Pittsburg Steel Foundry v. Pittsburg Steel Co.

72 A. 813, 223 Pa. 430, 1909 Pa. LEXIS 553
CourtSupreme Court of Pennsylvania
DecidedJanuary 21, 1909
DocketAppeal, No. 188
StatusPublished
Cited by3 cases

This text of 72 A. 813 (Pittsburg Steel Foundry v. Pittsburg Steel Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pittsburg Steel Foundry v. Pittsburg Steel Co., 72 A. 813, 223 Pa. 430, 1909 Pa. LEXIS 553 (Pa. 1909).

Opinion

Opinion by

Mr. Justice Potter,

This was an action brought to recover the amount of an award, and also for damages for the breach of a contract. A jury was waived by agreement of the parties, and the case was heard by the court. It appears .from the evidence, that the contract entered into between the plaintiff, the foundry company, and the defendant, the steel company, was an absolutely safe one in so far as the foundry company was concerned, provided it produced the steel ingots in the quantity and of the quality required. It ran no risk of loss, for it was to receive as compensation a profit of fifteen per cent on the actual cost of the materials, labor, fuel, etc., used in making the steel; and the steel company further guaranteed that the aggregate amount of profit which should thus accrue to the foundry company under the contract during the two years for which it was to run, should not be less than $50,000. Even in the event of cancellation, this much was to be secure; for while there was a provision under which the steel company reserved the right to cancel the agreement, it could only do so by paying to the foundry company such a sum as would, with the profit already made under the contract, on steel then delivered, equal the sum of $25,000, or the estimated cost of its investment in facilities for carrying out the contract; and in addition thereto the further sum of $25,000 as a bonus for the privilege of canceling the agreement. So that if it performed its duty, the foundry company was in any event assured of profits under the contract, amounting, at least, to the sum of $50,000, without the risk of loss. The plaintiff was to work substantially upon a percentage basis. The fact that the steel company was to pay the entire cost of all materials, and the cost of manufacturing them into steel, and a profit on the whole to the foundry company, gave to the defendant a vital interest in the securing of the raw materials as cheaply as possible.

The contract was made on June 30, 1899, and provided that deliveries of steel ingots to the defendant company were to commence about October 1 following. But neither the furnaces of the plaintiff company nor the mill of the defendant [436]*436company was ready for operation at that time. The defendant company, however, anticipated that the price of raw material would advance; and, as set forth in the ninth finding of fact by the trial judge, “On August 9, 1899, the defendant authorized the plaintiff to purchase 1,000 tons of scrap for use in producing ingots ‘for our account,’ and from that time until January or February, 1900, a large number of written communications passed between the parties in regard to the purchase of scrap and other melting materials, the defendant company stating that it would require 2,500 tons for each of three months beginning December, 1899, and saying to the plaintiff, ‘You can purchase material to cover same to the best advantage.’ In October the defendant company authorized the plaintiff to purchase for its account 9,000 tons of basic pig iron, which was bought by the plaintiff. The defendant also on the same day authorized the purchase of from 500 to 1,000 tons of scrap; and a large number of other communications of like import passed between the parties, and a considerable amount of melting material was purchased in accordance therewith, the whole amounting to some fifty or sixty thousand dollars worth, in addition to the 9,000 tons of pig iron, which appears to have been sold not long after its purchase.”

There can be no question under the evidence, but that this raw material was all purchased, not only for the benefit of the defendant company, but with its approval, and nearly all of it upon its express request. And if the contract had been carried out, as was contemplated by both parties when it was made, this material would all have been used in the manufacture of ingots for the defendant company. In order to bear part of the burden of purchasing raw material in advance of its need for actual conversion into ingots, the defendant company advanced to the plaintiff the sum of $40,000. This amount would, in the natural course of the transaction, be used as a credit against the value of the ingots, as manufactured and delivered by the plaintiff; but it could make no great difference in the end, whether the money advanced was appropriated specifically to the cost of material or not. This [437]*437was only one of the elements with which the defendant company was properly chargeable under the contract; in addition thereto, as fast as the material was worked up, the cost of manufacture, fuel, etc., and the profit of fifteen per cent thereon, would all be chargeable to the defendant. So that, if the money advanced were applied to the credit of the general account the same result would in the end be reached. All would have gone smoothly no doubt between the parties, had it not been for the change in the market price of steel, which is shown in the twenty-first of plaintiff’s requests for findings of fact, affirmed by the trial judge, and from which it appears, “That at the time the contract between the plaintiff and defendant was made in June, 1899, the market for steel was rapidly rising and continued to rise until about November, 1899, when it began to fall and continued to decline until beginning with June, 1900, and continuing until March, 1901; the defendant company could purchase' open hearth steel billets in the market at an average cost of over twenty dollars per ton less than they were costing the defendant under this contract, when made from the high priced melting materials purchased by the plaintiff on orders of the defendant.” In his opinion, the trial judge further says, “It is very apparent that considering the price of steel in the winter of 1901, it was very greatly to the advantage of the defendant to get rid of the contract, for the reason that it could buy steel at very much lower prices than its cost would be to it under the contract, and there is no apparent reason why the plaintiff should avoid the contract.”

The court below found that the plaintiff was entitled to recover for the value of the ingots actually delivered by it, and which were found to be of such a character that they should have been accepted by the defendant. But he refused to allow for the loss on materials purchased by the plaintiff at-the instance and request of the defendant, to be manufactured into ingots for it, and he also refused to allow as damages for the breaking of the contract, the minimum amount stipulated to be paid by the defendant company in case the contract should be canceled by it. The failure to award damages for the [438]*438breach of the contract seems to us inconsistent with the findings of fact, and with the construction of the contract as set forth in the first conclusion of law by the trial judge, in which he holds that: “The contract is not one for the delivery to the defendant of such an amount of steel ingots as it might choose to order up to one hundred tons a day, but it is only for the ingots required for its use, that is, all that it should use from time to time in operating its twenty-inch mill, which was the only way it could use them.” We agree fully with this conclusion, and in a careful examination of the evidence, we find nothing therein to justify the suggestion that any change was ever made in the terms of the contract; nor do we find any support for the fourth and fifth conclusions of law reached by the'trial judge wherein he holds that the plaintiff did not continue to stand upon the position that it was only obliged to furnish a supply of ingots sufficient to meet the capacity of defendant’s mill.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Porreca v. Freeman
117 F.2d 326 (Third Circuit, 1941)
In Re Oscar Nebel Co.
117 F.2d 326 (Third Circuit, 1941)
Rees v. R. A. Bowers Co.
124 A. 653 (Supreme Court of Pennsylvania, 1924)

Cite This Page — Counsel Stack

Bluebook (online)
72 A. 813, 223 Pa. 430, 1909 Pa. LEXIS 553, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pittsburg-steel-foundry-v-pittsburg-steel-co-pa-1909.