Pierce Lathing Co. v. Isec, Inc.

956 P.2d 93, 114 Nev. 291, 1998 Nev. LEXIS 34
CourtNevada Supreme Court
DecidedApril 2, 1998
Docket28895
StatusPublished
Cited by10 cases

This text of 956 P.2d 93 (Pierce Lathing Co. v. Isec, Inc.) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pierce Lathing Co. v. Isec, Inc., 956 P.2d 93, 114 Nev. 291, 1998 Nev. LEXIS 34 (Neb. 1998).

Opinion

OPINION

Per Curiam:

Appellant Pierce Lathing Company (“Pierce”) and respondent ISEC, Inc. (“ISEC”) were subcontractors in connection with construction of luxury suites at the Caesar’s Palace resort in Las *293 Vegas. The stated contract price was $78,000.00. The subcontract contained the following “retention” provision:

ISEC shall upon receipt from the Owner pay the subcontractor 90% of such work, labor, and materials and shall retain the remaining 10% until the final completion and acceptance of all work covered by this Subcontract, and such percentage so retained shall not be considered monies due and owing until the work under the contract has been completed to the satisfaction of and the same acceptance by the Owner and payment therefore has been made by Owner to ISEC. All pay estimates must be submitted in an approved form on or before the 15th day of each month and will be paid within 10 days after the pay request is accepted by the Owner and the Owner has paid ISEC.

Pursuant to the subcontract, Pierce agreed to paint and install glass fiber reinforced gypsum (“GFRG”) moldings for the Caesar’s Palace job. ISEC was to supply the GFRG molding for the installation and painting. 1

Pierce alleges that the GFRG molding supplied by ISEC was substandard. 2 However, due to time constraints, the general contractor, Perini Construction Company (“Perini”), instructed Pierce to go forward with the installation of the molding. Pierce claims it honored the responsibilities under its subcontract with ISEC. The defective molding allegedly caused Pierce to expend extra time and services re-working the substandard moldings.

Specifically, Pierce states that ISEC required Pierce’s employees to perform “antique” and “opaque” painting. When Pierce received ISEC’s order, Pierce asserted that it was entitled to additional compensation because antique painting was a “special finish” which was specifically excluded from the Pierce/ISEC subcontract. Pierce’s paint expert testified that the painting industry does indeed consider “opaque” and “antique” painting as types of “special finishes.” ISEC concedes that the “special painted finish” is essentially an artistic painted finish. ISEC’s project manager, Ms. Hoffritz-Brown, could not give a specific reason at trial as to why the contract excluded “special finishes” and “special painted finishes.”

When Pierce submitted invoices for the extra work performed to repair the GFRG moldings and perform antique painting work, ISEC denied payment. On August 30, 1994, ISEC wrote Pierce a letter and enclosed two checks totalling $12,028.70 — check num *294 ber 78372 for $11,638.70 and check number 78371 for $390.00. The cover letter provided:

Pursuant to our conversation on August 18, 1994, I have looked into your matter regarding the Antique and Glaze Finishing for the Architectural Woodwork along with the installation of the GFRG molding for the above referenced project and for all reasons previously stated, your position is without merit. Accordingly, we reject any additional claims and are prepared to tender to your firm the final payment due Pierce Enterprises in the amount of $12,028.70. Execution of this check will constitute full satisfaction of all obligations owed by ISEC, Incorporated to Pierce Enterprises.

Pierce forwarded the checks to its main office in Fresno, California, where the checks were eventually deposited into the Pierce Enterprises account on February 6, 1995. Pierce included a disclaimer that stated, “The above terms are not accepted by payee, payee claims extra work in the amount of $71,031.00.” According to ISEC, Pierce violated the endorsement/cashing restriction as set forth in ISEC’s letter to Pierce by including the disclaimer on the checks.

On September 30, 1994, Pierce’s counsel wrote ISEC, demanding payment of $49,000.00 for settlement. Although ISEC was not amenable to discussing the matter any further, it did not notify Pierce of its intent to utilize an accord and satisfaction as a defense. Pierce filed a complaint on December 6, 1994. ISEC’s answer did not affirmatively allege accord and satisfaction. 3 A five-day bench trial commenced on February 12, 1996.

After Pierce introduced the checks and letter during the second day of trial, ISEC moved to amend its answer to include accord and satisfaction as an affirmative defense. The district court expressed great concern regarding ISEC’s failure to notify Pierce of this possible defense, stating that ISEC should have previously amended its answer to include it. After initially denying ISEC’s motion to amend its answer, the district court ultimately allowed the amendment pursuant to Adelman v. Arthur, 83 Nev. 436, 433 P.2d 841 (1967).

On February 21, 1994, ISEC moved for dismissal pursuant to NRCP 41(b), arguing that the cancelled checks constituted an accord and satisfaction as a matter of law. The court extended *295 Pierce one week to find authority against the motion. Thereafter, the district court granted ISEC’s motion to dismiss.

Pierce appeals the district court’s order granting ISEC’s motion at trial to amend its answer, the order of dismissal, and the order denying its motion to retax costs.

DISCUSSION

ISEC’s motion to amend

Pierce contends that the district court abused its discretion when it granted ISEC’s motion to amend its answer pursuant to NRCP 15(b). 4 Pierce further argues that ISEC purposely concealed its intent to plead accord and satisfaction until the second day of trial.

In addressing the importance of pleading affirmative defenses, this court has stated:

An affirmative defense raises a matter which is beyond the limits of the plaintiff’s prima facie case. Surprise and prejudice may result when evidence is admitted to prove a true affirmative defense that is without the scope of the plaintiff’s complaint.

See Mason v. Hunter, 534 F.3d 822, 825 (8th Cir. 1976). If an affirmative defense is not pleaded, it is deemed waived, and no evidence can be submitted relevant to that issue. Chisholm v. Redfield, 75 Nev. 502, 508, 347 P.2d 523, 526 (1959).

When the district court permitted ISEC to amend its answer, it relied upon Adelman v. Arthur, 83 Nev. 436, 433 P.2d 841 (1967). We held in Adelman that, despite a defendant’s failure to specifically plead accord and satisfaction under NRCP 8(c), a narrow exception may apply. This court stated:

In the case under consideration neither Arthur nor Prudential especially pleaded accord and satisfaction as required by NRCP 8(c), however, there occurs an exception

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Baluma, S.A. v. Sriqui
D. Nevada, 2021
Guzy v. Arbor Co., LLP
Nevada Supreme Court, 2018
Campos v. Town of Pahrump
274 F. Supp. 3d 1106 (D. Nevada, 2017)
Whealon v. Sterling
119 P.3d 1241 (Nevada Supreme Court, 2005)
J.A. Jones Construction Co. v. Lehrer McGovern Bovis, Inc.
89 P.3d 1009 (Nevada Supreme Court, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
956 P.2d 93, 114 Nev. 291, 1998 Nev. LEXIS 34, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pierce-lathing-co-v-isec-inc-nev-1998.