Pioneer Reserve, LLC v. United States

119 Fed. Cl. 201, 2014 U.S. Claims LEXIS 1286, 2014 WL 6536762
CourtUnited States Court of Federal Claims
DecidedNovember 21, 2014
Docket14-376C
StatusPublished
Cited by2 cases

This text of 119 Fed. Cl. 201 (Pioneer Reserve, LLC v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pioneer Reserve, LLC v. United States, 119 Fed. Cl. 201, 2014 U.S. Claims LEXIS 1286, 2014 WL 6536762 (uscfc 2014).

Opinion

Clean Water Act; mitigation bank; contract; regulatory function; subject matter jurisdiction

OPINION

BRUGGINK, Judge.

Pioneer Reserve, LLC (“Pioneer” or “plaintiff’), presents this court with a breach of contract claim, Defendant, the United States Government, filed a motion to dismiss *203 plaintiffs complaint, contending that plaintiff did not have a contract with the federal government and that we, therefore, do not have subject matter jurisdiction. The matter is fully briefed and we heard oral argument on November 6, 2014, For the reasons explained below, we deny defendant’s motion.

BACKGROUND 1

Pioneer Reserve, LLC was formed by the Walther family to manage two tracts of valuable land (“the tracts” or “the land”) located in Matanuska-Susitna Borough, Alaska that the family acquired in 1998. These tracts of land were capable of being developed and therefore had significant value.- The Walther family also suspected that there would be even greater value in preserving the land and selling its status as a preserved natural resource to developers who were required to compensate for the impact their developments elsewhere would have on other natural resources. The .framework for this arrangement is set forth in the following statutes and regulation.

I. The Clean Water Act and Its Implementation Through Regulation

Congress passed the Clean Water Act to “restore and maintain the chemical, physical, and biological integrity of the Nation’s waters.” 33 U.S.C. § 1251(a) (2012). The Act accomplishes this restoration by prohibiting the discharge of pollutants into bodies of water, id. § 1311(a), except by special permit issued by the appropriate federal agency. Id. § 1344(a). Thus, if a developer seeks to dredge or dump fill, i.e., discharge pollutants, into the waters, including wetlands, 2 of the United States, it must apply for a permit, which may or may not be granted after a period for public notice and comment. Id.

After the developer applies for the permit, the Department of the Army, Corps of Engineers (“Corps”), engages in a public-interest analysis that takes into account measures proposed by the developer to mitigate the unavoidable impact to the waters or wetlands. 33 C.F.R. § 320.4(r) (2014). The mitigation may be accomplished on or off the site intended for development, and the Corps may condition the permit upon the implementation of the proposed mitigation. Id. § 325.4(a). Additionally, the developer is not required to be the entity that accomplishes the mitigation. Rather, the regulations contemplate an option whereby the developer may secure mitigation “credits” from a third party mitigation bank, 3 which assumes responsibility for the preservation of a piece of land containing natural resources, such as wetlands, in exchange for compensation from the developer. See id. § 332.2 (“The operation and use of a mitigation bank are governed by a mitigation banking instrument.”).

The mitigation banking instrument 4 (“instrument”) features prominently in the process of proposing, approving, and establishing a mitigation bank. The process begins when the entity seeking to establish a mitigation bank, which is referred to as the “sponsor,” submits a proposal to the Corps. This proposal must contain the following: a draft mitigation plan describing “the ecological characteristics of the proposed compensatory mitigation project site;” a work-plan for restoring, enhancing, or preserving the resources described; “the number of credits to *204 be provided, including a brief explanation of the rationale for this determination;” and the method of achieving preservation, including any legal arrangements or instruments necessary to ensure the long-term protection of the site. Id. § 332.8(c)(l)(iii). The district engineer, on behalf of the Corps, then assembles an Interagency Review Team (“IRT”) to review the documents submitted by the sponsor. Id. § 332.8(b)(1). “[Representatives from the U.S. Environmental Protection Agency, U.S. Fish and Wildlife Service, NOAA Fisheries, the National Resource Conservation Service, and other federal agencies, as appropriate, may participate in the IRT,” Id. § 332.8(b)(2).

The IRT will review the proposal, instrument, “and other appropriate documentation and provide comments to the district engineer” in order “to facilitate the establishment of mitigation banks.” Id. § 332.8(b)(3). During the IRT review period, the public is also given a 30-day period to comment on the sponsor’s proposal, Id. § 332.8(d)(5). If the district engineer determines that the proposal has potential, he or she will provide the sponsor with the district engineer’s initial evaluation letter along with comments from the public and the IRT. Id. § 332.8(d). “After considering comments from the district engineer, the IRT, and the public, if the sponsor chooses to proceed with establishment of the mitigation bank ... he must prepare a draft instrument and submit it to the district engineer.” Id. § 332.8(d)(6)(i). The draft instrument must contain the mitigation plan and a credit release schedule. Id. § 332.8(d)(6). When the sponsor submits the draft instrument, it triggers one more round of review and comments by the district engineer and the IRT. Id. § 332.8(d)(7). The sponsor has the ability to alter the draft instrument to respond to comments. If the feedback during this round of review indicates that the draft instrument is generally acceptable, then the sponsor may submit a final instrument. Id.

Submission of the final instrument results in a final round of review by the district engineer and the IRT. Id. § 332.8(d)(8). Although the district engineer “retains final authority for approval of the instrument,” he or she “will give full consideration to any timely comments and advice of the IRT.” Id. § 332.8(b)(4). Once the final instrument is approved, the district engineer arranges for the instrument to be signed by the parties. Id § 332.8(d)(8); 33 C.F.R. § 332.8(a)(1) (“All mitigation banks ... must have an approved instrument signed by the sponsor and the district engineer prior to being used to provide compensatory mitigation” credits.). Members of the IRT also have the option of signing the instrument to “indicate their agreement with the terms of the instrument” or to “submit a letter expressing concurrence with the instrument.” 33 C.F.R. § 332.8(b)(3).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pioneer Reserve, LLC v. United States
125 Fed. Cl. 112 (Federal Claims, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
119 Fed. Cl. 201, 2014 U.S. Claims LEXIS 1286, 2014 WL 6536762, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pioneer-reserve-llc-v-united-states-uscfc-2014.