Plantation Landing Resort, Inc. v. United States

30 Fed. Cl. 63, 24 Envtl. L. Rep. (Envtl. Law Inst.) 20185, 1993 U.S. Claims LEXIS 217, 1993 WL 475461
CourtUnited States Court of Federal Claims
DecidedNovember 19, 1993
DocketNo. 91-1474 L
StatusPublished
Cited by3 cases

This text of 30 Fed. Cl. 63 (Plantation Landing Resort, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Plantation Landing Resort, Inc. v. United States, 30 Fed. Cl. 63, 24 Envtl. L. Rep. (Envtl. Law Inst.) 20185, 1993 U.S. Claims LEXIS 217, 1993 WL 475461 (uscfc 1993).

Opinion

ORDER

MOODY R. TIDWELL, III, Judge:

This case is before the court on cross-motions for summary judgment. For the reasons set forth below, the court grants defendant’s motion and denies plaintiffs cross-motion for summary judgment.

FACTS

In October 1984, Preston Mauboulez, a land developer in the state of Louisiana; J. Folse Roy, a real estate consultant in that state; and the Jefferson Guaranty Bank formed a joint venture partnership for the purpose of owning and developing Plantation Landing, a 220 acre tourist destination resort on Grand Isle, Louisiana, about forty-eight miles south of New Orleans. In November 1985, the Bank, on behalf of the joint venture, filed an application with the New Orleans District of the U.S. Army Corps of Engineers (the Corps) requesting a permit1 [64]*64to dredge and fill the 220 acre site in preparation for development. Plaintiff alleged that Preston Mauboulez, or the corporations over which he had control,2 held property interests in 132 acres of the site, and J. Folse Roy and the Jefferson Guaranty Bank owned the remaining eighty-eight acres.

The Corps gave notice of the project to the public on December 18,1985 and the town of Grand Isle conducted a public hearing on January 14, 1986. The consensus of the general public supported the project. A revised public notice dated July 24, 1986 called for protests to the proposed work, suggestions for modifications, or objections to be filed with the Corps by August 13, 1986. Plaintiff, Plantation Landing Resorts, Inc., was formed in August 1986.3

In a letter dated February 6, 1987, Louisiana senators and members of congress requested that the Corps give every possible consideration to pursuing a revised environmental assessment for the project rather than an environmental impact statement (EIS),4 thereby facilitating the permit process for plaintiff.

At a meeting held on April 1,1987, plaintiff alleged that its representatives and those of the Corps agreed that, in return for a reduction of the project size from 220 acres to 59 acres, which would eliminate the requirement for an EIS, the Corps would expedite the approval of the permit. An EIS would cost plaintiff about $200,000 and precipitate a two year delay in the project.

In a letter dated October 16, 1987, the Corps advised plaintiff that, as a result of a telephone conversation on July 27, 1987 and a meeting on August 6, 1987 conducted between their respective representatives, the Corps expected to receive a revised permit application. The Corps explained that because a revised application was not filed and because plaintiff made no progress on the project, the Corps decided to return the original permit application. With a cover letter, also dated October 16, 1987, plaintiff’s agent filed a permit application dated October 13, 1987 seeking authorization for a fifty-nine acre proposal with an estimated total project cost of $44 million. The proposal in question encompassed thirty-seven acres of shallow bay bottom5 and twenty-two acres of saline intertidal marsh on or near the northern side of Grand Isle. The plan called for extensive dredging of canals and embayments to create a small boat harbor/marina and the raising of [65]*65marshlands with fill material to a height of five feet above sea level for the construction of condominiums, townhouses, a motel, restaurant, and other services and facilities. Plaintiff alleged ownership of the fifty-nine acres involved in the project but defendant disputed plaintiffs ownership of certain parcels of land that constituted a significant portion of the development site.6

The Corps gave notice to the public of the revised project on December 7, 1987 and later extended the date within which to file an opposition to the project from December 29, 1987 to January 8, 1988. On March 24, 1988 the Corps gave notice of a public hearing to be held on April 26,1988 to discuss the project. Once again the public response to the proposed project was favorable.

On December 14, 1988 the New Orleans District Engineer, Colonel Lloyd K. Brown, U.S. Army Corps of Engineers, issued a draft statement of findings about plaintiffs permit application. The draft findings concluded that, after thorough analysis of the various factors, the proposed work complied with established state and local laws, regulations, and codes. Furthermore, the draft findings concluded that although adverse environmental effects had been identified that related to the proposed work, issuance of the CWA § 404 permit was consonant with national policies, statutes, and administrative directives, and that on balance, issuance of the permit was not contrary to the public interest.

The draft statement of findings required plaintiff to create five acres of saline marsh in Caminada Bay during initial infrastructure dredging and fill activities. The artificially created marshlands, vegetated with native trees and shrubs and protected from shoreline erosion by the installation of floating breakwaters, were to be part of the mitigation required for the wetlands that would be lost as a result of the development.7 The installation of two thirty-six-inch-diameter water control structures were proposed as further mitigation. Furthermore, according to plaintiff, the conditions required for the Coastal Use Permit issued by the Louisiana Department of Natural Resources, namely the construction of a sewerage treatment facility for the development, constituted additional mitigation.

Copies of the Corps’ draft statement of findings and a letter indicating its intent to issue the permit were sent to the United States Environmental Protection Agency (EPA); the U.S. Fish and Wildlife Service, Department of the Interior; and the National Marine Fisheries Service, Department of Commerce.

On January 13, 1989 the Acting Assistant Administrator of EPA’s Office of Water wrote to the Assistant Secretary of the Army (Civil Works) and requested review of the New Orleans District Engineer’s draft statement of findings in favor of issuing the permit to plaintiff. The Assistant Secretary agreed to policy level review by the Office of the Chief Engineer and so advised EPA on February 3, 1989. On April 21, 1989 Brigadier General Patrick J. Kelly, the Director of Civil Works, U.S. Army Corps of Engineers in Washington, advised the New Orleans District Engineer of the Assistant Secretary’s decision, directed the Corps to re-evaluate the application for permit by plaintiff, and provided additional guidance as to the interpretation and implementation of the Section 404(b)(1) guidelines.

On January 4,1990, following re-evaluation of the permit application in accordance with the April 21, 1989 guidelines, the Corps advised plaintiff that the mitigative measures required as special conditions for permit issuance were altered to require creation of twenty-two acres, instead of the original five acres, of saline marsh in Caminada Bay prior to initial infrastructure dredge and fill activi[66]*66ties. Unsatisfied with the new conditions, plaintiff responded on March 6, 1990 with a counter-offer to acquire twenty-two acres of previously removed freshwater wetlands in south Louisiana (150 miles north west of Grand Isle and the development site at issue) and convert them to their former wetlands status.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

John R. Sand & Gravel Co. v. United States
62 Fed. Cl. 556 (Federal Claims, 2004)
Holden v. United States
38 Fed. Cl. 732 (Federal Claims, 1997)
Plantation Landing Resort, Inc. v. United States
39 F.3d 1197 (Federal Circuit, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
30 Fed. Cl. 63, 24 Envtl. L. Rep. (Envtl. Law Inst.) 20185, 1993 U.S. Claims LEXIS 217, 1993 WL 475461, Counsel Stack Legal Research, https://law.counselstack.com/opinion/plantation-landing-resort-inc-v-united-states-uscfc-1993.