Pinewood Homes, Inc. v. Spiros Zagouris and Mary Zagouris

CourtCourt of Appeals of Texas
DecidedAugust 29, 2002
Docket13-00-00697-CV
StatusPublished

This text of Pinewood Homes, Inc. v. Spiros Zagouris and Mary Zagouris (Pinewood Homes, Inc. v. Spiros Zagouris and Mary Zagouris) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pinewood Homes, Inc. v. Spiros Zagouris and Mary Zagouris, (Tex. Ct. App. 2002).

Opinion

                                   NUMBER 13-00-697-CV

                             COURT OF APPEALS

                   THIRTEENTH DISTRICT OF TEXAS

                                CORPUS CHRISTI

PINEWOOD HOMES, INC.,                                                   Appellant,

                                                   v.

SPIROS ZAGOURIS AND

MARY ZAGOURIS,                                                              Appellees.

    On appeal from the 357th District Court of Cameron County, Texas.

                                   O P I N I O N

                     Before Justices Dorsey, Yañez, and Chavez[1]

                                  Opinion by Justice Chavez


Pinewood Homes, Inc. appeals from a judgment awarding Spiros and Mary Zagouris $70,000 on a breach of contract claim.[2]  Appellant contends the trial court erred in awarding judgment to appellees because (1) the $70,000 awarded in damages was less than the $96,000 appellees had agreed to pay on the contract, but never did; (2) the evidence was insufficient to prove that the $70,000 was the reasonable cost to repair any failures to comply with the contract; (3) the evidence was insufficient to support the finding that Pinewood authorized anyone to contract with the Zagourises to build them a house; (4) that Pinewood=s failure to complete the contract was excused; and, (5) the percentage of pre-judgment interest was incorrect.  We reverse and render.


In early 1993, the Zagourises, on the recommendation of their friend George Bonas, requested that Mike Rabago build them a house. Rabago subsequently submitted a written Aprobable cost@ proposal to the Zagourises in the amount of $96,865.  After some discussion, Rabago orally agreed to build the house for $96,000.  The Zagourises also agreed to pay Rabago $300 a week for ninety days to superintend the construction.  The proposal was on ARabago & Juarez@ letterhead and the construction plans drafted by Rabago & Juarez showed Rabago & Juarez to be the contractor.  During this time, however, Rabago was telling the Zagourises that he worked for or was an officer of Pinewood Homes.  When the Zagourises went to the bank to sign the necessary documents to secure their interim financing, Rabago went with them.  The mechanic=s lien note was made payable to Pinewood Homes, Inc. and was secured by a mechanic=s lien in its favor.  Rabago endorsed the note and transferred the lien to the bank, signing both documents as a vice-president of Pinewood Homes, Inc. in order to secure the interim financing.

The building permit was obtained on September 13, 1993 and the construction began.  Rabago came by weekly to inspect the construction and to pick up his weekly $300 check.  After the ninety days expired in December and Mrs. Zagouris told Rabago she was giving him his last check, Rabago[3] stopped coming to the job site. There were numerous things wrong with the construction of the house.  The garage openings were too narrow, there were problems with the cabinetry, the stairs were too narrow, the floors were bumpy, and many others.  According to Mr. Zagouris, he went with Bonas to see Humberto Zamora, the president of Pinewood Homes in Harlingen.  Bonas was there to talk to Zamora about something else.  This was the first and only time that Zagouris ever met Zamora.  Zagouris contends that he had an opportunity to say two things to Zamora to explain to him that the house was unfinished and that there were problems with the construction.  According to Zagouris, Zamora agreed to fix the problems if they could be fixed and to finish the home.  Zamora testified he never agreed to do any such thing because he did not even know Zagouris was building a house.  Zamora testified that he first learned Zagouris was building a house when he got served with the citation.  The Zagourises then hired the subcontractor that had done the framing to finish the home.


The first draw on the interim financing was on September 24, 1993.  Although checks from the interim loan were made payable to Pinewood Homes, the checks were deposited to the Zagourises personal account and Mrs. Zagouris would use the monies to pay for materials, labor and Rabago=s fees.  A full accounting of this account was not made during the trial.  Mrs. Zagouris, however, testified that in addition to the $96,000 obtained on the bank loan, she had spent another $100,000 to correct the deficiencies and finish the home.  She could not fully explain how all of this money was specifically spent, but offered that perhaps Rabago=s bid had been too low for the construction of the three story bay home.

In its third issue, appellant argues that there was no or insufficient evidence to support a finding that Pinewood authorized anyone to agree to any contract to build the Zagouris house.  In reviewing a no-evidence point, we consider only the evidence and inferences tending to support the jury=s fact finding.  We disregard all evidence and inferences to the contrary. 

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pool v. Ford Motor Co.
715 S.W.2d 629 (Texas Supreme Court, 1986)
Plas-Tex, Inc. v. U.S. Steel Corp.
772 S.W.2d 442 (Texas Supreme Court, 1989)
Land Title Co. of Dallas, Inc. v. F. M. Stigler, Inc.
609 S.W.2d 754 (Texas Supreme Court, 1980)
Petroleum Anchor Equipment, Inc. v. Tyra
419 S.W.2d 829 (Texas Supreme Court, 1967)
Westech Engineering, Inc. v. Clearwater Constructors, Inc.
835 S.W.2d 190 (Court of Appeals of Texas, 1992)
Simons v. City of Austin
921 S.W.2d 524 (Court of Appeals of Texas, 1996)
Burroughs Wellcome Co. v. Crye
907 S.W.2d 497 (Texas Supreme Court, 1995)
Peco Construction Co. v. Guajardo
919 S.W.2d 736 (Court of Appeals of Texas, 1996)
Cain v. Bain
709 S.W.2d 175 (Texas Supreme Court, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
Pinewood Homes, Inc. v. Spiros Zagouris and Mary Zagouris, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pinewood-homes-inc-v-spiros-zagouris-and-mary-zago-texapp-2002.