANTED. I. Factual Background In March 2022, this Court entered judgment against Defendant MCC Development, Inc. (“MCC”) in the amount of $103,950 and awarded Plaintiff a total of $10,482 in attorney’s fees. (ECF Nos. 32, 34, 35, 74.) Since that time, Plaintiff’s attempts to collect

1 The present motion concerns the same issue that is the subject of Plaintiff’s pending motion for injunction and appointment of receiver. (ECF No. 132.) Defendant filed a response to that motion which the Court now references along with Plaintiff’s pending motions and the Court’s previous orders. (ECF No. 138.) the judgment and fees awarded have been largely unsuccessful.2 In early 2023, after Defendants failed to make payments as agreed, Plaintiff conducted a creditor’s examination which revealed that Defendant Buffa transferred MCC’s assets to other shell corporations he owns to avoid POAI’s efforts to collect the judgment. (ECF No. 132.) Defendant Buffa admitted as much—in a May 18, 2023 deposition he testified that he

“took steps to protect the company’s resources” and “to avoid [the present] litigation [from] putting the company out of business.” (ECF No. 132-15, PageID.2410.) Plaintiff also discovered that MCC entered into a contract with the Donaldson Company, Inc. (“Donaldson”) on January 20, 2023 (the “Contract”). Pursuant to the Contract, Donaldson owed MCC funds amounting to $398,000 after the completion of certain work. Once that work was completed and some funds were received, however, evidence shows that Buffa diverted receipts of $199,000 and $10,000 from the account of MCC to the accounts of shell entities he owns. (ECF No. 132-15, PageID.2416; ECF No. 132-17, PageID.2454-55; ECF No. 141-4, PageID.2615.) Buffa then amended the

Contract to divert $99,810 of the funds still owing to a third party, Teal LLC, doing business as Ideal Environmental Products, also known as Chem-Stor, (“Ideal”), (the “Amended Contract”). Plaintiff states that certain of the funds have already been diverted and that Donaldson refuses to release funds absent an order from the Court. (ECF No. 144, PageID.2627-28.) In an exhibit attached to Donaldson’s garnishee disclosure, a

2 As recognized by the Magistrate Judge, Plaintiff has garnished $13,899.00 from MCC. (ECF No. 48.) Although a stipulated order states that Plaintiff received another $6,110.36, that check bounced. (See ECF No. 48; ECF No. 71-3). The parties also dispute whether defendants paid $6,110.36 in February 2023. (See ECF No. 70, PageID.1043; ECF No. 71.) During a March 2023 motion hearing, defense counsel produced documentation showing a payment in that amount from Endeavor, another company Buffa owns, but counsel stated he needed to verify whether Plaintiff received those funds. In any case, Defendants still owe at least $83,940 on the Judgment and $10,482 in attorney’s fees (totaling $94,422). (See ECF No.147, PageId.2666 n.1.) representative of Donaldson states that it continues to incur direct costs necessary to ensure the work by MCC is completed as contracted. Therefore, he states, the remaining amounts owed to MCC are unclear and in dispute. (ECF No. 145, PageID.2662.) In response to the actions and admissions by Buffa, Plaintiff filed a motion for a permanent injunction and appointment of a receiver. (ECF No. 132.) Though the motion

remains pending, the Magistrate Judge recently issued a report and recommendation in which she recommends that Plaintiff’s motion be granted. (ECF No. 147.) The Court, being thoroughly familiar with this litigation and having reviewed the report and recommendation, motion pleadings, and relevant evidence, anticipates accepting and adopting the Magistrate Judge’s Report and Recommendation when the time comes to do so. In the meantime, however, Plaintiff seeks an Order from this Court requiring that Ideal immediately submit any funds it received under the Amended Contract and that such funds be deposited into an account with the Clerk of the Court pending further order.3 Plaintiff also requests that this Court direct Donaldson to pay to Plaintiff under the

garnishment any sums owing to MCC. II. Legal Standard Federal Rule of Civil Procedure 65(b) grants the Court the authority to issue a temporary restraining order “to preserve the status quo so that a reasoned resolution of a dispute may be had.” Procter & Gamble Co. v. Bankers Tr. Co., 78 F.3d 219, 226 (6th Cir. 1996). The Court considers the following when determining whether the issuance of a temporary restraining order is appropriate: (1) whether the movant has a strong likelihood of success on the merits; (2) whether the movant would suffer irreparable injury

3 Alternatively, counsel for Plaintiff agrees to receive and deposit such funds in a trust account pending further order of this Court. (ECF No. 144, PageID.2628 n.2.) absent a stay; (3) whether granting the stay would cause substantial harm to others; and (4) whether the public interest would be served by granting the stay. Ohio Republican Party v. Brunner, 543 F.3d 357, 361 (6th Cir. 2008). “These factors are not prerequisites but are factors that are to be balanced against each other.” Overstreet v. Lexington Fayette Urban County Government, 305 F.3d 566, 573 (6th Cir. 2002).

III. Analysis Because of the involvement of the Magistrate Judge and the limited authority granted to her under 28 U.S.C. §636(b)(1), this is a unique case in which the party suffering harm has moved for a temporary restraining order after being heard on a motion for permanent injunction. The Magistrate Judge recommends granting Plaintiff the relief it seeks, but per 28 U.S.C. § 636(b)(1)(C), the parties must be afforded fourteen days in which to file written objections. Thus, more than one week remains before this Court “may accept, reject, or modify, in whole or in part, the findings or recommendations made by the magistrate judge.” Id. Plaintiff has shown there is a likelihood it will suffer harm in this time period necessitating

the issuance of a temporary restraining order. The injunctive factors, on balance, strongly support the issuance of the temporary restraining order Plaintiff requests. First, Plaintiff has shown a strong likelihood of success on the merits. Given the behavior of Defendant since entry of Judgment and the difficulties Plaintiff has experienced thus far in its collection efforts, it is highly likely Court intervention is needed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Plastic Omnium Auto Inergy Industrial SA de CV v. MCC Development, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/plastic-omnium-auto-inergy-industrial-sa-de-cv-v-mcc-development-inc-mied-2023.