Pilchuck Contractors, Inc., V Dept. Of L&i

Court of Appeals of Washington·Decided October 8, 2013·No. 43327-3·Unpublished

Opinion

FILED

CC1U Or APPEALS

2013 OCT -8 AM 9: 26

IN THE COURT OF APPEALS OF THE STATE OF W

DIVISION II

PILCHUCK CONTRACTORS, INC., I No. 433,

Appellant,

V.

DEPARTMENT OF LABOR AND UNPUBLISHED OPINION INDUSTRIES,

Respondent.

Penoyar, J. — Pilchuck appeals the Board of Industrial Insurance Appeals' (Board)

decision that the Department of Labor and Industries (Department) proved two violations by Pilchuck. Pilchuck argues that (1) Department did not prove a prima facie case because it did the

not show that Pilchuck violated the Washington Administrative Code (WAC) standards or that Pilchuck knew of the violations, ( )even if the Department proved a prima facie case, the

2

affirmative defense of employee misconduct applied, and (3) Department erred in calculating the

Pilchuck's penalty.' There is substantial evidence that Pilchuck violated the applicable WACs and that it could have known of the violations through the exercise of reasonable diligence.

Additionally, the Board did not err by finding that the employee misconduct defense did not apply because Pilchuck failed to establish that it had taken steps to discover and correct violations and that it effectively enforced its safety program in practice. The Board correctly

1 The Department correctly states that Pilchuck did not assign error to any of the Board's findings of fact. Under Division II's general order 98 2,an appellant does not have to separately -

assign error to each challenged finding of fact as RAP 10. (g) 3 requires, but the appellant must still provide the verbatim text of the finding of fact. Pilchuck did not do so here;Labor & all of therefore, Indus.,

the findings are verities on appeal. Mid Mountain Contractors, Inc. v. Dep't of 136 Wn. App. 1,4, 146 P. d 1212 (2006).This would effectively negate Pilchuck's appeal, but

3

we exercise our discretion under RAP 1. ( address the issues Pilchuck raised.

c) 2 and

- -

affirmed the Department's penalty calculation because there was. substantial evidence that the

Department considered all of the mitigating factors. We affirm.

FACTS

The Department received an anonymous complaint about possible safety hazards at a Pilchuck jobsite. On June 16, 2009, a safety compliance officer for the Department, John

Korzenko, visited the jobsite. When he arrived, he saw three Pilchuck employees working in a

trench. The trench varied in depth, but the area where the employees were working appeared to

be over eight feet deep. The employees were using a single hydraulic cylinder and Finn boards

A

to shore the sides of the trench. There were " spoils pile[ ] along the edge of the trench.

s

Clerk's Papers (CP)at 166.

Korzenko inspected the site and spoke with the foreman, Jeff Heaton. Korzenko issued Pilchuck a citation with three serious violations based on his observations at the jobsite on June

16. He issued the first violation, 1. ,because the trench lacked a safe exit. He issued the second

1

violation, 1. ,because the spoils piles were not at least two feet away from the edge of the trench

2

as WAC 296-155-

b) He issued the third violation, 1. ,because the trench was 655( 0)(

1 requires. 3 not adequately protected from cave ins as WAC 296 -155-657( )( - a) 1 requires. Trenches over six

2 The record also refers to the cylinder pump jack." CP a " as - at 259. The cylinder extends horizontally across the trench to keep the soil on the sides of the trench from caving in. 3 Finn boards are fiberglass coated plywood boards that vertically line the walls of the trench. The hydraulic cylinders push up against the boards to shore the sides of the trench. 4 A spoils pile"is a pile of material excavated from the trench. CP at 165.

"

5 A violation is " erious"if there is a substantial probability that death or serious physical harm s "

could result from a condition which exists, or from one or more practices, means, methods, operations, or processes which have been adopted or are in use in such workplace." RCW 180( 49. 7.

6).

- -

feet deep require two hydraulic cylinders for shoring, and this trench, which was at least eight feet deep, only had one cylinder. The Department penalized Pilchuck $ 9, 3, per

450— 150

$

violation.

Pilchuck appealed the violations to the Board. At the hearing, Pilchuck's safety director

testified that Pilchuck ensures compliance with its trenching and excavation safety program by

holding safety meetings, providing safety trainings and orientations, providing the proper tools

and techniques, and conducting field inspections. He also testified about Pilchuck's disciplinary

policy, explaining that the method of discipline varied by circumstances and that it could be anything from a written or verbal warning to termination. He stated that Heaton was given a written warning for the violations at issue here.

