Pittsburgh v. Pennsylvania Public Utility Commission

222 A.2d 395, 208 Pa. Super. 260, 1966 Pa. Super. LEXIS 837
CourtSuperior Court of Pennsylvania
DecidedSeptember 15, 1966
DocketAppeals, Nos. 92 to 117, inclusive, and 119
StatusPublished
Cited by15 cases

This text of 222 A.2d 395 (Pittsburgh v. Pennsylvania Public Utility Commission) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pittsburgh v. Pennsylvania Public Utility Commission, 222 A.2d 395, 208 Pa. Super. 260, 1966 Pa. Super. LEXIS 837 (Pa. Ct. App. 1966).

Opinion

Opinion by

Ervin, P. J.,

This rate proceeding began when Columbia Gas of Pennsylvania, Inc. filed tariffs increasing Columbia’s gross revenue by some $6.5 million or about 9%. Complaints against the proposed increase were filed by the commission, the City of Pittsburgh, County of Allegheny, Borough of Ambridge, Borough of Canonsburg and eleven industrial consumers. The commission suspended the proposed rates for a period of nine months (July 28, 1964 to April 28, 1965). Further, the commission provided that the existing rates should continue in effect after April 28, 1965 as temporary rates, under §310 of the Public Utility Law, subject to recoupment on final order.

By final order dated October 4, 1965 the commission granted an increase in allowable operating revenues of $5,085,466, or more than 75% of the increase sought. The commission found a fair return of $5,-917,000 based on a fair rate of 6.1%, on a fair value finding of $97 million.

[265]*265Appeals to this Court from the commission order of October 4, 1965 were taken by Columbia, the City of Pittsburgh and ten of the eleven industrial complainants. Columbia was permitted to intervene as appellee in the appeals of the city and the industrial companies. All appeals have been consolidated for argument and will be disposed of in one opinion.

In general, Columbia contends that the commission’s finding of (1) fair value, and (2) rate of return is too low, and (3) that the exclusion of certain operating expenses makes the allowance for that item too low. By contrast, the city and industrial complainants contend the findings of the commission on fair value, rate of return and allowable operating revenues, are excessively high.

Fair Value: Original Cost. The commission accepted Columbia’s claim of $93,729,608 for undepreciated original cost. The city alleges there is no evidence showing original cost of Columbia’s property on the record. Columbia was “spun off” from Manufacturers Heat and Light Company pursuant to a realignment order of the commission dated September 12, 1961. Complainants did not raise any question concerning original cost before the commission, or in their appeal petitions, and ordinarily cannot raise such question on appeal. Cf. George Hyam Associates, Inc. v. Pa. P.U.C., 199 Pa. Superior Ct. 3, 184 A. 2d 414 (1962).

Under the Uniform System of Accounts, original cost figures for Manufacturers, the parent company, were recorded, and approved by commission orders dated December 30, 1946 and February 21, 1955. Original cost figures for the parent company were produced in two rate cases. See Pa. P.U.C. v. Manufacturers Light and Heat Co., 35 Pa. P.U.C. 727, 740 (1958), and 37 Pa. P.U.C. 345, 354 (1959), and Pittsburgh v. Pa. P.U.C., 187 Pa. Superior Ct. 341, 144 A. 2d 648 (1958). Thus the property of Manufacturers, the par[266]*266ent company, used in furnishing gas service in Pennsylvania, was recorded at original cost prior to the transfer to Columbia. Further, on September 12, 1961 the commission entered a detailed order approving realignment and transfer. Pittsburgh contends that some $17 million of transmission mains were improperly reclassified by Manufacturers as distribution mains, and transferred in the realignment proceedings to Columbia. The implication is that the “reclassification” was made to wrongfully increase the property transferred to Columbia as part of its rate base. However, there is no showing, as the city contends, that transmission mains of Manufacturers were wrongfully included in the original cost, or wrongfully entered into the fair value finding of Columbia’s property. Columbia presented an original cost figure and many exhibits dealing with original cost of its property in this proceeding. Exhibit 9 showed net depreciated original cost of plant in service as of March 31, 1964 as $73,801,438, or $93,-732,200 undepreciated. The realignment proceeding of September 12, 1961 expressly provided that it did not bind the commission on the question of valuation in a subsequent rate case. However, the realignment proceeding did disclose original cost figures, less reserve, for depreciation, depletion and amortization, and to which was added other current assets, making a total of $82,526,579.

