Pickard & Butters Construction v. County of Santa Cruz CA6

California Court of Appeal·Decided December 22, 2020·No. H046816·Unpublished

Opinion

Filed 12/21/20 Pickard & Butters Construction v. County of Santa Cruz CA6 NOT TO BE PUBLISHED IN OFFICIAL REPORTS California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication or ordered published for purposes of rule 8.1115.

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

SIXTH APPELLATE DISTRICT

PICKARD & BUTTERS H046816 CONSTRUCTION, INC., (Santa Cruz County Super. Ct. No. 16CV01495) Plaintiff and Appellant,

v.

COUNTY OF SANTA CRUZ,

Defendant and Respondent,

and

NORTH AMERICAN SPECIALTY INSURANCE COMPANY,

Intervener and Respondent.

The trial court entered an order under Code of Civil Procedure section 664.6 enforcing a settlement agreement executed by a surety company as the assignee of plaintiff’s rights under an indemnity agreement; a judgment of dismissal followed. Plaintiff appeals, arguing that the trial court in Santa Cruz County lacked authority to enforce the settlement because issues implicating the indemnity agreement’s enforceability were being litigated in an action before the San Bernardino County Superior Court. For the reasons stated here, we will affirm the judgment. I. BACKGROUND The County of Santa Cruz awarded plaintiff Pickard & Butters Construction, Inc. (PBC) a public works construction contract exceeding $1.6 million. Acting as surety, North American Specialty Insurance Company (North American) issued payment and performance bonds on behalf of PBC in connection with the project. As consideration for those and other bonds issued on its behalf, PBC executed a general indemnity agreement in favor of North American. The agreement authorizes North American to demand that PBC deposit money as collateral security on the bonds upon a notice of claim or lawsuit asserting liability. The agreement assigns PBC’s rights under the project contracts to North American upon PBC’s default, and defines default as including failure to deposit any required collateral security. The agreement authorizes North American “to decide and determine in its sole discretion whether any claim, liability, suit or judgment made or brought against [North American or PBC] on any Bond shall or shall not be paid, compromised, resisted, defended, tried or appealed, and [North American]’s decision shall be final, binding and conclusive upon [PBC],” and authorizes North American as PBC’s attorney-in-fact to execute any release required to reach a claim settlement. North American received claims against a number of PBC’s bonded projects beginning in April 2015. Between August 2015 and October 2018, North American investigated and paid over 100 claims totaling nearly $1.4 million on PBC’s obligations, including $605,371 to resolve 29 bond claims on the Santa Cruz County project. North American sent PBC a written demand in March 2016 to deposit $1.4 million as collateral security to protect North American against loss under the indemnity agreement. PBC did not post collateral or respond in writing to the demand, and in December 2018 North American sued PBC in San Bernardino County Superior Court for breach of the indemnity agreement and reimbursement. In that action, North American sought

