Opinion

MB. CHIEF COMMISSIONEB POOBMAN

prepared the opinion for the court.

This is an action in ejectment. Yerdict and judgment for defendant. Plaintiff appeals from the judgment and from an order overruling its motion for a new trial. The acts of defendant complained of appear in the statement.

At the times mentioned in the complaint plaintiff was the owner of certain mill sites and placer claims, or parts thereof, described in the complaint, including the Junction mill site, the French mill site, and the South Side placer. The defendant owned certain lands northwest of and adjoining the lands of plaintiff. At one time the Western Mine Enterprise Company owned all of the lands involved herein, and in 1897 it conveyed by deed to A. F. Graeter and others all or a part of the Junction mill site, the French mill site, and the South Side placer, with other lands. This deed contains the following reservations: “Excepting the lumber and material in the water flume connecting with the so-called Golden Leaf mill, and in the ore-bins and mill tram thereon, said lumber and material being the property of the Bannack Mining & Milling Company, and excepting and reserving to the said party of the first part the right of a roadway for wagons across the said premises to connect with the Golden Leaf mill; the right to discharge mill tailings upon the said premises from the operation of the said mill, and excepting and reserving any and all veins or lodes of quartz which may be found or which may be within or upon the said premises and the right to work and explore the same.” The grantees named in this deed in 1898 conveyed their interest to plaintiff. In 1906 the Western Mine Enterprise Company sold and conveyed all of its property which it had not theretofore sold to Graeter and his associates to Carlton H. Hand, who in turn sold it to the defendant [261]*261company. The predecessor in interest of the "Western Enterprise Company was the Golden Leaf Mining Company, the then owner of the Golden Leaf mill, which was operated by water-power conveyed to it through the North Side Ditch, and the flume, extending across a part of the lands conveyed to the plaintiff company. At the time of the execution of the deed to Graeter and others, the "Western Mine Enterprise Company owned the Golden Leaf mill and the land on which the same was situated, but did not own the mill machinery. That was owned by a subsidiary company known as the Bannack Mining & Milling Company, which was the operating company of the mill. The rights of this latter company subsequently passed to the defendant herein.

The defendant maintains that at the time of the sale to Graeter the flume and mill were in a workable condition, the witness stating: “We had been using the mill and conveying the water from the North Side Ditch down to the mill. At the exact time of the conveyance to Graeter * # * they would be in such a condition that a few dollars would have put them into operating condition. It would be just the ordinary work that would have to be done on a flume if you were to shut down in the fall, say, and start work in the spring.” This condition of the mill and flume is disputed by the plaintiff.

The defendant further maintains that the plaintiff, in dredging its ground, destroyed the flume and so changed the surface of the ground that it was impossible to ascertain the exact location of the original flume. Plaintiff also disputes this fact, and maintains that there was no flume there except in certain places.

Subsequently the Bannack Mining & Milling Company rebuilt the flume and, as maintained by defendant, on the same line of the original flume, as nearly as could be then ascertained. The flume so built was of practically the same size as the original flume. The plaintiff, however, claims that the new flume was in a new location and was larger than the old flume.

[262]*262Some time prior to the trial, the plaintiff caused its ground to be surveyed, and according to that survey, as appears from the evidence, the building designated as a retort building projected on to plaintiff’s land a distance of 3.35 feet in width and twenty-four feet in length. There was also a structure designated as a penstock, or standpipe, which extended across the line on to plaintiff’s ground a distance of five feet, also a pump-house seven feet three inches by nine feet, a toilet building seven feet three inches square, a tail-race 93.5 feet long, twelve feet wide, and ten feet deep, but according to the survey made by the defendant, which was also in evidence, the retort building was not on the plaintiff’s land, and the building known as the pump-housé was entirely abandoned and removed by the defendant before the commencement of the action; that it was only a small house; that the pump was used to pump water in mixing cement for the foundation of the mill; that the toilet was a mere temporary structure set upon the gravel, without a pit or foundation. The flume referred to in the plaintiff’s .evidence was also upon the plaintiff’s ground. It was also maintained by defendant that this flume, tail-race, and standpipe are necessary to the operation of the mill. All these matters, in so far as there was a conflict of evidence, were determined by the verdict of the jury. The only question then remaining here is the question of law relating to the right of the defendant to maintain the flume and the tail-race. The standpipe or penstock, according to the testimony in this case, was a necessary part of the flume, being required to enable the defendant to utilize the water with which to operate the mill.

