PJR CONSTRUCTION OF NEW JERSEY INC. v. VALLEY FORGE INSURANCE COMPANY

CourtDistrict Court, D. New Jersey
DecidedJuly 31, 2019
Docket3:17-cv-04219
StatusUnknown

This text of PJR CONSTRUCTION OF NEW JERSEY INC. v. VALLEY FORGE INSURANCE COMPANY (PJR CONSTRUCTION OF NEW JERSEY INC. v. VALLEY FORGE INSURANCE COMPANY) is published on Counsel Stack Legal Research, covering District Court, D. New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
PJR CONSTRUCTION OF NEW JERSEY INC. v. VALLEY FORGE INSURANCE COMPANY, (D.N.J. 2019).

Opinion

NOT FOR PUBLICATION

UNITED STATES DISTRICT COURT DISTRICT OF NEW JERSEY

PJR CONSTRUCTION OF NEW JERSEY, INC.,

Plaintiff, Civil Action No. 17-4219 (MAS) (LHG) v.

VALLEY FORGE INSURANCE COMPANY & MEMORANDUM OPINION NATIONAL FIRE INSURANCE COMPANY OF HARTFORD,

Defendants.

SHIPP, District Judge

This matter comes before the Court upon Defendants Valley Forge Insurance Company (“Valley Forge”) and National Fire Insurance Company of Hartford’s (“National Fire”) (collectively, “Defendants”) Motion for Summary Judgment. (ECF No. 17.) Plaintiff PJR Construction of New Jersey, Inc. (“Plaintiff” or “PJR”) opposed (ECF No. 20), and Defendants replied (ECF No. 21). The Court has carefully considered the parties’ submissions and decides the motion without oral argument pursuant to Local Civil Rule 78.1. For the reasons set forth herein, Defendants’ Motion for Summary Judgment is granted. I. BACKGROUND1 The instant dispute arises from Defendants’ denial of coverage under a commercial general liability coverage policy Defendants issued to Plaintiff (the “Policy”). (See Compl. ¶¶ 3-11, ECF

1 The Court’s recitation of facts draws from Defendants’ Rule 56.1 statement (Defs.’ Statement of Material Facts Not in Dispute (“DSUMF”), ECF No. 17-2) and Plaintiff’s Rule 56.1 statement (Pl.’s Counterstatement of Material Facts (“PJRSUMF”), ECF No. 20-3). In accordance with No. 1.) Pursuant to the Policy,2 Plaintiff sought coverage for a dispute between Plaintiff and Cambridge Real Property, LLC (the “PJR-Cambridge Dispute”). (DSUMF ¶ 37.) On December 7, 2011, Plaintiff and Cambridge Real Property, LLC (“Cambridge”) executed an agreement for Plaintiff to construct a “26,250 square foot swim club[] and 3,150

square foot pavilion building” in Aberdeen Township, New Jersey (the “Project”). (DSUMF ¶ 1; Ex. 1 at 9, ECF No. 17-4 (the “Agreement”).)3 Plaintiff was to complete “Phase 1” of three phases of the Project. (PJRSUMF ¶ 5.) The contract price for Plaintiff’s work was $5,194,700. (Agreement 12.) The scope of Plaintiff’s work on the Project is identified in two Riders to the Agreement. (Id. at 7, 9-16.) Pursuant to the Agreement, Lisa Landers of Fabiano Designs was designated as the Initial Decision Maker. (PJRSUMF ¶¶ 8-10; Agreement at 2, 6, 27.) The Agreement defines a “claim” as a “demand or assertion by one of the parties seeking, as a matter of right, payment of money, or other relief with respect to the terms of the [Agreement].” (Agreement at 54.) All claims were referred to the Initial Decision Maker for an initial decision and the Initial Decision Maker was

Response (“PJRResp”), ECF No. 20-2; Defs.’ Response, ECF No. 21-1 (“DResp”).) While the parties generally agree on the facts, the Court notes, as necessary, where the parties disagree. 2 The Policy consists of five individual year-long policies issued by Defendants and effective from August 18, 2011 through August 18, 2016. (DSUMF ¶ 42; Exs. 17-21, ECF Nos. 17-20 to 17-24.) National Fire issued three policies covering August 18, 2011 through August 18, 2014. (DSUMF ¶ 42.) Valley Forge issued two policies covering August 18, 2014 through August 12, 2016. (Id.) Because the relevant portions of the Policy are the same in each individual policy, the Court cites only to the policy in effect from August 18, 2011 to August 18, 2012. (Policy, Ex. 17, ECF No. 17-20.) 3 Many of the exhibits submitted by Defendants do not contain internal pagination or the exhibit is a combination of multiple documents with nonconsecutive pagination. Thus, when citing to the defendants’ exhibits, the Court uses the page numbers imprinted on the documents by the CM/ECF system. When citing to a deposition transcript, the Court uses the page numbers provided in the transcript. required to take action within ten days of the claim. (Id. at 55.) The Initial Decision Maker could approve or deny a claim. (Id.) Landers reviewed Plaintiff’s applications for payment for work completed on the Project. (PJRSUMF ¶ 14.) Landers would go to the Project site and “assess where [PJR was] in terms of

construction and approve or deny the [a]pplication for [p]ayment[,]” and she also would report to Rudy Fabiano, Principal of Fabiano Designs, whether the application for payment should be approved or denied. (Ex. D, Lisa Landers Dep. Tr. 17:15-18:5 (“Landers Dep.”); ECF No. 20-4.) Landers did not provide the final sign-off on Plaintiff’s applications for payments; this sign-off, or certification, was provided by Rudy Fabiano. (Id.; PJRSUMF ¶ 15.) When an application for payment was certified, it indicated that a representative of Fabiano Designs had observed the work on the project;4 the work had been completed to the extent indicated in the application; “the quality of the workmanship and material performed to [the Agreement];” and that the “architect [knew of] . . . . no reason why payment[] should not be made.” (Landers Dep. 20:7-25.) Fabiano Designs provided construction administration services for the project from

