Piedmont Aviation, Inc. v. AIR LINE PILOTS ASS'N, INTERNAT'L

347 F. Supp. 363, 81 L.R.R.M. (BNA) 2042
CourtDistrict Court, M.D. North Carolina
DecidedAugust 11, 1972
DocketC-154-WS-69
StatusPublished

This text of 347 F. Supp. 363 (Piedmont Aviation, Inc. v. AIR LINE PILOTS ASS'N, INTERNAT'L) is published on Counsel Stack Legal Research, covering District Court, M.D. North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Piedmont Aviation, Inc. v. AIR LINE PILOTS ASS'N, INTERNAT'L, 347 F. Supp. 363, 81 L.R.R.M. (BNA) 2042 (M.D.N.C. 1972).

Opinion

MEMORANDUM OPINION

EUGENE A. GORDON, Chief Judge.

This case arises from events first occurring in 1965. In that year the plaintiff, Piedmont Aviation, Inc. (Airline), decided to buy twelve Boeing 737 twin-turbojet aircraft (737). In the following year the defendant, the Air Line Pilots Association, International (Alpa), revised its crew complement policy to provide for a three-pilot crew on all turbojet aircraft certified after 1966. Alpa made the revision in spite of findings by the Federal Aviation Administration that the 737’s can be safely flown with a two-pilot crew complement.

Alpa contends that the revision in the crew complement policy was made solely on safety considerations and that the FAA’s findings are not binding because the FAA is directed to maintain only minimum safety requirements. The revision is purported to be binding on all of its members and prohibits them from operating any turbojet aircraft with less than a three-pilot crew.

Airlines all over the United States whose pilots were members of Alpa began negotiations with Alpa on this question. The plaintiff-Airline entered into extensive bargaining with Alpa, and on July 24, 1968, the parties entered into a comprehensive collective agreement which settled such issues as longevity pay, salaries, flight scheduling, vacations, etc., for all aircraft except the 737. Also on July 24, the parties entered into a supplemental agreement dealing with the crew complement of the 737’s. In this agreement, the Airline agreed to allow three-pilot crews for the 737's and established the rates of pay for these officers until a decision on the same issue was reached by United Airlines and Alpa who were in the process of arbitrating the issue before a Special Review Board. The supplemental agreement states:

“Rates for a 2-man operation (80 hours) effective 1/1/69 based on the assumption that United procedures or arbitration results in a decision for a 2-man operation: (rates omitted)
■Js1 w ^ y?
“In the event the United arbitration or procedures result in a decision for a 3-man operation, the parties agree to reopen negotiation under the provisions of the Railway Labor Act for 3-man operations and rates of pay beginning January 1, 1969.”

United subsequently agreed to the three-pilot crews on its 737’s and the plaintiff and Alpa reopened negotiations. Alpa contends that the negotiations were only to settle working conditions, duties, training, and rates of pay because the question of the crew complement had been settled by the United decision. The plaintiff-Airline, however, contends that the supplemental agreement did not mean that they were bound to follow the United decision and that the parties had merely recessed. Further negotiations, including the aid of the National Mediation Board, proved fruitless and the Airline announced that it was discontinuing the three-pilot crews.

On July 21, 1969, the plaintiff-Airline attempted two-pilot operation of the 737’s. Alpa asked the federal district court in Washington, D. C., to grant a temporary restraining order to prevent the two-pilot operation, but the court refused to grant the temporary injunction on the grounds that Alpa did not show a reasonable probability of success at the final hearing of the matter. Ruby v. Piedmont Aviation, Inc., No. 1820-69 (D.D.C. August 1, 1969).

*365 Alpa had already called a strike of all pilots employed by the plaintiff-Airline, and on August 5, 1969, the Airline sought injunctive relief in this Court on the grounds that Alpa had not bargained in good faith as required by the Railway Labor Act, 45 U.S.C. § 152, First. The Court granted the requested relief on August 14, 1969, upon a finding that irreparable injury was occurring to the general public because of the strike. Alpa was ordered to cancel the strike and to maintain the status quo of two-pilot crews until the case could be decided on its merits. The temporary injunction was affirmed on appeal but modified to the extent that the status quo was to be maintained with three-pilot crews. Piedmont Aviation, Inc. v. Air Line Pilots Association, International, 416 F.2d 633 (4th Cir.1969), cert. denied 397 U.S. 926, 90 S.Ct. 924, 25 L.Ed.2d 105 (1970), reh. denied 398 U.S. 915, 90 S. Ct. 1687, 26 L.Ed.2d 80 (1970).

Through these preliminary stages of the litigation, both parties apparently assumed that the dispute was a major dispute and, therefore, within the district court’s jurisdiction as opposed to a minor dispute which is within the exclusive jurisdiction of the System Board of Adjustment. However, in its opinion affirming the temporary injunction the Fourth Circuit Court of Appeals indicated that the supplemental agreement of July 24 might have changed the dispute from a major dispute to a minor one, and even though the parties thought it was a major dispute, their designation is not controlling. Piedmont Aviation, Inc. v. Air Line Pilots Association, International, supra, 416 F.2d at 639. The Court further directed that this Court,

“ [Sjhould not decide the case on its merits unless it is clearly shown, despite the supplemental agreement, that the controversy is still a major dispute. If there is a substantial question about the character of the dispute, the district court should condition injunctive relief upon prompt submission of the controversy to the Board so that it may consider the threshold question of its own jurisdiction.” 416 F.2d at 639. (Emphasis added)

This Court must therefore decide whether the plaintiff-Airline has clearly shown that the controversy is still a major dispute. In making this decision it is much easier to define major and minor disputes than it is to apply those definitions to the facts of this case.

A major dispute is one which arises over the formation of collective agreements or where there is no such agreement. A minor dispute contemplates the existence of a collective agreement and no effort is made to bring about a new agreement; the dispute arises over the meaning of the agreement or the proper application of the agreement. Elgin, Joliet & Eastern R. Co. v. Burley, 325 U.S. 711, 65 S.Ct. 1282, 89 L.Ed. 1886 (1944).

The Airline contends that the dispute is a major one because the parties had been negotiating without success on this issue and that they merely recessed to await the result of the bargaining between Alpa and United. Therefore, since no agreement had been reached, the crew complement would be the subject of an original dispute which has not been a part of any agreement. The Airline supports this argument by claiming that Alpa never believed that an agreement had been reached as indicated by its letter asking to reopen negotiations following the United decision. The Airline also points to the fact that Alpa repeatedly called the dispute a major one and it has waited for three and one-half years before trying to enforce the “agreement” before the System Board of Adjustment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
347 F. Supp. 363, 81 L.R.R.M. (BNA) 2042, Counsel Stack Legal Research, https://law.counselstack.com/opinion/piedmont-aviation-inc-v-air-line-pilots-assn-internatl-ncmd-1972.