Pinkham v. Haynes

68 A. 642, 103 Me. 112, 1907 Me. LEXIS 25
CourtSupreme Judicial Court of Maine
DecidedOctober 23, 1907
StatusPublished

This text of 68 A. 642 (Pinkham v. Haynes) is published on Counsel Stack Legal Research, covering Supreme Judicial Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pinkham v. Haynes, 68 A. 642, 103 Me. 112, 1907 Me. LEXIS 25 (Me. 1907).

Opinion

Whitehouse, J.

This is an action of assumpsit to recover damages for an alleged breach on the part of the defendants of the following contract for the sale and delivery of potatoes, viz :

" Lincoln, Maine, Sep. 30, 1905.
"This day sold to E. H. Pinkham 1000 bu. Potatoes to be Green Mountains and good merchantable stock well assorted and [114]*114to be delivered on board cars either at South Winn or North Lincoln Station on or before Nov. 1, 1905.
" Rec’d this day on account of above potatoes fifty dollars said potatoes to be paid for at forty cents per bushel.
" C. C. Haynes,
"B. F. Wyman.”
" I hereby agree to take said potatoes if they freeze in the barn after being stored before Nov. 1st, at the said within price.
"E. H. Pinkham.”

yAThe last clause, signed by the plaintiff, expressly agreeing to accept, under the contract, potatoes that might " freeze in the barn after being stored before November 1,” appears to have been indorsed on the contract October 7, as a result of a conversation between the parties at that time, when the defendants expressed a fear that the potatoes would freeze in the barn.

The plaintiff avers in his declaration that he was ready to receive the potatoes on the first day of November at North Lincoln and had cars there ready to receive them and requested the defendants to load them, but he alleges that the defendants refused to deliver them. The potatoes were never in fact delivered to the plaintiff, but were sold and delivered to other parties on the second day of November.

It was not in controversy that the cars on board of which the potatoes were to be delivered under the terms of the contract, were to be furnished by the plaintiff, and that it was consequently the right of the plaintiff to determine the time when the potatoes should be delivered within the limitation prescribed by the contract. The defendants state that they acquiesced in the proposition made by the plaintiff Sept. 30, the time the contract was signed, that he "couldn’t take the potatoes that day, but would take them as soon as the price advanced so that he could do so at a profit;” and although according to the testimony of the plaintiff himself, the market price of potatoes at Lincoln had so advanced that for at least a week prior to November 1, it was 65 cents a bushel loaded on the cars, there is no evidence that the plaintiff made any effort to obtain cars, or if so, he failed'to obtain any, until October 28, He then informed [115]*115the defendants, through his agent that "he had ordered the car and that he would let them know when it got there.” The ear did not arrive until the night of October 31. Howard Pinkham, the plaintiff’s brother, testifies that he was "sent by the plaintiff to the defendant Haynes” and that he arrived at Haynes’s house "about ten o’clock” the first day of November, the next day after the car arrived. He thus describes the interview between Mr. Haynes and himself: "I told him the car was there and ready for potatoes and I says, "Haven’t you got a canvas you can throw right over your load?” We didn’t make much talk. Isays, "Pretty hard day to haul potatoes,” says I. "What time will you be there tomorrow with a load?” He didn’t say much. I says, "Probably about nine o’clock?” And he thought it would take until nine o’clock to get there — had to load up. That was all the talk I had with him and came back.”

The suggestion of the witness that a canvas might be thrown over the load obviously had reference to the heavy rain that, was falling that day. Two hundred bushels of the potatoes were stored in a barn four miles distant from North Lincoln, and eight hundred bushels were three miles distant. It satisfactorily appears from the testimony of the defendants that it was between eleven and twelve o’clock when the interview between Howard Pinkham and Haynes actually took place on November first. It is shown by undisputed evidence that it would have required at least ten well equipped teams to move all of those potatoes before nine o’clock that night, that it was practically impossible to procure so many teams that day, and that it would have required five days to move them with the two teams which it may be inferred from the testimony, were the only ones’ ordinarily used by them in their business and the only ones which would have been available for their use that afternoon.

The defendant Haynes’s testimony in regard to this interview of November 1, does not differ very materially from the plaintiffs. According to his version of it, the plaintiff came to his house about twelve o’clock and told him he had a car, "but it was raining so I couldn’t haul the potatoes, but could haul the next day if it didn’t rain,” He denies that he said he would be ready and commence [116]*116hauling the next morning at nine o’clock or that he said in reply to the plaintiff that "that was about as early as he could get around.” But in answer to a further inquiry he says: “We couldn’t have delivered them on the first of November. We should have started in though, if he had said so, but it would have been impossible.”

It appears, however, that Howard Pinkham understood that the defendants would commence hauling on the morning of November 2, and was on the road to North Lincoln at eight o’clock' that morning for the purpose of being present to weigh out the potatoes, when the defendant Haynes met him and informed that "they were not going to load the potatoes because the contract had expired.”

It is contended in-behalf of the plaintiff,, that under a reasonable construction of the contract the plaintiff had the privilege of furnishing cars anytime up to and including November 1, and if furnished on November 1, the defendants were required to commence hauling and to continue hauling and loading on that and succeeding days until all the potatoes were delivered on board the car.

It is the opinion of the court that such a construction of the contract in this case would neither be in harmony with the natural and ordinary interpretation of the phrase " on or before ” used in the contract, nor with the legal rights of the defendants under a contract which must be deemed an entirety, nor consistent with the intention of the parties at the time the contract was made.

With respect to the ordinary signification of the words " on or before,” this court has said; "within” a certain period "on or before” a day named, and "at or before” a certain day, are equivalent terms and the rules of construction apply alike to each,” Leader v. Plante, 95 Maine, 341. In New Jersey a question arose in regard to the proper interpretation of these words, in the return of the surveyors fixing the time when a road should be opened, and the court say; " The road cannot be opened in a day; the time for opening it may with propriety, be extended in some cases to many days.In the present case the words of the return are that the road shall be opened on or before the first day of September next. The natural, legal and correct construction of [117]*117these words is that the surveyor shall open the road between the day of the return and the first day of September.” Matter of Public Road in M. & M. Counties, 4 N. J. L. 329, *290.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
68 A. 642, 103 Me. 112, 1907 Me. LEXIS 25, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pinkham-v-haynes-me-1907.