Placer County Water Agency v. Hofman

165 Cal. App. 3d 890, 211 Cal. Rptr. 894, 1985 Cal. App. LEXIS 1778
CourtCalifornia Court of Appeal
DecidedMarch 19, 1985
DocketCiv. 20556
StatusPublished
Cited by12 cases

This text of 165 Cal. App. 3d 890 (Placer County Water Agency v. Hofman) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Placer County Water Agency v. Hofman, 165 Cal. App. 3d 890, 211 Cal. Rptr. 894, 1985 Cal. App. LEXIS 1778 (Cal. Ct. App. 1985).

Opinion

Opinion

BLEASE, J.

Placer County Water Agency exercised the power of eminent domain to acquire easements necessary for the construction, maintenance, and use of water pipelines traversing respondents’ (Hofmans) land. In the condemnation action the jury verdict awarded the Hofmans substantial sums for expenses incurred to mitigate damages and for severance damages to the remainder of the Hofmans’ property. The court awarded the Hofmans litigation expenses. (Code Civ. Proc., § 1235.140.) 1 It denied the agency’s request to offset the value of the Hofmans’ use of the property against the interest otherwise due on the compensation awarded in the proceeding. We will affirm the judgment except for the award of mitigation damages.

Facts

The agency decided to construct a pipeline to convey water from its water treatment plant to the City of Lincoln. The route traversed the 4,993-acre parcel of land owned by the Hofmans. It filed this action in May 1977 to acquire a permanent 25-foot-wide easement across the parcel for use as a corridor for the buried pipeline and future pipelines as needed. The agency also sought a temporary easement encompassing an additional 15 feet on each side of the permanent easement zone for use in constructing the pipeline.

Construction commenced pursuant to an order for possession prior to judgment. (See § 1255.010 et seq.) During the construction of the pipeline the Hofmans developed suspicions that the contractor was not building the pipeline according to project specifications. The pipe is buried in a trench. In order to protect the pipe from fractures, the project plans require that the backfill medium in which the pipe is embedded be compacted as specified, not contain large rocks and be of specified depth. The Hofmans paid engineers to investigate and evaluate the suspected deviations from the project *894 specifications. They also paid lawyers to bring a separate action to compel the agency to comply with the environmental mitigation measures contained in the project’s environmental impact report (EIR) and to remedy defects they perceived in the pipeline construction. The EIR proposed, as mitigation measures, that the ground disrupted by the trenching activities be reseeded with native flora and that rocks unearthed in the trenching work be removed from the project easements. The Hofmans contended this had not been accomplished with the likely result of safety hazards and erosion damage to their remaining land. This litigation resulted in a stipulated judgment, filed October 3, 1978, which, as approved by the court, provided that the agency must “comply with the provisions of the [EIR].” The part of the proposed judgment providing that the construction work comply with good engineering and construction practices and enable the Hofmans to use the land without impairment was stricken by the court.

After the pipeline was completed it was tested and spot repairs were made. The agency then decided to reconstruct portions of the pipeline. It replaced a significant segment of the line and reworked the layer of bedding material on top of the pipe. The work was completed by December 10, 1979, and the temporary easement ended.

Prior to trial the agency learned that the Hofmans planned to cross over the pipeline with a large piece of earthmoving equipment, a J621, to construct a cattle feedlot area. The J621 when loaded has a “wheel load” exceeding 25,000 pounds. The agency estimated that the reconstructed pipeline would bear the stress of any vehicle “wheel load” up to 25,000 pounds but that any higher weight posed an unacceptable risk of injury to the pipeline. It filed a supplemental complaint enlarging the burden of the permanent easement to prohibit, without the consent of the agency, the crossing of the pipeline by vehicles with a “wheel load” heavier than 25,000 pounds.

