Pittsley v. King

55 A. 920, 206 Pa. 193, 1903 Pa. LEXIS 674
CourtSupreme Court of Pennsylvania
DecidedMay 18, 1903
DocketAppeal, No. 259
StatusPublished
Cited by10 cases

This text of 55 A. 920 (Pittsley v. King) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pittsley v. King, 55 A. 920, 206 Pa. 193, 1903 Pa. LEXIS 674 (Pa. 1903).

Opinion

Opinion by

Mr. Justice Bbown,

On March 31, 1900, Henry E. Pittsley, trading as the Sayre Lumber 'Company, entered into a contract with F. M. Young and 185 other individuals or firms for the erection of a milk “ condensory.” This suit was brought by the appellants, as the use plaintiffs, to recover from the 186 defendants, jointly, the balance due on the contract price for the building and equipment of the plant and for extra work done and materials furnished. Demurrers were filed to plaintiffs’ statement by different defendants, all, however, on the same ground, that the contract was several and not joint. The court below, having-been of opinion that there was no joint liability, entered judgment for the defendants on their demurrers, and from it we have this appeal.

The first clause of the contract is : “ It is hereby agreed between the Sayre Lumber Company, of Sayre, Pa., party of the [195]*195first part, and the other subscribers hereto as party of the second part. That the first party is to build, equip and complete in good running order for said second party within four months from the date hereof, a Milk Condenso'ry Plant, according to plans and specifications hereto attached, at Clark’s Summit, State of Pennsylvania, County of Lackawanna, on land provided by said second party for the agreed price of forty-two thousand dollars ($-12,000), which is to be paid as follows: Seven thousand dollars ($7,000) when the building is completed; ten thousand dollars ($10,000) when boilers and engines are set and pumps and can-making machinery are delivered in building; ten thousand dollars ($10,000) when the copper works and all machinery is delivered in building; ten thousand dollars ($10,000) when all machinery is set and arranged in position ready to start; the balance, five thousand dollars ($5,000) sixty days from the starting of said plant. This sixty days time is given on the final payment, as a guarantee that the factory is complete and to demonstrate that the first party has fully discharged his part of this contract and the machinery is all new and first class, and of the character, quality and capability for which it is intended and recommended. And if said trial should discover or develop any flaws, defect or mistake in the construction or equipment of said plant, said first party shall have the right to correct such en’ors or mistakes withiu a reasonable time after the discovery of the same. Such errors or mistakes shall be corrected, as quickly as is practical, and with as little obstruction as possible to the continuous running of said plant. It is understood and agreed that the second party is to furnish the land on which to build the said plant, and the water on said land ready to attach-the pumps, and to provide all needed tilling, sewerage or drainage, at their own expense, from beyond fifty feet outside of building, if needed, aside from the price of plant named in the contract, and within thirty days from the date of this contract, the second party shall provide the first party with a written or printed description of the land with permit to build thereon, free from all incumbrances or liabilities.” That the obligation imposed upon and assumed by the appellees by this clause is joint, is too plain for discussion. Party of the first part agreed to build, equip and complete for the parties of the second part “a [196]*196milk eondensory plant ” for the agreed price of $ 42,000. The price so agreed upon was to be paid by the parties of the second part, who were also to furnish the land on which the plant was to be built. They were not to pay aliquot parts of the contract price, nor to furnish aliquot portions of the land ; but, jointly, they were to pay the sum agreed upon, and, jointly, to furnish the land needed. “ Wherever an obligation is undertaken by two or more, or a right given to two or more, it is the general presumption of law that it is a joint obligation or right. Words of joinder are not necessary for this purpose ; but, on the other hand, there should be words of severance, in order to produce a several responsibility or a several right. Whether the liability incurred is joint, or several, or such that it is either joint or several at the election of the other contracting party depends (the rule above stated being kept in view) upon the terms of the contract, if they are express : ” 1 Parsons on Contracts, page 11. “ It is a general presumption of law, when two or more persons undertake an obligation, that they undertake jointly. Words of severance are necessary to overcome this primary presumption. In all written contracts, therefore, whether the liability incurred is joint or several, or joint and several, is to be determined by looking at the words of the instruments, and at them alone. The subject-matter of the contract, and the interests of the parties assuming a liability, have nothing to do with the question. It may be otherwise with respect to the rights of the covenantees, where there are more tharr one. There are not wanting cases in which it has been held that when the interests of the covenantees are several, they may sue severally, though the terms of the covenant upon which they sue are strictly joint. Even this, however, has been doubted. But, however it may be with the rights of covenantees, it is a settled rule that whether the liability of covenantors is joint, or several, or both, depends exclusively upon the words of the covenant. And the language of severalty or joinder is the test. The covenant is always joint, unless declared to be otherwise: Enys v. Donnithorne, 2 Burrows, 1190 ; Phillips v. Bonsall, 2 Binn. 138 ; ” City of Philadelphia v. Reeves, 48 Pa. 472.

