Pierce v. Sinner

140 P.2d 474, 60 Cal. App. 2d 259, 1943 Cal. App. LEXIS 516
CourtCalifornia Court of Appeal
DecidedAugust 20, 1943
DocketCiv. No. 2896
StatusPublished

This text of 140 P.2d 474 (Pierce v. Sinner) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pierce v. Sinner, 140 P.2d 474, 60 Cal. App. 2d 259, 1943 Cal. App. LEXIS 516 (Cal. Ct. App. 1943).

Opinion

GRIFFIN, J.

Defendants and appellants John B. Sinner and Oscar A. Sinner, are partners, doing business as Sinner Brothers, and were engaged in the contracting business. They were the general contractors employed to remodel a cathedral located in San Diego. As a part of the work to be done, the outside of the building was changed and resurfaced. There were numerous buttresses projecting from the outside walls o-f the building, between which appeared recesses. It was [261]*261while he was working upon the surface of one of these recesses that plaintiff and respondent was injured.

Plaintiff was a plasterer employed by the plastering subcontractors, Larson Brothers. Lester A. Larson was one of the members of that firm. Sinner Brothers, under its general contract, was required to build, construct, maintain and make the necessary changes in the scaffolding which was used by the plasterers and others.in doing the work required to be done. The resurfacing of the building was done by the ‘ ‘ gun-nite process, ’' with a machine designed for the purpose, which forced heavy plastering material through a hose to a nozzle and the gunnite crew operated the nozzle so as to spray the material under pressure upon the outside of the building. This gunnite material dried quickly, but before it was set it was necessary to smooth out the rough places which were a usual and customary incident of the gunnite process. This smoothing was the work of the plasterers. They followed the gunnite crew and, working from the scaffold, reached the wall surface and put the final touches on the gunnite finish. In doing this work it was customary for the plasterer to use a tool known to the trade as a rod.

Defendant John B. Sinner testified concerning the details of the scaffold, as constructed by him. He identified the model which he had made to illustrate its construction. Witnesses on behalf of the plaintiff disputed his testimony in this regard, and although they admitted that this model correctly portrayed the scaffold as it was originally built, they contended that the scaffold had been changed and portions thereof removed shortly before the accident, as portrayed by a model made and identified by Lester A. Larson. All of plaintiff’s witnesses agreed that Larson’s model was correct. As originally constructed, and as illustrated by Mr. Sinner, the scaffold had an additional platform which extended into the recess between the two buttresses. The scaffold, as described by plaintiff's witnesses and illustrated by the model, did not have such extension, but the planks forming the platform extended' outside of the buttresses. Originally, the scaffold was a regulation, pole-type scaffold. The “uprights” were 4"x4". The ledger boards were l"x8". The planks for the flooring of the scaffold were 2"xl0" and 16z long. At the time of the accident there were two planks constituting the lower floor or tier of the scaffold which were laid about six feet from the ground and about four feet from the recess walls. The scaf[262]*262folding as originally constructed was too close to the building for the use of the gunnite men and the plasterers. The evidence would indicate that it was at Larson’s suggestion that the defendants made the change in the plans of the original scaffold, and three tiers were rebuilt by them. Defendants maintain otherwise.

Just prior to the time of the accident here involved Mr. Larson and plaintiff had been smoothing the cement and marking it off in squares on the first floor or tier of the scaffold. Plaintiff found that it was necessary to have additional platform laid into the recess before he could reach in and finish the work in that corner. He notified Larson of his inability to reach into the recess from the scaffold as thus constructed. Larson then called down to the defendants’ workmen: “Somebody get something in that angle so we can work it out.” It had been defendants’ previous instruction to Larson that if any planks were to be moved or rearranged for him, he should notify defendants and they would have their workmen do it. Thereafter, one of defendants’ workmen (Homsma) who was on the ground, started to select from the lumber around the building, some boards with which to erect an additional platform for Larson and the plaintiff. One Smith, who had been working with the gunnite crew and who was then on the ground, heard the request of Larson. He testified that Homsma “started to get up on the scaffold”; that he was awfully slow; that the gunnite was drying; that he, Smith, climbed up there and told Homsma to hand “me the planks up,” and that he handed him a 2x4 and a 2x10, each about 8 feet long; that he laid them on the scaffold as “near the corner as he could get them”; that he laid the 2x4 flat, rather than on its edge; that it ran “from the inner platform board ... in about a 45 degree angle over to the ledger board”; that the 2x10 was laid “practically perpendicular to the building, the end of it about even with the outside of the scaffold, and the other end a little farther from the recess than the ledger board, and this 2x10 is practically across the center of the 2x4”; that after he laid the boards he then went on with his gunnite work; that he did not pay any particular attention to the 2x4 when it was handed up to him; that he “never really looked at it. They was in a hurry, so I just laid it up there.” While he was thus placing the boards, Larson went around to the front of the building.

