Pioneer Concrete & Fuel, Inc. v. Apex Construction, Inc.

664 P.2d 938, 204 Mont. 387, 1983 Mont. LEXIS 724
CourtMontana Supreme Court
DecidedJune 16, 1983
Docket82-147
StatusPublished
Cited by2 cases

This text of 664 P.2d 938 (Pioneer Concrete & Fuel, Inc. v. Apex Construction, Inc.) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pioneer Concrete & Fuel, Inc. v. Apex Construction, Inc., 664 P.2d 938, 204 Mont. 387, 1983 Mont. LEXIS 724 (Mo. 1983).

Opinion

*389 MR. JUSTICE WEBER

delivered the opinion of the Court.

United Pacific Insurance Company (United) appeals from a January 8, 1980, judgment in the District Court of Silver Bow County in the amount of $17,532.93 in favor of Pioneer Concrete & Fuel, Inc., (Pioneer) against Apex Construction, Inc., (Apex), a public works subcontractor. In that judgment, the Court found that United, the bonding company for the subcontractor, was fully obligated for any indebtedness of Apex. Darrell Birdsbill, d/b/a Birdsbill Cement Contractor (Birdsbill), subcontractor of Apex, appeals from a judgment of December 22, 1981 in favor of Apex against Birdsbill in the amount of $13,921.04, and in favor of United against Birdsbill in the amount of $17,532.92. We affirm the judgments of the District Court with the exception that we modify the judgment against Apex so that United is held jointly liable to Pioneer and modify the judgment against Birdsbill so that it grants judgment in the alternative against Apex or United in the amount of $13,921.04.

The issues presented:

1. Whether United is liable to Pioneer, supplier of materials to subcontractor Apex, under subcontract bonds issued by United in behalf of Apex under two municipal contracts for street and storm sewer improvements in Butte?

2. In the absence of liability on the part of United under the wording of the subcontract bonds issued in behalf of Apex as subcontractor, can the judgment of the District Court be affirmed on a theory of equitable responsibility of United for the Apex obligation?

3. Is there substantial evidence sufficient to require affirmance of the judgment against Birdsbill?

4. In the event that the judgment against Birdsbill is affirmed, should the judgment in behalf of United be reduced to the same amount as the judgment in behalf of Apex?

The facts disclose that Jim Gilman Excavating, Inc. (Gilman) entered into two contracts for street and storm *390 sewer improvements in the city of Butte with Butte-Silver Bow, a municipal corporation. The Bellevue Project was contracted in April 1978, and the Farragut Project was contracted in August 1978. As general contractor, Gilman provided performance bonds which are not at issue in this case.

In May 1978, Gilman hired Apex to perform curb, gutter, sidewalk and driveway work on the Bellevue Project and in September 1978 again hired Apex to perform similar work on the Farragut Project.

In turn, Apex subcontracted a portion of its work to Birdsbill for handfinishing sidewalks, driveway and curbs on the Bellevue Project in June 1978 and in October 1978 on the Farragut Project.

On each project, Apex furnished to Gilman a Subcontract Bond in identical form, which provided that Apex and United were bound to Gilman for the amount of the subcontracts, with reference to the two contracts between Gilman and Butte-Silver Bow. The bonds further provided:

“NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION IS SUCH, That, if the above bounden Principal shall faithfully perform the work contracted to be done under said Subcontract, and shall indemnify the Said Obligee against all loss or damage which obligee may sustain by reason of the failure of said Principal to pay claims for labor, services or materials, furnished and used or consumed directly in connection with the performance of such Subcontract, then this obligation shall be void; otherwise it shall remain in full force and effect.
“PROVIDED, HOWEVER, notwithstanding anything in said Subcontract to the contrary, this bond is one of indemnity only and does not inure to the benefit of or confer any right of action upon any person other than the named Obligee.”

The contracts between Apex and Gilman were on a Standard Subcontract Agreement form prepared by the Associated General Contractors of America. Regarding the payment by Apex for materials and labor, both contracts *391 provided:

“That the Subcontractor shall:
“(3) Pay for all materials and labor used in or in connection with, the performance of this contract, through the period covered by previous payments received from the Contractor, and furnish satisfactory evidence when requested by the Contractor, to verify compliance with the above requirements.”

Trying the case without a jury, the District Court found in its findings of fact that Pioneer had furnished ready mix concrete, cement, sand and curing compound to Apex on both the Bellevue and Farragut Projects. The Court further found that the total of the claims for such materials on the two projects was $30,244.84, and that Apex had paid $12,711.91, leaving a balance owing from Apex to Pioneer of $17,532.93. The District Court further found that United was obligated fully under its subcontractor bonds. Judgment was decreed in the amount of $17,532.93.

In the same cause, Apex and United had sued Birdsbill as a third-party defendant. Initially, default judgment was entered against Birdsbill. Subsequently the default was set aside and the third-party portion of the action went to trial before the District Court without a jury. The District Court found that $3,611.88 was owing by Apex to Birdsbill which was to be offset against the debt owing from Birdsbill to Apex in the amount of $17,532.92. The District Court therefore concluded that the net amount owed by Birdsbill to Apex was $13,921.04 and entered judgment accordingly. As to United, the District Court concluded that the offset of $3,611.88 was not properly to be allowed, and therefore entered judgment in the full amount of $17,532.92.

I.

The first issue is whether United is liable to Pioneer, supplier of materials to Apex, a subcontractor, under subcontract bonds issued by United in behalf of Apex. This issue *392 must be determined by a careful analysis of the wording in both subcontract bonds, which are identical in substance.

Pioneer contends that the interpretation required is similar to the bond interpretation made by this Court in Carl Weissman & Sons, Inc. v. St. Paul Fire & M. Ins. Co. (1968), 152 Mont. 291, 448 P.2d 740. In contrast, United contends that the bond interpretation must be construed in accordance with Treasure State Industries Inc. v. Welch (1977), 173 Mont. 403, 567 P.2d 947. We find these cases to be controlling, and conclude that Treasure State Industries requires a conclusion for United.

A comparison of the bonds and underlying subcontracts in Weissman, Treasure State Industries and this case discloses significant differences. As pointed out in Treasure State Industries, 173 Mont. at 406, 567 P.2d at 949:

“We feel Weissman can be distinguished on the facts. In Weissman

Free access — add to your briefcase to read the full text and ask questions with AI

Related

K-W Industries v. National Surety Corp.
754 P.2d 502 (Montana Supreme Court, 1988)
K-W Industries v. National Surety C
Montana Supreme Court, 1987

Cite This Page — Counsel Stack

Bluebook (online)
664 P.2d 938, 204 Mont. 387, 1983 Mont. LEXIS 724, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pioneer-concrete-fuel-inc-v-apex-construction-inc-mont-1983.