[1] At the time plaintiff acquired title to this land, it was charged with the knowledge of the existence of this mill and of the fact that same was operated by water-power conveyed to it through the North Side Ditch and the flume, for the ditch and the flume extended across the land conveyed to plaintiff, and the deed to the plaintiff’s immediate grantor refers to the “water flume connecting with the Golden Leaf [263]*263mill,” reserving the material thereon, with the statement that the same belonged to the Bannack Mining & Milling Company. The deed also reserves a right to a roadway for wagons to the “Golden Leaf mill,” also “the right to discharge tailings upon the said premises from the operations of said mill.” The Western Mine Enterprise Company was at the time of the conveyance to plaintiff’s immediate grantors the owner of the mill, which was operated only by this water-power. While the deed did not expressly reserve the right to convey water across the land conveyed to the plaintiff’s grantors, or to erect and maintain a flume thereon, yet there is the clear implication that the company did not intend to abandon its mill or the operation thereof, else why would it reserve the right to discharge mill tailings upon the premises conveyed “from the operation of the said mill”?

[2] It is true, as maintained by appellant, that no easement exists so long as there is a unity of ownership, because the owner of the whole may at any time rearrange the qualities of the several parts, but the moment a severance occurs, by the sale of a part, the right of the owner to redistribute the properties of the. respective portions ceases; and easements or servitudes may thus be created or reserved. The parties are presumed to contract with reference to the condition of the property at the time of the sale, provided the marks are open and visible. (Lampman v. Milks, 21 N. Y. 505; Martin v. Murphy, 221 Ill. 632, 77 N. E. 1126; Oland v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Our Lady of the Rockies, Inc. v. Peterson
2008 MT 110 (Montana Supreme Court, 2008)
Ponderosa Pines Ranch, Inc. v. Hevner
2002 MT 184 (Montana Supreme Court, 2002)
Albert G. Hoyem Trust v. Galt
1998 MT 300 (Montana Supreme Court, 1998)
Woods v. Houle
766 P.2d 250 (Montana Supreme Court, 1988)
White v. Landerdahl
625 P.2d 1145 (Montana Supreme Court, 1981)
Godfrey v. Pilon
529 P.2d 1372 (Montana Supreme Court, 1974)
Shammel v. Vogl
396 P.2d 103 (Montana Supreme Court, 1964)
Spaeth v. Emmett
383 P.2d 812 (Montana Supreme Court, 1963)
Te Selle v. Storey
319 P.2d 218 (Montana Supreme Court, 1957)
Olson v. Mullen
68 N.W.2d 640 (Supreme Court of Minnesota, 1955)
Hewitt v. Novak
158 P.2d 627 (Montana Supreme Court, 1945)
Bogovich v. Scandrett
158 P.2d 637 (Montana Supreme Court, 1945)
Groshean v. Dillmont Realty Co.
12 P.2d 273 (Montana Supreme Court, 1932)
Johnson v. Franklin
152 A. 64 (Supreme Court of Connecticut, 1930)
Stetson v. Youngquist
248 P. 196 (Montana Supreme Court, 1926)

Cite This Page — Counsel Stack

Bluebook (online)
198 P. 748, 60 Mont. 254, 1921 Mont. LEXIS 95, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pioneer-mining-co-v-bannack-gold-mining-co-mont-1921.