Pierson v. Borough of Haddonfield

57 A. 471, 66 N.J. Eq. 180, 21 Dickinson 180, 1904 N.J. Ch. LEXIS 119
CourtNew Jersey Court of Chancery
DecidedFebruary 23, 1904
StatusPublished
Cited by2 cases

This text of 57 A. 471 (Pierson v. Borough of Haddonfield) is published on Counsel Stack Legal Research, covering New Jersey Court of Chancery primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pierson v. Borough of Haddonfield, 57 A. 471, 66 N.J. Eq. 180, 21 Dickinson 180, 1904 N.J. Ch. LEXIS 119 (N.J. Ct. App. 1904).

Opinion

Grey, V. C.

The bill in this case is filed under' the Mechanics’ Lien statute of this state “to secure the payment of laborers and other persons who furnish work and materials for public improvements in municipalities of this state,” approved March 30th, 1892. Gen Stat. p. 2078.

The proofs show that a notice was, in accordance with the statute, filed against the fund remaining in the custody of the borough of Haddonfield by the complainants on the 17th day of April, 1902, with the proper officer of the borough, claiming the sum of $3,191.58 from the portion of the contract price due, or to grow due, to John Quinlan, who had. contracted with the borough to construct a system of sewers and sewer disposal for a named price.

The borough of Haddonfield is a municipality of this state. The contract with Quinlan was. made on the 8th day of September, 1901, and required that he should furnish both the work and material for the system of sewage and sewage disposal projected within that borough.

[186]*186The defendant the City Trust Company, by a bond which accompanied Quinlan’s contract, became surety for his faithful performance of it.

Quinlan shortly after entered upon tire performance of his contract and continued (with a cessation of a few days in Eovembor, 1901), until the month of April, 1902, when he abandoned the work.

The eighteenth section of the borough’s contract with Quinlan is in these words:

“In case of any unnecessary or -inexcusable delay in tlie general conduct oí the work, or in the event of an actual or practical abandonment of the work, the engineer will notify the contractor and the bondsmen in writing to that effect. If the contractor shall not' within five consecutive days thereafter take such measures as will, in the judgment of the engineer, insure the satisfactory completion of the work in the time specified, or in a reasonable time thereafter if he has been permitted to continue beyond the time specified as provided elsewhere in this contract, the engineer may then, by and with the consent of the borough council of said borough, notify the aforesaid contractor to discontinue all work under this contract, and it is hereby agreed that the con-, tractor is to immediately respect said notice and stop work. The engineer shall thereupon have the power to take such and as many persons as he may deem advisable, by contract or otherwise, to work at and complete the work herein described and to use such plant, horses, carts, tools and materials belonging to- or leased by the contractor as he may find on the work and in the yards and storehouses of the contractor, or to procure by lease or purchase other materials, machinery or appliances for the completion of the same, and to charge the expense of said labor and materials, machinery and appliances to the aforesaid 'contractor, and the expense so charged shall be deducted and paid to the party of tho first part out of any such moneys as may then be due to the said contractor under and by virtue of this agreement, or any part thereof; and in case such expense is less than the sum which would have been payable for such work under this contract, if the same had been completed by the party of the second part, the contractor shall be entitled to receive the difference. If the expense is greater, then flic bondsmen will be called upon to make good the difference.”

Pursuant to this clause, when Quinlan abandoned the further performance of the contract, the engineer for the borough gave the first notice by a letter, dated April 16th, 1902, to the bondsmen, the City Trust Company, that the work had been abandoned by Quinlan, and that if such measures as would [187]*187insure satisfactory completion of the work under the contract were not taken in five daj's the engineer would be obliged to notify the contractor and his surety to cease the work, and that the borough would complete it in accordance with the terms of the contract. Very shortly after this notice was given, the defendant the City Trust Company, the surety on Quinlan’s bond (without waiting for or receiving any second notice to the effect that the borough would proceed to complete the work), made its arrangements.to proceed itself with the performance of Quinlan’s contract. If the borough desired to exercise its privilege to have its engineer complete the work, the contract required that the borough council should consent and that the engineer should give a second notice to the contractor. that he discontinue all work under the contract. This was obviously necessary in order that there should be no confusion, which might arise if the contractor and the engineer were both working at the same time in completing the improvement.

This second notice (preliminary to the assumption of the completion of the contract work by the engineer) was not given. In fact the engineer never undertook to complete the residue of the work which the contractor had left unfinished. The defendant the City Trust Company, surety for Quinlan, acting for him and in his place, completed the performance of the contract work in accordance with his contract.

The City Trust Company claims that the work which it has done in finishing that which Quinlan had left undone was by virtue of a new agreement which it entered into with the borough of Haddonfield. Ho such agreement was made in writing, nor did the borough, by its council, or even by its executive officers, definitely agree at any time with the City Trust Company that it should complete the work. Desultory conversations between the representative of the City Trust Company and the officers of the borough, casually held at various times on the subject of the completion of the work, and the fact that the City Trust Company, acting for Quinlan, actually did it, are claimed to have amounted to a new contract between the borough and the City Trust Company.

[188]*188It is explicitly denied by the borough officers that there ever was any such new or substituted contract. They testify that the defendant company proceeded with the performance of Quinlan’s contract as his surety, and that no other agreement whatever was made between that company and the borough on the subject. The attending'circumstances support the testimony of the borough officers. No definite terms of any such contract are proven. The defendant company in fact took the place of Quinlan, and in his stead performed his contract as his surety. It carried on the work in every detail as he had agreed to do, and accepted partial payments for work done at various stages in the completion of his contract at the prices agreed to be allowed him by orders or certificates drawn payable to John Quinlan, or bearer.

At the time when the contractor, Quinlan, in April, 1902, abandoned the contract, $2,115.01 was due and payable to him for work theretofore done by him under the contract. This portion of the fund was actually due to Quinlan when the complainant’s lien notice was filed. In addition to the $2,115.01, there was another sum of $3,711.75 which had also been earned by Quinlan by work done under the contract. This was the twenty per cent, retained under section 25 of the contract, which, under section 26, became payable to the contractor within fifteen Jays after the engineer should have certified that the work had been finally completed on the part of the contractor. This is the portion of the fund which when the lien notice was filed was “to grow due” to Quinlan.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Johnson v. Fred L. Emmons, Inc.
170 A. 850 (New Jersey Court of Chancery, 1934)
Buskirk v. State-Planters Bank & Trust Co.
169 S.E. 738 (West Virginia Supreme Court, 1933)

Cite This Page — Counsel Stack

Bluebook (online)
57 A. 471, 66 N.J. Eq. 180, 21 Dickinson 180, 1904 N.J. Ch. LEXIS 119, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pierson-v-borough-of-haddonfield-njch-1904.