This text of Pitney Bowes Inc. v. Acro Service Corp. (Pitney Bowes Inc. v. Acro Service Corp.) is published on Counsel Stack Legal Research, covering District Court, D. Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pitney Bowes Inc. v. Acro Service Corp., (D. Conn. 2023).

Opinion

UNITED STATES DISTRICT COURT DISTRICT OF CONNECTICUT PITNEY BOWES INC., ) Plaintiff, ) ) v. ) ) 3:22-CV-337 (OAW) ACRO SERVICE CORP., ) Defendant/Third-Party Plaintiff, ) ) v. ) ) VITALITY STAFFING SOLUTIONS, ) LLC, ) Third-Party Defendant. OMNIBUS ORDER This action is before the court upon the Motion for Leave to File Third-Party Complaint filed by Defendant Acro Service Corporation (“Acro Motion”), see ECF No. 31, and the Amended Motion to Modify the Case Management Order1 filed by Third-Party Defendant Vitality Staffing Solutions, LLC (“Vitality Motion” and, together with the Acro Motion, “Motions”), see ECF No. 34.2 The court has reviewed the Motions and the record in this case and is fully advised in the premises. This case arises from a contract between Plaintiff and Defendant Acro Service Corporation (“Acro”) under which Acro was responsible for providing temporary laborers at certain of Plaintiff’s facilities. ECF No. 1 at ¶¶ 14–16. The contract obligated Acro to ensure that all the temporary laborers were legally able to work in this country. Id. at ¶¶ 18–19. Acro, in turn, subcontracted to Third-Party Defendant Vitality Staffing Solutions,

1 The Vitality Motion appears to be identical to an earlier motion filed for the same relief, see ECF No. 30, except that the amended version includes certain expert discovery deadlines which were not included in the original motion. The court disregards the earlier version of the motion. 2 In Plaintiff’s response to the Motions, it also moved to compel Acro to cooperate in certain depositions. They have resolved that dispute, see ECF No. 40, and so the court will not discuss the motion to compel. LLC (“Vitality”), to provide the laborers, and it is alleged that Acro’s contractual obligation with respect to checking the legal status of the laborers was “flowed down” to Vitality. Id. at ¶¶ 27–30. Plaintiff discovered that some of the leased laborers did not possess the documentation necessary to work in the United States, and this dispute ensued. Id. at ¶ 32–33. Plaintiff initiated this action against Acro on March 2, 2022. Id. On May 12, 2022,

Acro filed a third-party complaint against Vitality. See ECF No. 17. On April 18, 2022, the court issued a general scheduling order that required discovery to be completed by December 31 (some eight months later). See ECF No. 13. Vitality waived service on May 16, 2022, see ECF No. 19, and answered the third-party complaint on June 15, 2022, see ECF No. 23. Discovery proceeded for the next several months. Then, on December 1, 2022, Acro filed the Acro Motion, seeking leave to implead an additional party: Zurich American Insurance Company (“Zurich”), who issued Vitality certain insurance policies under which Acro alleges it was an additional insured party. On the same day, Vitality filed the original version of the Vitality Motion, which it

amended on December 11, 2022. See ECF Nos. 30 and 34. Vitality seeks an additional four months of time to complete discovery, noting that it joined this action several months after the other parties and did not participate in the drafting of the Local Rule 26(f) report, which became the basis for the court’s scheduling order. Plaintiff opposes both Motions.

I. Acro’s Motion Seeking To Implead (Insurer) Zurich “The decision whether to permit a defendant to implead a third-party defendant is committed to the sound discretion of the trial court.” Chiaravallo v. Middletown Transit Dist., No. 3:18-CV-1360 (SRU), 2022 WL 3369722, at *1 (D. Conn. Aug. 16, 2022) (citing Kenneth Leventhal & Co. v. Joyner Wholesale Co., 736 F.2d 29, 31 (2d Cir. 1984)). And courts should consider several factors, including: “(a) whether the moving party deliberately delayed or was derelict in filing the motion; (b) whether impleading would unduly delay or complicate the trial; (c) whether impleading would prejudice the plaintiff or the third-party defendant; and (d) whether the proposed third-party complaint states a

claim upon which relief can be granted.” Hughes v. Target Brands, Inc., No. 3:17-CV- 00270 (VAB), 2018 WL 2722460, at *2 (D. Conn. June 6, 2018). Acro asserts that these factors weigh in favor of granting the motion, but Plaintiff disagrees. Plaintiff argues that Acro was derelict in seeking to implead Zurich, and that impleader at this point in litigation would cause undue delay. It is common for insurers to be impleaded in civil actions since it is Rule 14’s “primary role” to address questions of indemnification. See St. Paul Ins. Co. v. Regal Ware, Inc., No. 504CV0276NPMGHL, 2006 WL 8453616, at *3 (N.D.N.Y. May 19, 2006). Consequently, the proposed third-party complaint states a cognizable claim. Additionally,

the court has subject matter jurisdiction over the third-party complaint. See Mar-Cone Appliance Parts Co. v. Mangan, 879 F. Supp. 2d 344, 357 (W.D.N.Y. 2012) (“Third-party claims by defendants for contribution against a third-party under Federal Rules of Civil Procedures 14(a) generally . . . fall within the court’s supplemental jurisdiction if the impleaded defendant’s actions share a ‘common nucleus of operative fact’ with the case already before the court.”) (quoting Grimes v. Mazda North American Operations, 355 F.3d 566, 572 (6th Cir.2004)) (alteration in original). However, the court finds that Acro has failed to implead Zurich in a reasonably timely manner. Acro has known since months before this action was initiated that Zurich was a related party. While Acro admits that it first contacted Zurich as early as November 2021, see ECF No. 31-1 at 4, it did not seek to implead Zurich until a year later, even as it impleaded a different third-party defendant in March 2022, see ECF No. 17. Acro asserts that it was awaiting Zurich’s response to its demand letters, but a delay in impleading Zurich was not necessary on that basis. To the contrary, impleading Zurich

likely would have forced an earlier response. Moreover, it appears that Zurich responded to Acro’s first demand letter in May 2022 (in it, the court presumes Zurich declined Acro’s request), but Acro still did not implead Zurich at that time. See ECF No. 31-1 at 4. Instead, Acro sent Zurich a second demand letter in August 2022, to which Zurich unsurprisingly again replied in the negative in October 2022. Id. Yet Acro still waited another two full months before filing the Acro Motion. Furthermore, the court finds that impleader would unduly delay and complicate the disposition of this matter. Acro asserts that the duty-to-defend issue could be managed with motion practice alone, but even that motion practice itself would cause a delay of several months, and discovery still could be required on that issue.3 And if all goes as

Acro wishes, and Zurich is required to defend in this action, Zurich likely will require additional time to do its own due diligence, even with respect to just the discovery that Acro has requested of Plaintiff. And while the court acknowledges that there is no ongoing injury to Plaintiff (such that any recovery which may be due to Plaintiff only would be delayed and not compounded), any delay in Plaintiff’s potential recovery would negate the conservation of judicial resources which impleader is intended to produce.

3 The court notes that there appears to be an ongoing contract dispute between Vitality and Acro in state court in New Jersey. It is unclear how that contractual dispute might impact the duty to defend that Zurich allegedly owes Acro, but the specter of comity issues presented in the Acro Motion also weighs against allowing impleader. II.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mar-Cone Appliance Parts Co. v. Mangan
879 F. Supp. 2d 344 (W.D. New York, 2012)
Kenneth Leventhal & Co. v. Joyner Wholesale Co.
736 F.2d 29 (Second Circuit, 1984)