Phoenix Ins. Co. v. Wehr Constructors, Inc.

134 F.4th 933
CourtCourt of Appeals for the Sixth Circuit
DecidedApril 18, 2025
Docket24-5325
StatusPublished

This text of 134 F.4th 933 (Phoenix Ins. Co. v. Wehr Constructors, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Phoenix Ins. Co. v. Wehr Constructors, Inc., 134 F.4th 933 (6th Cir. 2025).

Opinion

RECOMMENDED FOR PUBLICATION Pursuant to Sixth Circuit I.O.P. 32.1(b) File Name: 25a0098p.06

UNITED STATES COURT OF APPEALS FOR THE SIXTH CIRCUIT

┐ PHOENIX INSURANCE COMPANY; TRAVELERS │ PROPERTY CASUALTY COMPANY OF AMERICA; ST. │ PAUL SURPLUS LINES INSURANCE COMPANY, │ Plaintiffs-Appellees, > No. 24-5325 │ │ v. │ │ WEHR CONSTRUCTORS, INC., │ Defendant-Appellant. │ ┘

Appeal from the United States District Court for the Eastern District of Kentucky at Ashland. No. 0:22-cv-00007—Karen K. Caldwell, District Judge.

Argued: February 12, 2025

Decided and Filed: April 18, 2025

Before: GILMAN, STRANCH, and LARSEN, Circuit Judges.

_________________

COUNSEL

ARGUED: Mark A. Boyle, BOYLE, LEONARD & ANDERSON, P.A., Fort Myers, Florida, for Appellant. Michael D. Risley, STITES & HARBISON, PLLC, Louisville, Kentucky, for Appellees. ON BRIEF: Mark A. Boyle, Thomas E. Shepard, BOYLE, LEONARD & ANDERSON, P.A., Fort Myers, Florida, for Appellant. Michael D. Risley, STITES & HARBISON, PLLC, Louisville, Kentucky, for Appellees. _________________

OPINION _________________

RONALD LEE GILMAN, Circuit Judge. Wehr Constructors, Inc. (Wehr) breached an agreement to build an addition to the St. Claire Medical Center (St. Claire) in Morehead, No. 24-5325 Phoenix Ins. Co. v. Wehr Constructors, Inc. Page 2

Kentucky. In response, St. Claire sued Travelers Casualty and Surety Company (Travelers Surety), Wehr’s performance-bond carrier, and Travelers Surety in turn brought in Wehr as a party to the litigation.

Wehr appeals the district court’s ruling that none of Wehr’s three insurers (Phoenix, St. Paul, and Travelers Property) had a duty to defend Wehr in that lawsuit. For the reasons set forth below, we AFFIRM the district court’s decision regarding St. Paul, but REVERSE its decision regarding Phoenix, VACATE its decision regarding Travelers Property, and REMAND for further proceedings as to these latter two insurers.

I. BACKGROUND

A. The Wehr-St. Claire Agreement

In April 2016, Wehr entered into a contract with St. Claire to construct a Medical Services Pavilion as an addition to St. Claire’s main hospital facility. Wehr and St. Claire set forth their agreement in a standard form issued by the American Institute of Architects (AIA) known as AIA document form A101-1997. The form is titled: “Standard Form of Agreement Between Owner and Contractor where the basis of payment is a STIPULATED SUM.” Section 14.2 of the Standard Form contains a termination clause that allowed St. Claire to terminate the contract if Wehr committed a “substantial breach,” provided that the architect on the project certified that sufficient cause exists (the Termination Clause). If St. Claire invoked the Termination Clause, Wehr would not be entitled to the remaining unpaid balance of the contract, and St. Claire could seek damages from Wehr under § 14.2.4 if the cost of completing the project exceeded the unpaid balance.

In compliance with the Construction Agreement, Wehr secured a performance bond for the project from Travelers Surety. The bond obligated Travelers Surety to complete the project if Wehr failed to satisfactorily perform under the Construction Agreement. Under Kentucky law, Travelers Surety could recover from Wehr any amount that Travelers Surety paid to satisfy Wehr’s liability or debts on the project. See Ky. Rev. Stat. Ann. § 412.080 (West 2024). No. 24-5325 Phoenix Ins. Co. v. Wehr Constructors, Inc. Page 3

B. Wehr’s breach and St. Claire’s termination

St. Claire claimed that Wehr failed to perform under the Construction Agreement. Among other things, Wehr missed deadlines, neglected to complete required inspections, and failed to properly supervise the subcontractors on the project. All of this resulted in serious defects to the building’s façade, air and moisture barrier, floor tiling, and fire-stopping mechanism. St. Clair alleged that, “as a result of water condensation throughout” the project, “mold conditions permeate the entire facility, endangering the health of patients and staff.”

Pursuant to the Termination Clause, St. Claire requested that the project architect certify that Wehr had substantially breached the Construction Agreement. After the architect performed an investigation, he issued a final report in January 2019 (the Architect Letter). The architect, in his letter, concluded that

[Wehr] has consistently demonstrated through failure to act, failure to complete, and failure to resolve, that it is unwilling or unable to correct the defects and deficiencies at this project for [St. Claire]. . . . Accordingly, . . . we do hereby certify that [Wehr] is ‘guilty of a substantial breach’ of the [Construction Agreement] under [the Termination Clause] and that sufficient cause exists to justify termination of the [Construction Agreement] should [St. Claire] wish to do so.

The Architect Letter also stated that St. Claire was entitled to withhold the remaining $2.2 million balance of the contract and that, between the likely damages and unpaid liens on the project, “this could be a $10+ million problem.”

Later that same month, St. Claire sent Wehr’s attorney a letter to terminate the Construction Agreement (the Termination Letter). The Letter read:

Based on the Architect’s certification of the multiple breaches of contract by Wehr Constructors, we are hereby providing notice that St. Claire Regional Medical Center is terminating its Medical Services Pavilion Construction Agreement executed by Wehr Constructors, Inc. on April 20, 2016, pursuant to the Termination For Cause provisions of Article 14.2 of the General Conditions of the Contract. It is the intention of St. Claire to cooperate with [Travelers Surety] to finalize construction in accordance with contract expectations in the most economical fashion possible consistent with industry standards of construction. To this end, St. Claire, or more likely [Travelers Surety], may seek to employ the services of No. 24-5325 Phoenix Ins. Co. v. Wehr Constructors, Inc. Page 4

Wehr’s former subcontractors and sub-subcontractors. Since this is contemplated by terms of the terminated contract, we request that you inform your client of St. Claire’s intent and its right to do so by the terms of the contract.

C. The insurance policies

Upon receipt of the Termination Letter, Wehr requested coverage under three insurance policies that it carried with three different entities (collectively, the Insurers): (1) a general- commercial-liability policy from Phoenix Insurance Company (Phoenix), (2) a professional- liability policy from St. Paul Surplus Lines Insurance Company (St. Paul), and (3) an “umbrella” excess policy from Travelers Property Casualty Company of America (Travelers Property). All of these are entities of Travelers Companies, Inc.

Summarized below are the relevant terms of the Phoenix and St. Paul policies. The relevant terms of the Travelers Property policy mirror those of the Phoenix policy.

i. Phoenix

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
134 F.4th 933, Counsel Stack Legal Research, https://law.counselstack.com/opinion/phoenix-ins-co-v-wehr-constructors-inc-ca6-2025.