Pitt v. Quanta Bldg. Group

2024 Ohio 2297, 246 N.E.3d 612
CourtOhio Court of Appeals
DecidedJune 17, 2024
Docket22CA011904
StatusPublished
Cited by2 cases

This text of 2024 Ohio 2297 (Pitt v. Quanta Bldg. Group) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pitt v. Quanta Bldg. Group, 2024 Ohio 2297, 246 N.E.3d 612 (Ohio Ct. App. 2024).

Opinion

[Cite as Pitt v. Quanta Bldg. Group, 2024-Ohio-2297.]

STATE OF OHIO ) IN THE COURT OF APPEALS )ss: NINTH JUDICIAL DISTRICT COUNTY OF LORAIN )

SHANE PITT C.A. No. 22CA011904

Appellee

v. APPEAL FROM JUDGMENT ENTERED IN THE QUANTA BUILDING GROUP, LLC. COURT OF COMMON PLEAS COUNTY OF LORAIN, OHIO Defendant CASE No. 18CV195173

and

J.C. JONES CORP.

Appellant

DECISION AND JOURNAL ENTRY

Dated: June 17, 2024

SUTTON, Judge.

{¶1} Defendant-Appellant J.C. Jones Corp. appeals from the judgment of the Lorain

County Court of Common Pleas. This Court affirms.

I.

{¶2} This action arose from the construction of a garage to house a private automobile

collection in Avon Lake, Ohio (“the Avon Lake project.”). Cupco LLC purchased the land in

Avon Lake, and subsequently hired a general contractor, Fortney & Weygandt, Inc., to serve as

the general contractor for the project. Fortney & Weygandt, Inc., contracted with J.C. Jones

Corporation (“Jones Corp.”) to construct part of the outer garage structure. Jones Corp. was

selected for the project because the company had experience in building such structures. Jones 2

Corp. then contracted with Quanta Building Group, LLC (“Quanta”), a Texas based company, to

supply the labor to put together the building. Quanta then contracted with Shane Pitt, also of

Texas, to supply labor for the project. Cupco LLC and Fortney & Weygandt, Inc., were not parties

to this lawsuit.

{¶3} Construction at the Avon Lake project commenced in 2018. Mr. Pitt entered into

a contract with Quanta for $180,000.00 to supply labor for the construction of the skeleton of the

steel building structure. When Mr. Pitt began working at the project site, the project was already

3-4 weeks behind due to delays in securing materials and problems with the site. Mr. Pitt and his

crew began working in May. At the end of the month, Mr. Pitt sent a request to Quanta to be paid

$54,000.00, and Quanta approved and paid that request. Mr. Pitt sent a similar request to Quanta

for $64,350.00 that was also approved and paid by Quanta in June.

{¶4} In July, Alex Vallardes, the owner of Quanta, found out that Mr. Pitt had contracted

directly with Jones Corp. on a separate upcoming project in Twinsburg, Ohio. Thereafter, when

Mr. Pitt sent a request to Quanta for the July payment of $40,050.00 for the Avon Lake project, he

received an email from Quanta informing him that his request would be approved and a check

would be sent. However, according to Mr. Pitt’s testimony, Mr. Vallardes did not provide payment

to Mr. Pitt for July, for the work Mr. Pitt’s did on the Avon Lake project, because Mr. Vallardes

was upset that Mr. Pitt directly contracted with Jones Corp. on the Twinsburg project. On August

2, 2018, Quanta sent a letter to Mr. Pitt alleging he was in breach of contract for the work he

contracted to do on the Avon Lake project.

{¶5} The same day that Quanta sent the letter, Mr. Pitt also called Jim Jones, the owner

of Jones Corp., regarding the July payment due to him from Quanta. Mr. Pitt recorded that phone

conversation. During the phone call, Mr. Jones assured Mr. Pitt that Quanta was going to pay him. 3

When Mr. Pitt mentioned his desire to file a lien on the project, Mr. Jones told Mr. Pitt that filing

a lien would “just fuck[] up everything[.]” Mr. Jones told Mr. Pitt that Quanta assured Mr. Jones

that Mr. Pitt will get paid. Mr. Jones then said, “I’ll make sure that you get paid off[,]” and told

Mr. Pitt “so don’t [file a lien] right away. There’s lots of time to do that. But I’ll talk to him and

make sure you get what’s owed to you[.]”