Of the above-quoted clause in the contract the learned judge said: “ The first clause of the contract, standing alone, with [197]*197the bare signatures of the Sayre Lumber Company and the defendants, would undoubtedly make the undertaking a joint one; ” but he was of opinion that, taking the contract as a whole, the intention of the parties, as gathered from it, was that it was several and not joint, and that each of the parties of the second part should be bound only to the extent of his subscription to the capital stock of a proposed corporation. The clauses in the agreement from which he interpreted the contract as a whole to be several are as follows: “ B'or the purpose of forming a corporation to own and operate said factory and fully carry out the intention of the subscribers, it is hereby agreed that when this contract is closed, second parties are to incorporate under the laws of the State, limited corporation stock, nonassessable, fixing the aggregate amount of capital at not less than the amount subscribed, divided into shares of one hundred dollars each, or according to the laws of the State, which are to be issued to subscribers in proportion to their paid-up interests in said factory; and it is understood and agreed that the by-laws shall provide that one half a cent a can toll shall be set aside as a fund and declared and paid to shareholders as dividend on stock, and shall be paid for no other purpose. And it is further agreed by and between all the subscribers for stock that the producers of milk are to receive all its product brings, less the actual cost of canning, packing, marketing, etc., after one half a cent a can has been declared as a dividend. In consideration of the above, all agree that all their milk shall be furnished to said condensory. For a full and faithful performance of our respective parts of this contract, we bind ourselves and our successors.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fabral, Inc. v. B & B Roofing Co., Inc.
773 F. Supp. 2d 539 (E.D. Pennsylvania, 2011)
Bell v. Gaidula
45 Pa. D. & C. 547 (Lackawanna County Court of Common Pleas, 1942)
Myers v. Plummer
21 Pa. D. & C. 12 (Montgomery County Court of Common Pleas, 1934)
Yadusky v. Shugars
151 A. 785 (Supreme Court of Pennsylvania, 1930)
Yadusky v. Shugars
13 Pa. D. & C. 541 (Schuylkill County Court of Common Pleas, 1930)
Willingham, Wright & Covington v. Glover
111 S.E. 206 (Court of Appeals of Georgia, 1922)
In re John B. Rose Co.
275 F. 409 (Second Circuit, 1921)
Mintz v. Tri-County Natural Gas Co.
103 A. 285 (Supreme Court of Pennsylvania, 1918)
Hascsak v. Leseinsky
39 Pa. Super. 642 (Superior Court of Pennsylvania, 1909)
Boltz v. Muehlhof
37 Pa. Super. 375 (Superior Court of Pennsylvania, 1908)

Cite This Page — Counsel Stack

Bluebook (online)
55 A. 920, 206 Pa. 193, 1903 Pa. LEXIS 674, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pittsley-v-king-pa-1903.