Korzenko also testified and explained how he reached the penalty amount for each violation. He stated that he considered the condition of the soil, the amount of time the

employees were exposed to the hazards, the sloughing of materials on the trench walls, and the lack of adequate shoring. He said that he also considered the employees' training, Pilchuck's safety program, the presence on the jobsite of a competent person, and the adequate shoring in some parts of the trench.

After the hearing, the industrial appeals judge (IAJ)vacated violation 1. and affirmed

1

violations 1. and 1. .

2 3 The IAJ found that the spoils piles were too close to the trench, the

shoring in the trench was not adequate for the depth, and Pilchuck could have known of the violations "with the exercise of reasonable diligence." CP at 51 (FF 6). IAJ also rejected The

Pilchuck's affirmative defense of employee misconduct, finding that it was not taking adequate

6 A competent person is "an individual who is capable of identifying existing and predictable hazards or working conditions that are hazardous, unsanitary, or dangerous to employees, and who has authorization to take prompt corrective measures to eliminate them."CP at 379.

- -

steps to discover safety violations or effectively enforcing its safety program. The Board

adopted the IAJ's decision and order. Pilchuck appealed to the superior court, which affirmed the Board. Pilchuck now appeals to this court.

ANALYSIS

I. STANDARD OF REVIEW

We review the Board's decision directly, based on the record before the agency. Mowat 407 (2009). We

Constr. Co. v. Dep't of Labor & Indus.,148 Wn. App. 920, 925, 201 P. d

3

review the Board's findings to determine if they are supported by substantial evidence in the record. RCW 49. 7. Substantial evidence is evidence sufficient to persuade a fair-

150(

1

1 ).

minded person of the truth of the declared premise. Mowat Constr. Co., Wn.App. at 925..

148

H. VIOLATIONS

Pilchuck first argues that the Board erred by finding that the Department proved two

serious violations. It argues that the Department failed to show that it violated the standards for

spoils piles and shoring requirements and that it knew or could have known of the violations. Because there is substantial evidence that Pilchuck violated both standards and that it could have

known of the violations with the exercise of reasonable diligence,we affirm the Board.

12-

violation. WAC 263- b).

115( To

2)(

The Department has the burden of proving a

prove a serious violation, the Department must show that

1) cited standard applies; 2) requirements of the standard were not met;

the ( the 3)employees were exposed to, or had access to, the violative condition; 4)

( the

employer knew or, through the exercise of reasonable diligence, could have known of the violative condition; and (5)there is a substantial probability that death or serious physical harm could result from the violative condition."

rd

- -

E Inc. J. . Dunn Nw., v. Dep't of Labor & Indus.,139 Wn. App. 35; 44 45, 156 P. d 250 (2007)

- 3

quoting Wash. Cedar & Inc. v. Dep't of Labor & Indus., Supply Co., 119 Wn. App. 906, 914, 83

P. d 1012 (2004)). 3

A. Violation of WAC Standards

The Board found that the Department proved that Pilchuck failed to meet the

Free access — add to your briefcase to read the full text and ask questions with AI

Pilchuck Contractors, Inc., V Dept. Of L&i, (Wash. Ct. App. 2013).

Pilchuck Contractors, Inc., V Dept. Of L&i (Pilchuck Contractors, Inc., V Dept. Of L&i) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Danzer v. Department of Labor & Industries
16 P.3d 35 (Court of Appeals of Washington, 2000)
Washington Cedar & Supply Co. v. Department of Labor
83 P.3d 1012 (Court of Appeals of Washington, 2004)
Legacy Roofing, Inc. v. Department of Labor & Industries
119 P.3d 366 (Court of Appeals of Washington, 2005)
Mid Mountain Contractors, Inc. v. Department of Labor & Industries
146 P.3d 1212 (Court of Appeals of Washington, 2006)
J.E. Dunn Northwest, Inc. v. Department of Labor & Industries
139 Wash. App. 35 (Court of Appeals of Washington, 2007)
BD Roofing, Inc. v. Department of Labor & Industries
139 Wash. App. 98 (Court of Appeals of Washington, 2007)
Mowat Construction Co. v. Department of Labor & Industries
148 Wash. App. 920 (Court of Appeals of Washington, 2009)
Erection Co. v. Department of Labor & Industries
160 Wash. App. 194 (Court of Appeals of Washington, 2011)