Pipe Systems, Inc. v. American Manufacturers Mutual Insurance

609 F. Supp. 571, 1985 U.S. Dist. LEXIS 21627
CourtDistrict Court, E.D. Missouri
DecidedMarch 19, 1985
DocketNo. 84-2584C(A)
StatusPublished
Cited by2 cases

This text of 609 F. Supp. 571 (Pipe Systems, Inc. v. American Manufacturers Mutual Insurance) is published on Counsel Stack Legal Research, covering District Court, E.D. Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pipe Systems, Inc. v. American Manufacturers Mutual Insurance, 609 F. Supp. 571, 1985 U.S. Dist. LEXIS 21627 (E.D. Mo. 1985).

Opinion

MEMORANDUM AND ORDER

HARPER, District Judge.

This matter is before the Court on the defendant’s motion to dismiss .for lack of jurisdiction and improper venue pursuant to Rule 12(b)(1) and 12(b)(3) Federal Rules of Civil Procedure.

Plaintiff is a Missouri corporation engaged in the business of furnishing pipe and other materials for construction and maintains its principal place of business in St. Louis County, Missouri. Plaintiff alleges that defendant is a corporation organized and existing under the laws of a state other than Missouri and maintains its principal place of business in the State of Illinois.

In the complaint, plaintiff alleges that it sold materials and furnished equipment to a contractor who was constructing a sewage collection facility in Iberia Parish, Louisiana. The contractor had entered into a contract with Sewage District No. 1 of Iberia Parish, Louisiana for the construction of that project. As required by the Louisiana Public Works Act La.R.S. 38:2241 et seq., the contractor obtained a public works bond. Defendant, as surety, issued the bond in the amount of $607,-553.50. Defendant’s liability under the bond matures in the event that the contractor defaults on its obligation to finish the project and to pay for labor and materials used on the project.

Plaintiff alleges that the contractor is in default of its obligations and that defendant, therefore, is required to pay sums due and owing plaintiff pursuant to the terms of the bond. Defendant acknowledges plaintiff’s claim, but disputes the amount claimed by plaintiff.

Defendant’s brief supporting its motion to dismiss asserts that plaintiff’s action should be dismissed by this Court for lack of jurisdiction and improper venue because suit has not been filed “ * * * in the proper court of the parish where the work was done * * * ” as required by the Louisiana Public Works Act § 2243, La.R.S. 38:2243. Defendant asserts that the Louisiana Public Works Act proscribes an exclusive procedure for resolving claims against the statutorily required public works bond.

[573]*573Plaintiff contends that the statutory procedure proscribed by § 2243 of the Act is not mandatory; and further, that the terms of the Louisiana statute are not incorporated into the bond because the bond did not specifically include a forum selection provision. It is plaintiffs position that the Louisiana statute is not controlling and that this Court, therefore, has jurisdiction in this diversity action.

The Louisiana Public Works Act was enacted to “protect persons doing work, performing labor or furnishing materials for the construction, erection, alteration or repair of * * * public works of any character.” La. Acts 1918, No. 224. The Act requires contractors performing work for the State or any political subdivision thereof to furnish a public works bond in the amount of no less than fifty percent of the contract price. The Act affords a “special remedy [to] a certain class of creditors for the concurrent enforcement of their claims and to regulate their rights as between themselves and against a contractor doing public work, and the surety on his bond.” Seal v. Gano, 160 La. 636, 107 So. 473 (1926).

La.R.S. 38:2243 provides in pertinent part:

“If at the expiration of the forty-five days and filed and recorded claims are unpaid, the governing authority shall file a petition in the proper court of the parish where the work was done, citing all claims and the contractor, subcontractor, and surety on the bond and asserting whatever claims it has against any of them, and shall require the claimants to assert their claims. If the governing authority fails to file the proceeding any claimant may do so.
“All the claims shall be tried in concursus and the claims of the claimants shall be paid in preference to the claims of the governing authority.” (Emphasis added.)

The purpose of this section was to provide a remedy to " * * * bring all parties concerned and having an interest together before one court and in one proceeding, to the end that their respective rights as between themselves and against the contractor and his surety might be recognized and adjusted.” Seal v. Gano, 107 So. at 475. The Louisiana legislature desired to prevent the multiplicity of suits that would arise when creditors enforced their individual claims against the principal and surety. The remedy created by § 2243 additionally enables all creditors to share ratably and in proportion to the amount of their respective claims in the common fund provided by the bond, therefore, eliminating the probability that some creditors would not recover because other creditors had exhausted the fund in prior suits.

Louisiana is not the only state to have enacted a bond statute that restricts the forum for suits to the state where the work was done. (See Appendix A, infra.) Plaintiff argues, however, that the Louisiana statute, unlike the Miller Act, 40 U.S.C. § 270b and other state statutes having forum restriction provisions, does not provide an exclusive procedure for recovery against the public works bond. It is pointed out that the other statutes use mandatory language, including the restrictive word “shall,” to proscribe the procedure for recovery, whereas the Louisiana statute provides that “ * * * any claimant may do so.” (Emphasis added.)

It is this Court’s opinion that plaintiff’s attempt to distinguish the Louisiana statute from other state statutes which provide forum restrictions on statutory public works bonds' is ill-conceived. The Louisiana Supreme Court in Seal v. Gano, supra, acknowledged that the purpose of the statute is to provide a “special” remedy for all parties concerned to adjudicate their respective rights in one proceeding. If plaintiff’s contentions are accepted as true, the statute’s effectiveness will be totally thwarted. Additionally, the statute provides that “[a]ll the claims shall be tried concursus * * A concursus action promotes the adjudication of all claimants’ rights in one proceeding, thereby eliminating multiplicity of suits and insuring that all claimants recover against the bonds. [574]*574The procedure prescribed by the Louisiana statute is, therefore, found to be mandatory in light of Seal v. Gano, supra.

The next point which needs consideration is whether the special remedy created by the Louisiana Public Works Act restricts the jurisdiction of this Court in a diversity action. Plaintiff alleges that this Court has jurisdiction in the case at bar because all requisites of diversity have been met. “It is generally true that a transitory action * * * may be brought in any- court of competent jurisdiction where jurisdiction over the defendant can be obtained,” however, a local cause of action may be restricted to a particular jurisdiction. State ex rel. U.S. Fidelity and Guaranty Co. v. Mehan, 581 S.W.2d 837 (Mo.App.1979).

The Supreme Court implicitly recognized a state’s right to restrict a cause of action to a specific court in Tennessee Coal, Iron & R. Co. v. George, 233 U.S. 354, 34 S.Ct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mission Medical Group, P.A. v. Filley
879 S.W.2d 743 (Missouri Court of Appeals, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
609 F. Supp. 571, 1985 U.S. Dist. LEXIS 21627, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pipe-systems-inc-v-american-manufacturers-mutual-insurance-moed-1985.