Pittsburgh, C. & St. L. Ry. Co. v. Keokuk & H. Bridge Co
This text of 155 U.S. 156 (Pittsburgh, C. & St. L. Ry. Co. v. Keokuk & H. Bridge Co) is published on Counsel Stack Legal Research, covering Supreme Court of the United States primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
15 S.Ct. 42
39 L.Ed. 106
PITTSBURGH, C. & ST. L. RY. CO. et al.
v.
KEOKUK & H. BRIDGE CO.
No. 633.
November 19, 1894.
This was a bill in equity, filed in the circuit court of the United States for the Northern district of Illinois by the Keokuk & Hamilton Bridge Company (hereinafter called the 'Bridge Company') against the Pittsburgh, Cincinnati & St. Louis Railway Company (hereinafter called the 'Pittsburgh Company') and the Pennsylvania Railroad Company, to recover deficiencies in tolls for the use of the plaintiff's bridge since March 1, 1883 under a contract, dated January 19, 1869, and modified June 6, 1871, by the Bridge Company with the Columbus, Chicago & Indiana Central Railway Company (hereinafter called the Indiana Central Company) and three other railroad corporations, by which the Briedge Company agreed to build and maintain a railway bridge across the Mississippi river, and granted to these four railroad companies in perpetuity the right to use it for the passage of their trains; and they agreed to pay monthly certain tolls, and, if those should fall below a certain sum, each to pay one-fourth of the deficiency.
This contract was executed by the Indiana Central Company upon the requests in writing of the presidents of the Pittsburgh Company and of the Pennsylvania Company, by which these two companies agreed to 'assume all the liabilities and obligations, and be entitled to all the benefits, of said bridge contract, the same as if it had been specifically named and made a part of the ninth article of' a lease of the Indiana Central Company to and with the Pittsburgh Company and the Pennsylvania Company, dated January 22, 1869.
By that lease, the Indiana Central Company leased it railroad to the Pittsburgh Company for 99 years; the Pittsburgh Company covenanted to pay a certain proportion of the earnings of that road to the Indiana Central Company, and, by the ninth article, to assume and carry out, receiving and enjoying the benefits thereof, certain existing concracts for transportation over railroads of other companies not mentioned above; and the Pennsylvania Company guarantied the performance of the covenants of the Pittsburgh Company.
The bridge aforesaid, with the railroads of the Pennsylvania Company, the Pittsburgh Company, the Indiana Central Company, and other railroad companies named in the bridge contract, formed a continuous line of railroad transportation from Philadelphia to Des Moines.
The privisions of the bridge contract and of the lease, and the circumstances attending and following their execution, are more fully set forth in the case between the same parties in 131 U. S. 371, 9 Sup. Ct. 770; but the above abstract is sufficient for the purposes of the present case.
In June, 1871, immediately after the modification of the bridge contract, the bridge was accepted by the Bridge Company and was opened for use, and thenceforward was used by the Pittsburgh and Pennsylvania Companies in the exercise of the control asserted by them under the contract and lease aforesaid. The Bridge Company demanded payment directly from the Pittsburgh Company, semiannually, of the sums payable by the Indiana Central Company for tolls and deficiencies under the modified bridge contract; and from June, 1871, to September, 1874, the Pittsburgh Company paid to the Bridge Company the amount both of such tolls and of such deficiencies. After that time, like payments were demanded by the Bridge Company of the Pittsburgh Company, and the tolls, only, paid.
On July 25, 1881, the Bridge Company filed a bill in equity against the Pittsburgh Company and the Pennsylvania Company to recover deficiencies in tolls for the use of the bridge from September 1, 1874.
To that bill the defendants answered that the Indiana Central Company, the Pittsburgh Company, and the Pennsylvania Company never authorized their officers to execute the bridge contract, or to bind them by it, and that the contract was beyond the scope of their corporate powers.
The Pittsburgh Company also, by way of supplemental answer, set up that in 1875 the trustees named in a mortgage made by the Indiana Central Company of its railroad, rights, and franchises, before the execution of the bridge contract, brought a bill in equity to foreclose that mortgage, and were thereupon appointed receivers, and, pursuant to decrees of foreclosure, there were conveyed by the Indiana Central Company to the receivers, and by them on January 10, 1883, sold and conveyed to three individuals, as trustees, for a smaller sum then the debt secured by the mortgage, its road, rights, and franchises, with the right to affirm or disaffirm the lease aforesaid, and the purchasers, on February 21, 1883, notified the Pittsburgh Company that they disaffirmed the lease; and further averred 'that, in accordance with said decrees, possession of said railway property, rights, and franchises has been surrendered to the said purchasers, and that it has been wholly ousted and evicted from all and singular the premises, rights, and franchises leased to it as aforesaid, and it relies upon the cancellation of said lease and the ouster and eviction, as aforesaid, as a full and perfect answer to the relief sought in the bill.'
To those answers a general replication was filed, and the case was referred to a master, who reported that there was due from the Pittsburgh and Pennsylvania Companies to the Bridge Company, as one-fourth part of the deficiency in the receipts of the Bridge Company from September 1, 1874, to March 1, 1883, the sum of $118,076.89; and that the road, rights, and franchises of the Indiana Central Company had been sold and conveyed, as alleged in the supplemental answer of the Pittsburgh Company, to trustees, and by them on March 17, 1883, to the Chicago, St. Louis & Pittsburgh Railroad Company. The circuit court confirmed the master's report, and entered a decree for the Bridge Company for the sum found due; and, on appeals by the Pittsburgh Company and the Pennsylvania Company, that decree was affirmed by this court. 131 U. S. 371, 9 Sup. Ct. 770.
The present bill was filed September 12, 1889, and set forth the proceedings and decree in the former suit. In an amended answer to this bill, the Pittsburgh Company and the Pennsylvania Company set up that the interlocutory decrees in the suit for foreclosure, appointing the receivers and directing a conveyance to them, were subject to the qualification that until further order of the court the receivers should not disturb the possession of the Pittsburgh Company; and that no order was made that they should disturb its possession, until and unless by the decrees of sale; but that, on the contrary, the Pittsburgh Company remained in undisturbed possession of the railroad property of the Indiana Central Company until March 17, 1883, when it was wholly dispossessed of the same and evicted therefrom, and from all rights under the lease, by the Chicago, St.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
155 U.S. 156, 15 S. Ct. 42, 39 L. Ed. 106, 1894 U.S. LEXIS 2261, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pittsburgh-c-st-l-ry-co-v-keokuk-h-bridge-co-scotus-1894.