Pipemasters, Inc. v. Putnam County Commission

625 S.E.2d 274, 218 W. Va. 512, 2005 W. Va. LEXIS 170
CourtWest Virginia Supreme Court
DecidedDecember 2, 2005
Docket32667
StatusPublished
Cited by5 cases

This text of 625 S.E.2d 274 (Pipemasters, Inc. v. Putnam County Commission) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pipemasters, Inc. v. Putnam County Commission, 625 S.E.2d 274, 218 W. Va. 512, 2005 W. Va. LEXIS 170 (W. Va. 2005).

Opinion

The Opinion was delivered PER CURIAM.

• PER CURIAM.

This case arises from a dispute over the installation of a waterline in rural Putnam County. After a three and one-half week jury trial, a verdict was rendered in favor of Pipemasters, Inc., plaintiff below/appellee. The West Virginia-American Water Company and the Putnam County Building Commission appeal the decision of the trial court in denying post trial motions. For the reasons stated herein we affirm.

I.

In the late 1990s the Putnam County Building Commission (“Commission”) began working on a project to extend water service in rural Putnam County. In total there were seven Putnam County waterline projects; the waterline extension in dispute in this case was one of those projects.

The Commission selected West Virginia-American Water Company (“Water Company”) to serve as project engineer. The Water Company hired HNTB Corporation (“HNTB”) to design the lines and to work as project inspector. The Commission hired Pipemasters, Inc. (“Pipemasters”) to install the lines in accordance with a written contract. Mid-State Surety (“Mid-State”) issued a performance bond to secure Pipemas-ters’ installation of the lines.

The Commission and the Water Company entered into an operation and maintenance agreement wherein the Water Company would be responsible for the operation, maintenance, repair and replacement of the waterlines, and the Water Company would be paid for the water supplied to customers.

A critical part of the contract in dispute involves the construction of the waterline longitudinally along a Department of Highways (“DOH”) right-of-way. The Commission, as owner of the project, applied to the DOH for a permit to enter upon, under, over or across relevant state roads and rights-of-way. The DOH permit included the condition that “[ujtility installation shall be in accordance with the current manual, Accommodation of Utilities on Highway Rights-of-Way.’” The contract required Pipemasters *515 to install the waterline according to the DOH manual, and with a minimum of forty-two inches of cover unless otherwise authorized.

Pipemasters worked from February to May 2000 installing the waterline. Inspections were regularly made by HNTB and the DOH. The right-of-way restoration was apparently completed to the satisfaction of the DOH as of May 2000. None of the parties objected to the quality of work performed by Pipemasters as of May 2000. Additionally, during this period Pipemasters submitted seven periodic pay estimates which, before payment could be made, had to be approved by both the Water Company and HNTB. All seven periodic pay estimates contained certifications by the Water Company and HNTB that the work had been performed in accordance with the contract. All pay estimates were paid. Pipemasters was paid for all of the contract bid price, except for $33,659.78 retainage.

In May 2000, after the installation had been completed and service to some customers had commenced, Pipemasters was required to perform some reditching on the DOH right-of-way. The reditching was required by a DOH supervisor who had not been previously involved with the project. In late 2000, the Water Company discovered that some sections of the waterlines had less than the required forty-two inches of cover. At the request of the Water Company, HNTB reviewed the matter and HNTB recommended that test holes be dug to determine to what extent any waterlines had less than forty-two inches of cover. The test holes confirmed that in a number of locations the waterline did have less than the specified forty-two inches.

The Water Company then requested Pipe-masters to re-lay those sections of the waterline with less than the required cover. Pipe-masters began re-laying the waterlines and submitted invoices for its work. On March 4, 2002, Pipemasters was paid $37,753.52, 1 and on March 5, 2002, appellants terminated the contract with Pipemasters — before the relaying of the waterline was completed. The Commission then authorized the Water Company to undertake the completion of re-laying waterlines that had inadequate cover.

On September 11, 2002, Pipemasters filed a lawsuit against the Commission in the circuit court of Putnam County, alleging breach of contract and an implied contract for the additional work Pipemasters had performed. Pipemasters’ complaint also included a claim against the Water Company for negligence. The Commission filed an answer to the complaint and countersued Pipemasters. The Commission also filed a third-party complaint against HNTB and Mid-State alleging breach of contract, negligence, and breach of duties under a performance bond. The Water Company filed a third-party complaint against HNTB for alleged breach of duties owed to the Water Company relating to inspections. HNTB filed its answers, and also filed a third-party counterclaim against the Water Company for failing and refusing to pay HNTB’s invoices for work performed. 2 Mid-State responded to the litigation with claims against Pipemasters and Pipemasters’ guarantors. 3 Before trial, the Commission assigned its claims to the Water Company and the Water Company agreed to hold the Commission harmless beyond remaining project funds.

A three and one-half week jury trial begain on January 28, 2004. The jury found that Pipemasters satisfactorily completed its obligation under the contract, and that Pipemas-ters was entitled to be compensated for work performed beyond its obligation under the original contract. The jury awarded Pipe-masters $390,446.29. 4 The juiy also rejected the Commission’s and the Water Company’s counterclaims against Pipemasters as well as *516 their third party claims. 5

Following the jury verdict, a joint motion *517 for judgment as a matter of law and for a new trial was filed by the Commission and the Water Company. The joint motion was denied by the trial court. It is from this order that the appellants appeal to this Court for relief.

II.

The appellants assign as error: (1) the trial court erred in denying the joint motions for judgment as a matter of law and for a new trial as to the claims of Pipemasters; (2) the trial court erroneously instructed the jury on the law of suretyship; and (3) the tidal court erred in denying the motion of the Water Company for a new trial as to the Water Company’s counter-claims and third-party claims (including those claims assigned to it by Commission).

Appellants brought their motion for judgment as a matter of law and for a new trial under Rules 50(b) and 59(a) of the West Virginia Rules of Civil Procedure.

We are first asked to review the circuit court’s order denying a post-verdict motion for judgment as a matter of law. In Syllabus Point 3 of Brannon v. Riffle, 197 W.Va. 97, 475 S.E.2d 97 (1996), this Court stated:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stevenson v. Independence Coal Co., Inc.
709 S.E.2d 723 (West Virginia Supreme Court, 2011)
James v. Knotts
705 S.E.2d 572 (West Virginia Supreme Court, 2010)
Fredeking v. Tyler
680 S.E.2d 16 (West Virginia Supreme Court, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
625 S.E.2d 274, 218 W. Va. 512, 2005 W. Va. LEXIS 170, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pipemasters-inc-v-putnam-county-commission-wva-2005.