Piedmont Engineering & Construction Corp. v. Amps Electric Co.

292 S.E.2d 411, 162 Ga. App. 564, 1982 Ga. App. LEXIS 2244
CourtCourt of Appeals of Georgia
DecidedJune 14, 1982
Docket63755
StatusPublished
Cited by3 cases

This text of 292 S.E.2d 411 (Piedmont Engineering & Construction Corp. v. Amps Electric Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Piedmont Engineering & Construction Corp. v. Amps Electric Co., 292 S.E.2d 411, 162 Ga. App. 564, 1982 Ga. App. LEXIS 2244 (Ga. Ct. App. 1982).

Opinion

Birdsong, Judge.

Breach of Contract. The facts of this case show that Piedmont Engineering & Construction Company was the prime contractor on several large apartment and condominium projects. One of these was in Gainesville (the Woodlake project) and one in Marietta (the Woods project). Piedmont subcontracted with Amps Electric Company, Inc. to perform all the electrical work on these projects. The agreement was that Amps would purchase all the electrical supplies necessary to complete the projects and install the electrical components of the projects. Amps bid a set rate for each project and was responsible for completing the electrical work within the bid cost subject to approved changes. The Woodlake project was bid at $72,375 and the Woods project bid at $116,911. Amps was located in Griffin and found that servicing the work at the Woodlake site in Gainesville was creating a transportation problem. Amps entered into an agreement with Service Electric to do the electrical work on the Woodlake project. Amps’ agreement with Service was for Service to purchase the electrical supplies and do the installation. Amps’ remuneration would be ten percent of the project (or $7,200) and Service would retain the remainder of the $72,375. Service apparently purchased material for other contracts it was performing at the same time. Amps had estimated the costs of electrical supplies for the Woodlake project as costing approximately $23,000. Service Electric charged electrical supplies to an electrical supplier, Goforth Electric Supply, of over $59,000, plus another $700 from City Plumbing Co. For reasons not shown on the record, Piedmont required Amps to resume its primary responsibility for the electrical work and remove Service from the project. Service had worked on the job from about February 1973 until April 1973, at which time Amps resumed the work and continued the project until the electrical portion was completed, and accepted by Piedmont and the owner. After Amps resumed work in its own capacity in April, Piedmont issued checks to Amps payable to Amps and Goforth Electric Supply as joint payees. Prior to that time, Piedmont had issued all draw checks to Amps alone. These earlier checks had been picked up by Service and negotiated by Service by virtue of a power of attorney. Amps denied owing any money to Goforth Electric Supply or City Plumbing Co. for any electrical supplies utilized on the Woodlake *565 project. Although Goforth and City Plumbing each filed liens against the Woodlake property, neither ever prosecuted their lien nor collected any money from Amps or from Piedmont. Thus, it reasonably appears that Service probably charged electrical supplies from Goforth for material for projects other than the Woodlake job. Up until Piedmont started issuing checks in the joint names of Amps and Goforth, Piedmont had paid Amps $49,470 toward the total contract price of $72,375, leaving a balance of $22,905. From April until the completion of Amps’ work, Piedmont issued one check payable to Goforth and Amps in the amount of $11,205. Amps negotiated the check and deposited it into its account without obtaining the endorsement of Goforth. Upon protest of improper endorsement, Amps returned the $11,205 to the bank. Thereafter Piedmont issued two more checks, also picked up by Amps but payable to Amps and Goforth in the amount of $4,750. Piedmont also prepared another check payable to Amps and Goforth in the amount of $1,447 but this check was never picked up by Amps and remained in the possession of Piedmont. After the first $11,205 check was protested, the president of Amps went to Goforth and sought Goforth’s cooperation in co-indorsing the checks. Goforth refused to cash any checks until satisfactory arrangements were made to settle Service’s indebtedness to Goforth amounting to $59,000. As a result Amps was not able to endorse or obtain the proceeds of any of the jointly payable checks issued by Piedmont after Amps returned to the Woodlake job in April, leaving an unpaid balance of $22,905.

As to the Woods project, the evidence shows that Amps entered into the same general contractual agreement with Piedmont as on the Woodlake job. Contrary to the results obtained in the Woodlake project, both Piedmont and Amps were required to leave the Woods project prior to its satisfactory completion. Up until Amps and Piedmont were required to leave the site, Piedmont had paid Amps approximately $81,726. Amps offered testimony that it submitted draws once each month. Each of such draws had been paid when submitted except as to the last one. Shortly before termination by the owner, Amps submitted a draw to Piedmont for $8,114. Also pursuant to the contract, Piedmont had retained $2,717 which in the absence of dispute would be paid to Amps upon completion of the work. Amps had worked for approximately two weeks after the last unpaid draw (of $8,114) before termination. Amps therefore sought an additional $4,000 as an estimated figure for work performed during the last two weeks. Thus Amps sought $14,831 as an unpaid amount for the Woods project. However, Amps conceded that because it had not received its last draws, it was indebted to one of its suppliers in an amount exceeding $13,000. That supplier successfully *566 filed claim against Piedmont’s performance bond insurer for $9,565 necessitating Piedmont to reimburse its insurer the $9,565. Amps paid the supplier the remaining $4,000. After unsuccessful demands for the $22,905 plus interest paid on the Woodlake job and $14,831 unpaid on the Woods job, Amps brought the present suit against Piedmont. Piedmont entered a general denial and sought a $9,565 counterclaim against Amps as reimbursement for the contribution Piedmont made to its insurer. After a two-day trial, the jury returned a verdict for Amps in the amount of $22,905 plus $9,620 interest. Apparently the jury found no verdict in favor of Amps on its $14,831 claim emanating from the Woods project nor in favor of Piedmont on its $9,565 counterclaim. Piedmont brings this appeal enumerating seven errors. Held:

1. In commencing our consideration of this case, we must first determine so far as possible, what was involved in the monetary verdict of the jury. While there were two separate contracts involving two different work sites, it appears obvious that the jury awarded Amps full recovery on its demand for the unpaid balance on the Woodlake project. Amps sought $22,905 plus interest, which was the exact amount awarded. In relation to the Woods project, Amps sought $8,114 as an unpaid draw (for work completed), $2,717 retained by Piedmont over the working life of the contract, and $4,000 as an estimated cost for the last period of work, a period that was estimated as one, two or three weeks as to length and equally indefinite as to expense. Ignoring because of vagueness the $4,000 figure, Amps’ more concrete demand for approximately $10,000 was generally offset by the counterclaim by Piedmont for approximately $9,600. In any event, the verdict transparently omitted any monetary recovery either for Amps or Piedmont based on the Woods project. We feel justified in reaching this conclusion because a verdict and judgment must be construed in connection with the pleadings. Bentley v. Still, 198 Ga. 743 (32 SE2d 814). Moreover, the judgment of the court should conform to the reasonable intendment of the verdict upon which it is based. Turley v. Turley, 244 Ga. 808, 809 (262 SE2d 112). In substance therefore, those enumerations of error based upon the Woods project which Piedmont protests benefit Amps, at best are harmless. See

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hodges v. Vara
603 S.E.2d 327 (Court of Appeals of Georgia, 2004)
Armech Service Co. v. Rose Electric Co.
386 S.E.2d 709 (Court of Appeals of Georgia, 1989)
Glen Restaurant, Inc. v. West
296 S.E.2d 153 (Court of Appeals of Georgia, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
292 S.E.2d 411, 162 Ga. App. 564, 1982 Ga. App. LEXIS 2244, Counsel Stack Legal Research, https://law.counselstack.com/opinion/piedmont-engineering-construction-corp-v-amps-electric-co-gactapp-1982.