Plaintiff testified that while this operation was going on [263]*263he continued with his plastering work; that he did not see the boards laid or who laid them; that Larson returned, asked for the rod, and indicated to plaintiff, who weighed about 200 pounds, to stand on the outward end of the 2x10; that he did so and Larson stepped across to the other end, finished the recess plastering, and just as he was about to turn, the 2x4, over which the 2x10 had been placed, broke; that Larson fell to the ground unhurt; that plaintiff fell over backwards and was severely and permanently injured. The accident happened on Sunday. Sinner Brothers were pressed for time and had requested the plasterers and the gunnite men' to work on that day in order to meet a deadline. The gunnite men were paid by Sinner Brothers but the gunnite equipment was rented from one Woods. No carpenters were present on the outside of the building when the necessity for additional timbers became apparent. Oscar Sinner was a carpenter and was inside of the building directing the work there. John B. Sinner was on the outside of the building engaged in general supervision of the work. No broken 2x4 was found after the accident. John B. Sinner testified that he looked for one but did not see any around; that there were several 2x4’s around the building; that he did not authorize Smith, the gunnite man, to rebuild or reconstruct the platform in the manner indicated; that he did not see nor inspect the lumber placed thereon for that purpose, and that he did not see plaintiff fall, although he was about 15 feet from him at the time; that he rented the gunnite men and equipment by the day and paid them and carried insurance on them; that he directed their work but did not have the right nor power to discharge them; that Woods gave no instructions to him regarding .their work while they were employed on that job. Other witnesses testified that they saw the 2x4 break, but did not examine it for imperfections or defects. Apparently, as a result of the imperfection in the 2x4 or in the manner in which it was laid, plaintiff received severe injuries. Plaintiff recovered judgment against defendants in the sum of $10,000. Defendants appealed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Silberman v. Industrial Accident Commission
134 P.2d 228 (California Supreme Court, 1943)
Douglass v. Crabtree
134 P.2d 912 (California Court of Appeal, 1943)
Dingman v. AF Mattock Company
104 P.2d 26 (California Supreme Court, 1940)
Hayden v. Paramount Productions, Inc.
91 P.2d 231 (California Court of Appeal, 1939)
DeGraf v. Anglo California National Bank
92 P.2d 899 (California Supreme Court, 1939)
Mudrick v. Market Street Railway Co.
81 P.2d 950 (California Supreme Court, 1938)
Lowell v. Harris
74 P.2d 551 (California Court of Appeal, 1937)
Fischer v. Davis Standard Bread Co.
24 P.2d 538 (California Court of Appeal, 1933)
Peters v. United Studios, Inc.
277 P. 156 (California Court of Appeal, 1929)
Callahan v. Harm
277 P. 529 (California Court of Appeal, 1929)
Brumhall v. Sutherland
293 P. 672 (California Court of Appeal, 1930)
McKeon v. Lissner
223 P. 965 (California Supreme Court, 1924)
Billing v. Southern Pacific Co.
209 P. 241 (California Supreme Court, 1922)
Fennessey v. Pacific Gas & Electric Co.
124 P.2d 51 (California Supreme Court, 1942)

Cite This Page — Counsel Stack

Bluebook (online)
140 P.2d 474, 60 Cal. App. 2d 259, 1943 Cal. App. LEXIS 516, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pierce-v-sinner-calctapp-1943.