Phoenix Iron Co. v. Richmond

17 D.C. 180
CourtDistrict of Columbia Court of Appeals
DecidedNovember 30, 1887
DocketNo. 9,144
StatusPublished

This text of 17 D.C. 180 (Phoenix Iron Co. v. Richmond) is published on Counsel Stack Legal Research, covering District of Columbia Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Phoenix Iron Co. v. Richmond, 17 D.C. 180 (D.C. 1887).

Opinion

Mr. Justice Hagner

delivered the opinion of the Court:

In the spring of 1883 P. EL Paine, the owner of lots at the northeast corner of H and Seventeenth Streets northwest, Washington, undertook the erection of a large building thereon, to be occupied as an apartment house; and in April of that year a contract in writing was entered into betwefen him and the complainant, a manufacturing firm of Trenton, N. J., to construct a steam heating apparatus in the new building for the sum of $3,500. Paine afterwards sold the property to an association incorporated in New York under the name of The Richmond, which accepted all the obligations, and became entitled to all the benefits of Paine’s contract. The complainant placed in the building all the materials requisite for the work, and received $1,700 on account. It proceeded with the work, and also performed extra work, for an agreed price; but dissensions arose between it and the owners, who claimed that the work had not been properly done, and refused on that ground to complete the payment. Finally, on the 6th of June, 1884, the following notice of an intention to hold a mechanics’ lien on the building was filed in the office, of the clerk of this Court:

The Phcenix Iron Company, a cor-" poration unde)' the laws of New Jersey, Claimant,
vs. V 890.
John F. Hanna and Mahlon Asheord, Trustees of The Richmond,
Owner.
Notice of lien.

Notice is hereby given that we intend to hold a mechanics’ lien upon parts of lots numbered 23 and 24 in W. [184]*184B. Hill’s trustees and others subdivision of lots in square numbered 165, being 100 feet on Seventeenth Street by 30 feet on H Street N. W., on the northeast comer of said streets, in the City of Washington, in the District of Columbia, and the building thereon, for the sum of $2,337.10, due to us from the owners thereof, for labor upon and materials furnished by us in the construction and repairs of heating apparatus of said building, under and by virtue of a contract with said owners by their agent.

The Phcbnix Iron Company, Claimant.
Pr. Robert B. Lines, Attorney.

The present bill was afterwards filed for the enforcement of the lien. After the defendant had answered, the cause was referred to the auditor, to ascertain and report from the evidence what amounts, if any, had been expended by defendant for work which should have been done by complainant under the contract, or to make good, work defectively done by complainant; and what further sum, if any, it would be necessary to expend to supply work omitted, and to remedy work defectively performed Toy complainant under the contract; and, also, what amount complainant expended, if anything, outside of thd sums stipulated to be paid by the contract, to overcome obstacles to the heating of the building caused by defendant’s fault.

The auditor filed his report, to which complainant and defendant excepted, both with respect to the results and the principles on which the findings were based.

The decree awarded $1,510.56, and interest from March 10, 1884, as due by The Richmond to complainant, declared it to be a lien on the real estate; and directed its sale, unless payment was made, by a designated day; and disallowed the defendant’s cross demands.

Both complainant and defendant appealed from the decree.

1. The first objection to the decree relied on by the de[185]*185fenclant in the argument here, is addressed to a supposed defect in the form of the notice of lien, which it is insisted asserts that the contract referred to was made with Hanna and Ashford, trustees of The Richmond; whereas, the bill sets forth a contract made with or adopted by The Richmond. But we do not think this objection is supported by the words of the notice itself, or even by the caption prefixed, which plainly enough shows that The Richmond was the owner of the property referred to, and that the contract was made with The Richmond by its agent.

But we hold that it was altogether unnecessary to have attached any such caption, and that a notice is entirely sufficient under Section 693, R. S. D. C., which states plainly, as this notice did, the intention of the claimant to hold a lien on the building; clearly describing the lot of ground, and specifically setting forth the amount claimed and stating that it was for labor and materials furnished in the construction and repair of the heating apparatus in the building constructed on the lot so described.

The notice of intention to hold a lien is required rather in the interest of ■ third persons than of the owner of the property, to the end that subsequent purchasers or incumbrancers resorting to the record for information as to the state of the title in this particular, may there be made aware of the existence, amount and character of all demands against the property, in the form of mechanics’ liens; and if the notice so filed furnishes all the information requisite to disclose these points of inquiry, the purpose of the law has been gratified, although there may be no formal caption attached, or although the caption may not be in all particulars critically correct.

2. It is next contended that the decree below should be reversed, because the notice of June 6, 1884, was not filed within three months after the work of the complainant was completed. The complainant averred in its bill that the apparatus, according to the terms of the contract, was to [186]*186have been, completed by September 1, 1883, but that in consequence of alterations and extra work required or made necessary by said Paine and the agents of The Richmond, its completion was delayed until the 10th of March, 1884, on which day it was fully completed. If this averment be correct, the notice was filed in time, even if the language of the act is to be construed as referring to the completion of the heating apparatus and repairs, as the point from which the three months is to be computed.

The defendant points to the statements of two of the witnesses who testify that the work was finished and the final tests made in February, 1884; but it appears that from December, 1883, there had been a constant controversy between The Richmond’s agents and the Phoenix Company, as to the delays in the completion of the work; and that as late as the 28th of February, the former made a formal demand upon the Phoenix Company that it should forthwith proceed to complete the work. On the 6th of March the complainant made the reply of that date, in which it charges upon The Richmond the responsibility for the delays; asserts that its work would have been entirely satisfactory if the building had been in proper condition to receive the apparatus, and refuses to proceed further with the work because of the defendant’s default.

Thus it appears that within the three months before the notice was filed, the defendant was insisting that the work was still incomplete; and the complainant was refusing, for the reasons stated, to do further work on the apparatus. It is further proved that in April the complainant was applied to to make good a crack in one of the boilers and performed the repairs as part of its original obligation and without charge, because such repairs were included in its agreement.

In South Fork Canal Co. vs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dermott v. Jones
69 U.S. 1 (Supreme Court, 1865)
Canal Co. v. Gordon
73 U.S. 561 (Supreme Court, 1868)

Cite This Page — Counsel Stack

Bluebook (online)
17 D.C. 180, Counsel Stack Legal Research, https://law.counselstack.com/opinion/phoenix-iron-co-v-richmond-dc-1887.