Pineo v. Smaltz (In Re Gordon Urmson Builder & Sons, Inc.)

295 B.R. 546, 2003 Bankr. LEXIS 775, 2003 WL 21666637
CourtUnited States Bankruptcy Court, W.D. Pennsylvania
DecidedJuly 16, 2003
Docket18-24953
StatusPublished
Cited by1 cases

This text of 295 B.R. 546 (Pineo v. Smaltz (In Re Gordon Urmson Builder & Sons, Inc.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, W.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pineo v. Smaltz (In Re Gordon Urmson Builder & Sons, Inc.), 295 B.R. 546, 2003 Bankr. LEXIS 775, 2003 WL 21666637 (Pa. 2003).

Opinion

OPINION 1

WARREN W. BENTZ, Bankruptcy Judge.

Introduction

Gordon Urmson Builder & Sons, Inc. (“Debtor”) filed a voluntary Petition under Chapter 7 of the Bankruptcy Code on December 19, 1997. William Pineo was appointed and serves as Chapter 7 Trustee (“Trustee”). Listed as an asset on Debt- or’s Schedule B, Personal Property, is an account receivable due from Richard M. and Linda Smaltz (the “Smaltzes”) in the amount of $67,436.37.

The Trustee filed the within Complaint for Turnover of Money or Property (“Complaint”) to collect the receivable from the Smaltzes, and against First Western Bank, now by merger Sky Bank (“Bank”) on the theory that the Debtor was a third party to the construction loan agreement between the Smaltzes and the Bank. Smaltzes filed an Answer and Counterclaim and the Bank filed an Answer and Statement of Defenses. After the Bank’s Motion for Summary Judgment was refused and prior to the commencement of trial, the Trustee and the Bank agreed to a settlement of the issues between them. A three-day trial was held on December 18, 19, and 20, 2002 on the Trustee’s Complaint against the Smaltzes and on the Smaltzes’ Counterclaims.

Post-trial argument was heard on December 30, 2002. By Order dated April 23, 2003, a net judgment in the amount of $33,550 was entered in favor of the Trustee on the Trustee’s Complaint and on the Smaltzes’ Counterclaims. The Smaltzes filed a timely Notice of Appeal on May 2, 2003. We write to amplify upon the basis for our decision.

Facts

Gordon Urmson started Gordon Urmson Builders as a proprietorship in 1953. The Debtor operated as a corporation for 6 or 7 years prior to the bankruptcy filing. The principals of the Debtor were Gordon Urmson and his two sons-in-law, Robert Schaller (“Schaller”) and Randy Carnino.

Schaller and the Smaltzes were longtime friends. In Spring, 1996, Schaller built some studio sets for the Smaltzes’ photography studio. Pleased with that work, the Smaltzes discussed with Schaller the possibility of building a house in the Fall of 1996. Schaller advised the Smaltzes to obtain a set of plans for review. Mr. Smaltz later presented a set of plans that he drew up himself. The drawings were incomplete but Schaller was able to use them to provide the Smaltzes with a ballpark figure of $269,000 for the cost of construction.

The Smaltzes then obtained further plans that were also incomplete, but provided enough information for Schaller to *549 prepare a bid. Schaller and Mr. Smaltz addressed certain details and agreed that other details could be reserved for later determination. The Debtor submitted a bid of $229,550. The usual cost for construction of a brick house of this type was $85 per square foot. The quote of $68/69 per square foot provided the Smaltzes a significant price break.

On August 1, 1996, Debtor and the Smaltzes executed a contract under which the Debtor agreed to construct a residence for the Smaltzes for the sum of $229,550 (the “Contract”). The Smaltzes signed a loan agreement for a construction loan from the Bank on September 17, 1996 (the “Loan Agreement”). The Loan Agreement provides a schedule for progress payments and provides that the construction will be completed within 6 months. Even though the completion date according to the Bank’s schedule was March, 1996, the parties initially agreed on a completion date of May 1, 1997 and later agreed to a completion date of July 31,1997.

Work commenced in September, 1996. Details in the Contract were incomplete, but Schaller and the Smaltzes believed that they had sufficient information to begin and that, as friends, they would work out the details during the construction process. The plans were incomplete. Mr. Smaltz didn’t want to pay the architect to finalize the plans. Mr. Smaltz was incompetent as an architect. Schaller tried to utilize the partial plans in an effort to save his friend some money.

Prior to work on the foundation, Schaller spent time putting measurements on the foundation plan. While this was pointed out in the testimony as a source of delay, it was not considered a significant delay at the time.

The Contract called for a basement with 13 courses of block per the Smaltzes’ request. After the masonry contractor had laid part of the 13th course of block, the Smaltzes determined that 13 courses was too high and elected to remove the top course. Mr. Smaltz removed the partially completed 13th course over a weekend. This is pointed out as an example of the many changes made by the Smaltzes and a cause of delay. This change was memorialized in a change order dated October 21, 1996 which provides:

the removal of 13th course of block done by homeowner and the brickledge add to left side of house and new slate tiles N/C the owner agrees to let us put proper grade up on the brick to get proper slope

Elimination of the 13th course of block was not considered a material event at the time. The only concern was grading which the parties agreed would be solved by allowing the Debtor to place dirt upon brick to obtain the proper grade.

Other changes were made at this early stage per the October 21 change order: extra foundation and drains for center wall, stove and fireplace; block and labor, lintels and rebar for center wall, stove and fireplace; the foundation was changed to provide for an enlarged sun porch.

Additional changes are referenced on change orders dated November 5 and November 19, 1996. While these changes may have been frustrating for the workmen, and certainly contributed to delay, this was nothing more than Schaller and the Smaltzes anticipated. This was part of the plan that the friends would work together to provide the best house at the best possible price.

The house was to have been bricked by November 28, 1996. The Smaltzes wanted bricking completed before harsh winter weather required inclusion of calcium or antifreeze in the cement to prevent freezing.

*550 The brickwork was not complete by November 28. Schaller now blames the delay on the number of changes made by the Smaltzes. The Smaltzes now blame the delay on the Debtor’s doing too many jobs at once and the failure to properly oversee its employees who they claim stood around performing little or no work. In any event, the parties agreed to defer bricking until the danger of frost had passed in Spring, 1997.

In December, 1996, the Smaltzes prepared a list of concerns. The list was presented to the Bank and was the subject of a meeting with the Bank’s representative, Mr. Smaltz, Schaller and Gordon Urmson. 2 The meeting was cordial, issues and dates were discussed and agreed upon.

Beginning in March, the Smaltzes began regular preparation of lists of things for completion (“Punch Lists”). There are Punch Lists dated March 21, 1997 and April 7, 1997 of items to be completed before the Debtor receives the next draw on the Smaltzes’ construction loan. In a Punch List dated June 7, 1997, the two main issues in this case first arise in writing:

-Walls in basement are wet and will not dry up.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
295 B.R. 546, 2003 Bankr. LEXIS 775, 2003 WL 21666637, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pineo-v-smaltz-in-re-gordon-urmson-builder-sons-inc-pawb-2003.