{¶6} After receiving no payment for his July work from Quanta or Mr. Jones, Mr. Pitt

filed the current action in the Lorain County Court of Common Pleas. Mr. Pitt’s amended

complaint alleged causes of action against Jones Corp. for breach of contract and promissory

estoppel. The amended complaint also alleged several causes of action against Quanta. Quanta

initially appeared and answered the claim, but eventually counsel for Quanta withdrew and Quanta

ceased to participate in the litigation.

{¶7} The case proceeded to a bench trial. In lieu of closing arguments, the trial court

asked the parties to submit bench briefs on the issues before the court. After considering the

evidence and the record, the trial court issued judgment for Jones Corp. on Mr. Pitt’s claim for

breach of contract and judgment for Mr. Pitt, and against Jones Corp., on the promissory estoppel

claim.

{¶8} Jones Corp. timely appealed, assigning two errors for this Court’s review.

II.

ASSIGNMENT OF ERROR I

THE TRIAL COURT ERRED BY ENTERING JUDGMENT FOR [MR.] PITT ON HIS CLAIM FOR PROMISSORY ESTOPPEL[.]

{¶9} In its first assignment of error, Jones Corp. argues the trial court erred by finding in

favor of Mr. Pitt on his claim for promissory estoppel. Specifically, Jones Corp. argues: 1) there

was no clear and unambiguous promise; 2) there was no reliance to Mr. Pitt’s detriment; 3) Mr. 4

Pitt, in not filing a mechanic’s lien, did not establish reliance; 4) Mr. Pitt breached his subcontract

with Quanta; and 5) Mr. Pitt suffered no damages based upon his reliance. For the following

reasons, we disagree.

Elements of Promissory Estoppel

{¶10} Promissory estoppel is not a contractual theory, but a quasi-contractual or equitable

doctrine designed to prevent the harm resulting to the promisee from the reasonable and

detrimental reliance on a promise made by the promisor. Karnes v. Doctors Hosp., 51 Ohio St.3d

139, 142 (1990). “The elements necessary to establish a claim for promissory estoppel are ‘a

promise, clear and unambiguous in its terms; reliance by the party to whom the promise is made;

that the reliance was reasonable and foreseeable; and that the party claiming estoppel was injured

by the reliance.’” Jones v. BPR/RICO Mfg., Inc., 9th Dist. Medina No. 20CA0084-M, 2022-Ohio-

2715, ¶ 6, quoting Davis v. Cinnamon Lake Assoc., Inc., 9th Dist. Wayne No. 19AP0052, 2020-

Ohio-5374, ¶ 24, quoting Rigby v. Fallsway Equip. Co., Inc., 150 Ohio App.3d 155, 2002-Ohio-

6120, ¶ 25 (9th Dist.).

A promise, clear and unambiguous in its terms.

{¶11} Jones Corp. argues there was no clear and unambiguous promise because “Quanta’s

subcontract with Jones [Corp.]* * * required Quanta to bond off any lien claim asserted by any

subcontractor to Quanta[,]” therefore, “[i]n this context[,] [Mr. Jones’] talk about no liens with

[Mr.] Pitt meant that a bond can replace a lien against the property[.]” In response, Mr. Pitt argues

the recorded conversation demonstrates a clear and unambiguous promise made by Mr. Jones to

pay Mr. Pitt.

{¶12} A review of the record shows that during the August 2, 2018 phone call between

Mr. Pitt and Mr. Jones, recorded by Mr. Pitt, Mr. Jones said: 5

As far as liens, I’ll make sure you get paid off before there’s any liens on the job, so don’t do that right away. There’s lots of time to do that. But I’ll talk to [Quanta] and make sure you get what’s owed to you, if that’s how it ends up.

Therefore, the record demonstrates there was a clear and unambiguous promise made by Mr. Jones

to see that Mr. Pitt would get paid, a promise Mr. Jones did not keep when he negotiated his own

settlement with Quanta.

Reliance by the party claiming estoppel.

{¶13} Here, Mr. Pitt is the party claiming estoppel. Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2024 Ohio 2297, 246 N.E.3d 612, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pitt-v-quanta-bldg-group-ohioctapp-2024.