The valuation trial was based upon the project as actually constructed. The major issue was the amount of damages to the remainder of the Hofmans’ property caused by the easements. (See § 1263.410 et seq.) The Hofmans presented two primary witnesses concerning these severance damages. Carlin Hofman, one of the owners, testified that the temporary easement for the construction of the pipeline substantially prevented use of the property for cattle and sheep ranching because of the intrusions of construction workers and the actual and potential disruption of access to the area of the property suitable for feedlot purposes. He calculated the damage inflicted on the market value of the property attributable to this interference was the rental value of comparable facilities, an aggregate figure of $109,049.

Carlin Hofman calculated the total reduction in the fair market value of the property attributable to the combination of the temporary and permanent *895 easements as $384,700. He cited various reasons for the damage caused by the permanent easement, e.g., loss of isolation as a result of pipeline repair and maintenance harming beef production; loss of guaranteed carrying capacity of the ranch in light of possible future pipeline construction; fears that the pipeline might be unsafe; loss of ability to use very heavy vehicle equipment because of the “wheel load” limitation; and difficulties in irrigating across the permanent easement. Hofman’s testimony was buttressed by Joseph Murphy, a real estate appraiser specializing in rural property. He affirmed in substance Hofman’s method of calculating the loss attributable to the temporary easement and estimated the total severance damages at $322,000.

The agency’s valuation witnesses contended that there were no severance damages. In their view the construction activities had little or no effect on ranching and the presence of the water pipeline would have no negative effect on the fair market value of the property. They testified that the value of the property was enhanced considerably by the potential for future development as a result of the treated water available from the pipeline.

The engineering testimony was also in sharp conflict. Merle Henry, a registered civil engineer with a background in design of waterline and sewerline systems testified for the Hofmans. In his opinion, despite the absence of any break of the line for six months, the reconstruction activities were insufficient to prevent an unacceptable risk of breaks for the portions of the pipeline where only the top fill had been reworked. He believed over time crossing the pipeline with ordinary vehicles may cause the pipeline to break in these areas. The agency witnesses testified that the pipeline as constructed would safely withstand all normal traffic.

The jury awarded damages in sum of $166,625; for the taking of the easements, $8,200; compensation for expenses incurred to mitigate damages, $62,425; compensation for severance damages to the remainder, $111,000; offset for special benefits $15,000. The court awarded litigation expenses of $157,717.81.

Discussion

I

The agency contends that the award of expenses to mitigate damages is erroneous as a matter of law. Expenses were for engineering and legal services largely incurred in a separate legal action which sought to compel the agency to comply with the project plans and EIR.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pebley v. Santa Clara Organics
California Court of Appeal, 2018
Pebley v. Santa Clara Organics, LLC
232 Cal. Rptr. 3d 404 (California Court of Appeals, 5th District, 2018)
CITY OF PUYALLUP v. Hogan
277 P.3d 49 (Court of Appeals of Washington, 2012)
City of Livermore v. Baca
205 Cal. App. 4th 1460 (California Court of Appeal, 2012)
City of Fremont v. Fisher
73 Cal. Rptr. 3d 54 (California Court of Appeal, 2008)
Metropolitan Water District v. Campus Crusade for Christ, Inc.
161 P.3d 1175 (California Supreme Court, 2007)
City of Carlsbad v. RUDVALIS
135 Cal. Rptr. 2d 194 (California Court of Appeal, 2003)
City of Stockton v. Albert Brocchini Farms, Inc.
111 Cal. Rptr. 2d 662 (California Court of Appeal, 2001)
City of Hollister v. McCullough
26 Cal. App. 4th 289 (California Court of Appeal, 1994)
Department of Transportation v. Zivelonghi
183 Cal. App. 3d 187 (California Court of Appeal, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
165 Cal. App. 3d 890, 211 Cal. Rptr. 894, 1985 Cal. App. LEXIS 1778, Counsel Stack Legal Research, https://law.counselstack.com/opinion/placer-county-water-agency-v-hofman-calctapp-1985.