2 $1,397,415 as damages for bond payments made for several projects, including the $605,371 paid on the Santa Cruz County project. The dispute between PBC and Santa Cruz County arose in 2014 over change orders and delay. The County paid PBC a total of $1,349,859, and in December 2015 it denied PBC’s claim for $894,075 (the contract balance plus changes totaling $433,105 and $460,970 in damages). In 2016, PBC filed the instant action in the Santa Cruz County Superior Court for money due, and the County cross-complained for breach of contract. North American declined PBC’s requests to intervene in the lawsuit to jointly prosecute PBC’s claims against the County. The case proceeded through discovery, and the parties were prepared for trial at the November 2018 calendar call. No courtrooms were available, and trial was rescheduled for January 2019. After PBC rejected the County’s offer to settle in the instant case, the County approached North American in January 2019 regarding settling the matter on behalf of PBC. On January 11, 2019, the trial court granted North American’s ex parte application to intervene based on the indemnity agreement, and North American filed a complaint in intervention asserting all claims held by PBC against Santa Cruz County. North American and the County entered into a written settlement, and on January 23, the day before the rescheduled trial calendar call, North American notified PBC that the matter had been settled and demanded that the lawsuit be dismissed with prejudice. The trial date was vacated, and a briefing schedule was set for North American’s motion to enforce the settlement agreement under Code of Civil Procedure section 664.6. North American argued in its motion that the settlement agreement should be enforced and the lawsuit dismissed because upon PBC’s failure to comply with North American’s demand for collateral, the indemnity agreement assigned PBC’s rights against the County to North American, giving North American the right to settle the instant lawsuit. North American filed declarations (supported with documents) from a claims vice president, its attorney, and the County’s attorney. North American argued in 3 the alternative that it was the real party in interest to any claims that PBC had against the County by virtue of the indemnity agreement’s assignment clause, and it should therefore be substituted into the action in place of PBC. North American argued that PBC’s defenses to North American’s action in San Bernardino County and PBC’s attorney’s fee lien were irrelevant to the motion. PBC argued North American was seeking to have the trial court summarily adjudicate “numerous vigorously disputed” material breach issues which “cannot be adjudicated in the context of this motion” and “must be fleshed out” in the San Bernardino case. PBC argued that the evidence, if developed and presented to the trier of fact in the San Bernardino case, would show that North American had materially breached the indemnity agreement by acting in bad faith in several ways: paying indemnity claims over PBC’s objections; refusing to intervene at the outset to jointly prosecute PBC’s lawsuits against project owners; and intervening and settling the instant case secretly after PBC incurred trial preparation costs. PBC argued those breaches excused obligations to perform and rendered the assignment to North American under the agreement unenforceable. PBC also argued that the court in the San Bernardino case could find the indemnity agreement unenforceable under the equitable doctrine of laches because North American sat on its rights for over three years during which time PBC incurred several hundred thousand dollars in litigation expenses related to multiple projects. PBC asserted the settlement was unjust because it was undertaken in secret, sabotaged PBC’s right to go to trial, and the negotiated amount ($650,000) was less than half of what PBC was prepared to prove at trial. PBC urged that North American’s claim to settlement funds was junior to the attorney’s fee lien held by PBC’s lawyer. In a written decision following an unreported hearing, the trial court ruled: “The uncontradicted evidence admitted in support of the motion establishes that [PBC] breached its obligations under the Indemnity Agreement, at a minimum, by failing to pay amounts claimed by its subcontractors [and others] on the [Santa Cruz County] project 4 bonded by [North American]. Due to its obligation as surety, [North American] was required to pay the total amount of $605,371.33 to resolve those bonded claims.

Free access — add to your briefcase to read the full text and ask questions with AI

Pickard & Butters Construction v. County of Santa Cruz CA6, (Cal. Ct. App. 2020).

Pickard & Butters Construction v. County of Santa Cruz CA6 (Pickard & Butters Construction v. County of Santa Cruz CA6) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Agnew v. State Board of Equalization
981 P.2d 52 (California Supreme Court, 1999)
In Re Marriage of Assemi
872 P.2d 1190 (California Supreme Court, 1994)
Crawford v. Southern Pacific Co.
45 P.2d 183 (California Supreme Court, 1935)
Malouf Bros. v. Dixon
230 Cal. App. 3d 280 (California Court of Appeal, 1991)
Haldeman v. Boise Cascade
176 Cal. App. 3d 230 (California Court of Appeal, 1985)
Fiore v. Alvord
182 Cal. App. 3d 561 (California Court of Appeal, 1985)
Corkland v. Boscoe
156 Cal. App. 3d 989 (California Court of Appeal, 1984)
Perez v. Grajales
169 Cal. App. 4th 580 (California Court of Appeal, 2008)
McDermott, Will & Emery v. Superior Court
99 Cal. Rptr. 2d 622 (California Court of Appeal, 2000)
Skulnick v. Roberts Express, Inc.
2 Cal. App. 4th 884 (California Court of Appeal, 1992)
Alexander v. Codemasters Group Limited
127 Cal. Rptr. 2d 145 (California Court of Appeal, 2002)
Arntz Contracting Co. v. St. Paul Fire & Marine Insurance
47 Cal. App. 4th 464 (California Court of Appeal, 1996)
Johnson v. County of Fresno
4 Cal. Rptr. 3d 475 (California Court of Appeal, 2003)
Kohn v. Jaymar-Ruby, Inc.
23 Cal. App. 4th 1530 (California Court of Appeal, 1994)
Williams v. Saunders
55 Cal. App. 4th 1158 (California Court of Appeal, 1997)