Pittman Contracting Co. v. City Home Builders, Inc.

30 So. 2d 426, 211 La. 549, 1947 La. LEXIS 778
CourtSupreme Court of Louisiana
DecidedApril 21, 1947
DocketNo. 38231.
StatusPublished
Cited by1 cases

This text of 30 So. 2d 426 (Pittman Contracting Co. v. City Home Builders, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pittman Contracting Co. v. City Home Builders, Inc., 30 So. 2d 426, 211 La. 549, 1947 La. LEXIS 778 (La. 1947).

Opinion

McCALEB, Justice.

This controversy grows out of the leasing of a crane by the plaintiff contracting company to the defendant. Each party claims that the other has defaulted in its obligation and that it has sustained damage *552 as a result. The events which brought about the dispute are as follows:

On December 10, 1943, plaintiff leased to the defendant, a corporation engaged in a house building enterprise in the Third District of the City of New Orleans, a diesel driven dragline (or crane), a hopper plant including scales and a concrete mixer for the sum of $1500 a month with a minimum rental guarantee of two months. Immediately after the crane had been put to use by defendant, its starter broke and, following a disagreement between the parties as to whether the starter was defective or whether defendant’s mechanic had stripped it, plaintiff agreed to allow defendant to use another crane of the same make (Koehring), which was driven by gasoline instead of diesel oil. Defendant accordingly obtained the crane and put it to work at the housing project. This was in December 1943 but it was not long before labor trouble occurred which had considerable effect upon the events which follow.

It appears that defendant had been employing non-union labor at its project, whereas, plaintiff was an employer of union labor. In January 1944, the New Orleans Building and Construction Trades Council sent a telegram to plaintiff advising it that the Council had voted to withdraw all union labor from all of its jobs unless the equipment rented to defendant was taken off of defendant’s project. As soon as plaintiff was advised of the attitude of the'labor union, it contacted the defendant but the latter insisted on keeping the equipment. Subsequently on February 24, 1944, after many conferences between plaintiff, defendant and the labor union, plaintiff agreed to an extension of the lease to March 10th 1944 but insisted upon the return of its machinery on that day. However, defendant did not return the crane on March 10th, and it remained in defendant’s use and possession until April 22nd, when plaintiff went upon defendant’s land and removed it.

After plaintiff had retrieved the crane from defendant’s property, many claims and counter-claims were made by the parties against each other. Defendant was much aggrieved by plaintiff’s action and plaintiff claimed that it was damaged because defendant had failed to return the crane upon request. Finally, on April 29, 1944, the parties composed their differences by an agreement of compromise. This contract recited, in substance, that, whereas a dispute had arisen respecting the term of the rental agreement of December 10, 1943, the parties, in order to settle their differences and to eliminate the possibility of litigation, agreed that

(1) A “P & H” Crane (which was a much heavier crane) would be substituted for the “Koehring” crane which had been removed by plaintiff;

(2) That plaintiff would construct mats on which the heavier crane would run and that the construction cost of these mats would be borne equally by the parties;

*554 (3) That the rental agreement, as amended, would expire on June 10, 1944, and that credit for rental would be given to defendant for the delay resulting from the construction of the mats. In other words, defendant would be given credit for $50 per day on account of the $1500 monthly rental for each day the crane could not be used during the time the mats were being constructed.

After defendant had signed the compromise contract, its attorney, by letter of May 3, 1944, addressed to the attorney for plaintiff, stated that, whereas he had approved the contract, he would like to supplement it with certain stipulations concerning the acceptance of the P & H Crane to be furnished to defendant. The substance of these stipulations, which were ^approved by plaintiff, is as follows:

(1) That the crane would not be finally accepted by the defendant until it had been operated at defendant’s site for a period of three hours on the mats which were to be constructed by plaintiff. (It was stated in the letter of defendant’s attorney that Mr. Wilson, defendant’s contractor, had examined the machine; that it appeared to be in good order but that it was feared that, because of its weight, it could not be fully operated unless it was run on mats) ;

• (2) That representatives of the plaintiff would be required to place the machine on the mats at the site where it was to be used as Mr. Wilson was not willing to assume this responsibility because of the heavy and unusual weight of the machine, and

(3) That, at the termination of the lease, plaintiff would be required to move the machine from the site at its own expense.

After the crane had been delivered to defendant’s project by plaintiff, defendant refused to pay the rental thereon, contending that the machine was not in good working order and unfit for the purpose for which it was leased.

Plaintiff, on the other hand, maintained that the crane had been tested in accordance with the supplemental agreement of May 3, 1944, and that it had complied with all of the obligations imposed upon it by the 'lease. Thereafter, plaintiff brought this suit to recover rent and other damages sustained by it, allegedly resulting from defendant’s breach of contract. The items of damage, amounting to the total of $6611.14, claimed by plaintiff in its petition are

(a) $650, representing rent due by defendant for use of the “Koehring” crane from April 10th through April 22nd at $50 per day;

(b) $1500, rent of “P & H” Crane from May 10 to June 10, 1944;

(c) $1500, loss of use of P & H Crane for additional month due to defendant’s failure to return the equipment;

(d) $2100, damages resulting from defendant’s refusal to deliver the concrete *555 mixer to plaintiff for six months, despite repeated demands. (This item is based on a rental for the mixer of $350 per month) ;

(e) $350, representing damage to the concrete mixer resulting from defendant’s failure to keep it in good order;

(f) $162, damages sustained to the “P & H” Crane while in defendant’s possession, and

(g) $349.14, representing one-half of the actual cost of construction of the mats provided for in the compromise agreement of April 29, 1944.

Defendant resisted the demand on the ground that the compromise agreement was conditioned upon plaintiff’s representation that the “P & H” Crane would be in good mechanical working order and fit for the purposes for which it was rented; that the crane was never in good order and that, therefore, the consideration failed. Defendant, however, admitted that it was indebted to plaintiff in the sum of $650 for rent of the “Koehring” crane from April 10 to April 22, 1944, and also that it owed plaintiff the sum of $350 for use of the concrete mixer for one month for which rent had not been paid.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ginlee v. Helg
203 So. 2d 714 (Supreme Court of Louisiana, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
30 So. 2d 426, 211 La. 549, 1947 La. LEXIS 778, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pittman-contracting-co-v-city-home-builders-inc-la-1947.