Pitts v. Highland Construction Co.

252 P.2d 14, 115 Cal. App. 2d 206, 1953 Cal. App. LEXIS 1645
CourtCalifornia Court of Appeal
DecidedJanuary 5, 1953
DocketCiv. 15090
StatusPublished
Cited by7 cases

This text of 252 P.2d 14 (Pitts v. Highland Construction Co.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pitts v. Highland Construction Co., 252 P.2d 14, 115 Cal. App. 2d 206, 1953 Cal. App. LEXIS 1645 (Cal. Ct. App. 1953).

Opinion

GOODELL, J.

espondents sued to enjoin an impending trustee’s sale under a deed of trust securing a promissory note for $4,304.21 given by respondents to appellants and with the ultimate purpose of effecting the cancellation of both instruments. A temporary injunction issued and after a trial judgment was entered decreeing that the note be de *207 livered up for cancellation and the deed of trust released of record. A new trial was denied and this appeal was taken.

Plaintiff, a World War veteran, owned a parcel of land in Contra Costa County on which he desired to build a four-room home by availing himself of a “G. I.” loan.

He applied to the Walnut Creek Branch of American Trust Company, which agreed after the. usual processing to lend him $8,975 on a first deed of trust, $4,000 of which would be insured or guaranteed to the bank by the Veterans’ Administration. The $8,975 figure was based on an estimate made by an appraiser designated by the Veterans’ Administration fixing the reasonable value of the land plus the proposed dwelling (according to Pitts’ plans) at $11,475. As a condition to its loan the bank required a contract between a responsible builder and the owner fixing a definite cost price. Pitts then laid the matter before Osmundsen, by whom he was then employed as foreman carpenter, who agreed to enter into such contract with him. On May 24, 1948, a “builder’s contract” was drawn up on a printed form (filled in with typewriting) signed by Pitts as owner, and Highland Construction Company as contractor, whereby the contractor agreed within the space of 150 days “from and after approval by lending agency and authorization to commence work to supply the necessary labor and materials required, and furnish and supply all necessary tools, implements and appliances, and perform and complete in a workmanlike manner the following described building or other work, to-wit: all the work described in the plans known as plans for residence for Mr. Harry E. Pitts.”

The owner agreed therein “in consideration of the performance of this agreement by the contractor, to pay as hereinafter suecified, at the times and to the party or parties and in the amounts and manner following, to wit:

“To the contractor:—A total of . . . $8,975.00 ... in five (5) equal payments of . . . $1,795.00 . . . each, as follows: “First—When sub-floor is complete “Second—When roof is on “Third—When ready for finish “Fourth—When complete
“Fifth—When lien period has been accounted for.

Any and all extras ordered by the owner after signing this contract are to be paid for on or before completion.”

*208 The difficulty in this case arises from a letter typewritten in Osmundsen’s office on Highland stationery, dated May 24, 1948, reading as follows:

“Mr. Harry E. Pitts Walnut Creek California
“Dear Mr. Pitts:
“In connection with the contract between yourself and Highland Construction Co. dated May 24, 1948, for the purpose of constructing a residence to be located in the Saranap Area, Contra Costa County, according to the plans drawn and titled ‘Residence for Mr. Harry E. Pitts’—
“The following is the understanding. The owner, Mr. Harry E. Pitts, will furnish all the carpentry labor and other labor and all the brick and brick-work necessary to complete the plan. The contractor, Highland Construction Co. will furnish all other work and materials and arrange for all subcontracting work to be completed in good order.
“For this, the contractor will charge the owner the cost of this work plus the usual contractor’s profit of ten percent and one and one-half percent for overhead cost. Any difference between the total of these amounts and the contract price will be paid to the owner.
“This agreement is in conjunction with and considered a part of said contract dated May 24, 1948
Highland Construction Co.
O. A. Osmundsen “Acknowledge—Harry E. Pitts”

During the negotiations there was lodged with the bank a copy of the formal contract. Pitts testified that during the negotiations he told one of the bank’s officers in at least two conversations that he was “going to furnish the labor and some of the materials on the house” but when asked at the trial whether he had said “that money [meaning for his services] was not to be paid out of the loan” he answered in the negative. The court found: “It is true that on the same day, May 24 . . . Osmundsen . . . without the knowledge of the bank ... or of the United States Government, delivered a letter to plaintiff . . . setting out an ‘understanding’ that by its terms was made a part of the builder’s contract dated the same day ...”

The $4,304.21 note and deed of trust were obtained as *209 follows: the dwelling was completed and occupied about Thanksgiving Day, 1948, and by February 7, 1949, appellants had computed the total cost of labor, materials, overhead and profit at $13,127.69. Deducting the $8,823.48 received by them from the owner through the bank loan, a difference remained of $4,304.21. On February 7, 1949, Osmundsen sent an associate to the home of respondents and had them execute the note and deed of trust. On March 22, 1949, the latter instrument was recorded and became a lien on respondents’ property junior to the bank’s deed of trust.

The respondents’ unquestioned obligation to the bank was $8,975 and on this second note the obligation now in question of $4,304.21, brought the total cost of the building up to $13,279.21.

Section 694a of the Servicemen’s Readjustment Act (38 U.S.C.A. § 694 et seq.) prescribes as one of the conditions of the government guaranty: “ (3) That the price paid or to be paid by the veteran for such property or for the cost of construction . . . does not exceed the reasonable value thereof as determined by proper appraisal made by an appraiser designated by the Administrator.” Under such appraisal, as already appears, the maximum allowable cost was fixed at $11,475, hence the two obligations exceeded that “ceiling” by $1,804.21.

There is no question that the letter of May 24 was not shown to the bank. It follows that the bank made the loan in reliance on the face of the formal contract and that the Veterans’ Administration made its guaranty of $4,000 to the bank on the same showing. The letter was incompatible with the formal contract since the former called for a “cost-plus” job while the latter bound the contractor to build the house for $8,975 and no more.

Appellants argue that the parties anticipated that the total cost would be under $8,975, and certainly well under $11,475. However, it turned out otherwise (See Elmers v. Shapiro, 91 Cal.App.2d 741, 752 [205 P.2d 1052]).

In our opinion this case is controlled by Young v. Hampton, 36 Cal.2d 799 [228 P.2d 1, 19 A.L.R.2d 830].

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kipperman v. Dixson (In re Diego's Inc.)
88 F.3d 775 (Ninth Circuit, 1996)
Chuidian v. Philippine National Bank
734 F. Supp. 415 (C.D. California, 1990)
South Tahoe Gas Co. v. Hofmann Land Improvement Co.
25 Cal. App. 3d 750 (California Court of Appeal, 1972)
Ulene v. Jacobson
209 Cal. App. 2d 139 (California Court of Appeal, 1962)
Fleming v. Kagan
189 Cal. App. 2d 791 (California Court of Appeal, 1961)
Lewis v. Wainscott
268 P.2d 835 (California Court of Appeal, 1954)

Cite This Page — Counsel Stack

Bluebook (online)
252 P.2d 14, 115 Cal. App. 2d 206, 1953 Cal. App. LEXIS 1645, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pitts-v-highland-construction-co-calctapp-1953.