Property installed by Columbia since the transfer of 1961 has been recorded at original cost pursuant to the Uniform System of Accounts. The commission decided, in the realignment proceeding of September 12, 1961, that the transfer between Manufacturers and Columbia was proper. Cf. Berner v. Pa. P.U.C., 382 Pa. 622, 116 A. 2d 738 (1955). While the realignment is not conclusive on the question of the valuation of Columbia’s property in a rate case, it does furnish substantial evidence on this question.

[267]*267Columbia properly points out that reclassification does not change the dollar value of the property. The commission in the 1961 realignment proceeding held the reclassification of property by Manufacturers in 1959 was lawful, and that the property transferred to Columbia was properly part of Columbia’s system. So, the reclassification by Columbia in 1963 of gas mains from transmission (Acct. 367) to Distribution (Acct. 376) had no effect on the original cost of Columbia’s property.

Trended Original Cost. Columbia offered five measures of value, viz., undepreciated original cost $93,-729,608 and estimates of trended original cost at one year average price level ($170,465,297) undepreciated; two-year average price level ($169,033,863) and three-year average price level ($167,605,345) and five-year average price level ($164,705,485). The commission criticized Columbia’s trended original cost study, stating: “Respondent’s trended original cost study lacked much of the detail necessary to fully check the applicability of the trending data employed.” The commission made detailed analysis and criticism of Columbia’s trend factors, including trend factors for the contract labor component, equipment component and cost of pipe. The city complains that the commission gave great weight to the trended original cost studies instead of making adjustments downward because of their frailty. Columbia, on the other hand, claims that the commission’s criticism of Columbia’s trending procedures is not justified or warranted by the evidence. The commission noted that Columbia’s actual cost experience for the years 1959-63, as shown by Columbia’s exhibit No.. 116, applied to total distribution pipe, exceeded trended original cost at the 1963 level by about $37,000,000 and stated that this showed “to some extent the reasonableness of respondent’s five-year estimates.” The city says the unit costs of 1963 are not [268]*268representative of the cost of reproducing the whole plant.

The commission noted that no adjustments had been made in the indexes to reflect change in dollar values or change in labor productivity or use of modern equipment, that is, no “supersession discount.” “Super-session discount” is the effect of the development of new materials, designs and methods of construction which have superseded older methods or materials, resulting in an increased efficiency, and means that a product costing more than the one it replaces requires a discount because it is more efficient than the article replaced. The commission rejected any claims for “supersession discount” on the ground that such matters were indefinite, theoretical and incapable of exact mathematical calculation. Application of Wilmington Suburban Water Corporation etc., (Del., June 14, 1965), 211 A. 2d 602.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Colorado Municipal League v. Public Utilities Commission
687 P.2d 416 (Supreme Court of Colorado, 1984)
Pike County Light & Power Co. v. Pennsylvania Public Utility Commission
465 A.2d 735 (Commonwealth Court of Pennsylvania, 1983)
Dauphin Consolidated Water Supply Co. v. Pennsylvania Public Utility Commission
423 A.2d 1357 (Commonwealth Court of Pennsylvania, 1980)
T. W. Phillips Gas & Oil Co. v. Pennsylvania Public Utility Commission
412 A.2d 1118 (Commonwealth Court of Pennsylvania, 1980)
Bell Telephone Co. v. Pennsylvania Public Utility Commission
408 A.2d 917 (Commonwealth Court of Pennsylvania, 1979)
NW Pub. Serv. v. CITIES OF CHAMBERLAIN, ETC.
265 N.W.2d 867 (South Dakota Supreme Court, 1978)
Bell Telephone Co. v. Commonwealth
331 A.2d 572 (Commonwealth Court of Pennsylvania, 1975)
Rhode Island Consumers' Council v. Smith
322 A.2d 17 (Supreme Court of Rhode Island, 1974)
Pennsylvania Power & Light Co. v. Pennsylvania Public Utility Commission
311 A.2d 151 (Commonwealth Court of Pennsylvania, 1973)
Central Railroad v. P.U.C.
285 A.2d 194 (Commonwealth Court of Pennsylvania, 1971)
New England Telephone & Telegraph Co. v. Department of Public Utilities
275 N.E.2d 493 (Massachusetts Supreme Judicial Court, 1971)
HELLER v. DEPUY
277 A.2d 849 (Commonwealth Court of Pennsylvania, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
222 A.2d 395, 208 Pa. Super. 260, 1966 Pa. Super. LEXIS 837, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pittsburgh-v-pennsylvania-public-utility-commission-pasuperct-1966.