December 2012 to January 14, 2014, and on February 29, 2014, Fabiano Designs informed Plaintiff that it was no longer providing those services and could not approve applications for payment. (PJRSUMF ¶¶ 39-40.) Landers was involved in approving payment applications numbers 1 to 14, and Sinibaldo Fabiano was involved with and signed off on payment applications numbers 15 through 20. (Id. ¶¶ 20-23.) After Fabiano Designs informed PJR that it could no longer approve payment applications, Frank Ward, Principal of Cambridge, paid and approved payment application numbers 21 to 25. (Id. ¶¶ 27, 41.)

4 Plaintiff avers that the certification indicates that the architect had “inspected” the work done on the Project. (PJRSUMF ¶ 16(a).) Landers, however, testified that “inspection” was a technical term and that the architect’s “construction administration responsibilities [were] observations.” (Landers Dep. 21:12-22:3.) The Court, accordingly, uses the term “observation.” Plaintiff began working on the Project on or about May 29, 2012. (DSUMF ¶ 3.) The Agreement contained a project completion date of March 1, 2013, but due to numerous Change Orders, the “substantial completion date” was extended 407 working days. (Id. ¶¶ 4-5.) Plaintiff was denied access to the Project’s site on November 13, 2014. (Id. ¶ 7.) Defendants state that

Cambridge estimated that the Project was between 55% and 74.3% complete when PJR stopped working on it. (Id. ¶ 8.) Plaintiff denies that Cambridge’s estimates are correct and states that the Project was at least 77.9% complete. (PJRResp. ¶ 8.) Plaintiff’s 77.9% completion is based on payment application number 26R2, which reflects a 77.9% completion rate. (PJRSUMF ¶ 32; Ex. G, Payment Application at 4 (“26R2”) ECF No. 20-4.) On November 25, 2014, counsel for Cambridge sent Plaintiff correspondence. (DSUMF ¶ 10; Ex. 4 (“Cambridge Termination”), ECF No. 17-7.) The correspondence indicated that the Agreement would be terminated by Cambridge on December 2, 2014 and the termination was pursuant to Sections 14.2.1.1; 14.2.1.2; and 14.2.1.4 of the Agreement. (Cambridge Termination.) On the same day, Plaintiff sent Cambridge correspondence indicating that the Agreement would

be terminated pursuant to Sections 14.1.3 and 14.1.4 of the Agreement. (DSUMF ¶ 15; Ex. 5, ECF No. 17-8.) Cambridge hired Sweetwater Construction Company (“Sweetwater”) to complete the Project. (DSUMF ¶ 18.) The parties disagree about the work Sweetwater had to perform to complete the Project. Defendants rely upon the testimony of Kenneth Eipel, a consultant Cambridge retained; Brian Furka, a Sweetwater representative; and Cambridge’s allegations in the PJR-Cambridge dispute to establish that certain work had to be completely redone and significant portions of the Project were left unfinished. (Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

West v. American Telephone & Telegraph Co.
311 U.S. 223 (Supreme Court, 1940)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Herman Wenzel v. Nautilus Ins Co
474 F. App'x 862 (Third Circuit, 2012)
Edwards v. HOVENSA, LLC
497 F.3d 355 (Third Circuit, 2007)
Atlantic Mut. Ins. Co. v. Hillside Bottling Co., Inc.
903 A.2d 513 (New Jersey Superior Court App Division, 2006)
Weedo v. Stone-E-Brick, Inc.
405 A.2d 788 (Supreme Court of New Jersey, 1979)
Flomerfelt v. Cardiello
997 A.2d 991 (Supreme Court of New Jersey, 2010)
United Rental Equipment Co. v. Aetna Life & Casualty Ins.
376 A.2d 1183 (Supreme Court of New Jersey, 1977)
Sealed Air Corp. v. Royal Indem. Co.
961 A.2d 1195 (New Jersey Superior Court App Division, 2008)
Kampf v. Franklin Life Insurance
161 A.2d 717 (Supreme Court of New Jersey, 1960)
President v. Jenkins
853 A.2d 247 (Supreme Court of New Jersey, 2004)
Lee v. General Acc. Ins. Co.
767 A.2d 985 (New Jersey Superior Court App Division, 2001)
Zacarias v. Allstate Insurance
775 A.2d 1262 (Supreme Court of New Jersey, 2001)
Butler v. Bonner & Barnewall, Inc.
267 A.2d 527 (Supreme Court of New Jersey, 1970)
Chubb Custom Insurance v. Prudential Insurance Co. of America
948 A.2d 1285 (Supreme Court of New Jersey, 2008)
Dunkin' Donuts Inc. v. Patel
174 F. Supp. 2d 202 (D. New Jersey, 2001)
Gasperini v. Center for Humanities, Inc.
518 U.S. 415 (Supreme Court, 1996)
Ohio Cas. v. Island Pool & Spa
12 A.3d 719 (New Jersey Superior Court App Division, 2011)
Manahawkin Convalescent v. Frances O'neill (071033)
85 A.3d 947 (Supreme Court of New Jersey, 2014)
Cypress Point Condominium Association, Inc. v. Adria Towers
118 A.3d 1080 (New Jersey Superior Court App Division, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
PJR CONSTRUCTION OF NEW JERSEY INC. v. VALLEY FORGE INSURANCE COMPANY, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pjr-construction-of-new-jersey-inc-v-valley-forge-insurance-company-njd-2019.