Phoenix Corp. v. U.W. Marx, Inc.

64 A.D.3d 967, 881 N.Y.S.2d 714
Appellate Division of the Supreme Court of the State of New York·Decided July 9, 2009·Published·Cited by 4 cases

Opinion

Stein, J.

Appeal from an order of the Supreipe Court (Doyle, J.), entered April 9, 2008 in Rensselaer County, upon a decision of the court in favor of plaintiff.

Plaintiff was hired as a subcontractor by defendant U.W. Marx, Inc. (hereinafter defendant) to install steel reinforcement on a fast-track construction project pursuant to a written subcontract executed by the parties. It is undisputed that plaintiffs contemplated start date was delayed for a variety of reasons, all unrelated to plaintiff.

Shortly after plaintiff finally began its work with an initial crew of six workers and an anticipated maximum crew of 15, defendant’s vice-president asked David J. Murray, plaintiff’s owner, to put between 25 and 35 workers on the job with each working six 10-hour days per week. When Murray initially indicated that he would not accede to this request, an oral agreement was reached. According to Murray, in exchange for his agreement to increase the anticipated number of workers by more than twofold and to pay unanticipated overtime, defendant agreed to float plaintiffs entire weekly payroll and to cover the additional overtime expense. Defendant’s vice-president acknowledges that he orally agreed to float plaintiffs weekly payroll (which included overtime costs) if Murray acceded to his request that plaintiff substantially increase the number of workers on the job. However, he denies that this oral modification to the written subcontract included an agreement to pay overtime expenses.

[968] Following this conversation, plaintiff substantially increased the number of workers on the project and defendant began paying plaintiffs weekly payroll. After a dispute arose concerning plaintiffs failure to pay union benefits, defendant stopped floating the payroll. Plaintiff thereafter resumed paying its own weekly payroll and ultimately completed the job, with the exception of a small area at a particular loading dock. As to this unfinished work, plaintiff made three attempts to complete it but the area was not ready through no fault of its own.

Plaintiff, as now relevant, commenced this action to recover $209,650 in overtime expenses pursuant to the alleged oral agreement. Defendant, along with its bonding companies, counterclaimed for back charges pertaining to the unfinished work at the loading dock and for reimbursement of its payment of one half of the union’s counsel fees in a federal action commenced by the union to collect moneys due.* Following a nonjury trial, Supreme Court found that the parties entered into an oral agreement that included a commitment by defendants to cover plaintiffs overtime expenses and that this oral agreement was enforceable despite a clause in the subcontract precluding oral modifications. The court also denied defendants’ requests for the back charges and for reimbursement of counsel fees. Defendants now appeal.

Plaintiff has failed to demonstrate an enforceable oral modification to the parties’ written subcontract with regard to the payment of overtime expenses. Generally, a written agreement that includes a provision prohibiting oral modification—as does the subcontract here—“cannot be changed by an executory agreement unless such executory agreement is in writing and signed by the party against whom enforcement ... is sought” (General Obligations Law § 15-301 [1]; see Rose v Spa Realty Assoc., 42 NY2d 338, 343 [1977]). However, the statutory requirement of a writing may be avoided by proof of either partial performance of an oral agreement to modify a written contract, which must be “unequivocally referable to the oral modification” (Rose v Spa Realty Assoc., 42 NY2d at 343), or equitable estoppel, based upon conduct which is “not otherwise . . . compatible with the agreement as written” (id. at 344; see Turk v Anello, 280 AD2d 819, 820 [2001]). The Court of Appeals has articulated that it is not sufficient that the conduct of the parties indisputably evidences a mutual departure from the written agreement if such conduct does not satisfy these rules (see Rose v Spa Realty Assoc., 42 NY2d at 344).

[969] Here, the written contract provided for compensation to plaintiff based upon a price per ton of reinforcing steel, which price was to be “all inclusive.” The contract further provided that the price per ton “includes the cost of any overtime or work shifts necessary for completion of the work of this subcontract and the project in accordance with the contractor’s schedules,” and that plaintiff would be responsible for payment of its own payroll. There is no dispute that the written contract contemplated plaintiffs payment of overtime expenses, that in response to defendant’s request to accelerate plaintiffs work it was necessary for plaintiff to perform some of its base contract work during overtime hours thereby increasing its labor costs, or that defendant agreed to advance plaintiffs payroll and overtime expenses. Nor is there any dispute that the parties varied from the terms of the written contract simply by virtue of the fact that defendant advanced payments to plaintiff in order to meet its payroll and overtime expenses. Since it is uncontroverted that the parties agreed to orally modify the agreement and did, in fact, do so, we have no disagreement with Supreme Court’s finding to that extent. However, the issue is not whether any oral modification was made, but whether the parties’ conduct is unequivocally referable to an agreement that defendant would actually assume responsibility for the payment of any of plaintiffs overtime expenses.

Free access — add to your briefcase to read the full text and ask questions with AI

Phoenix Corp. v. U.W. Marx, Inc., 64 A.D.3d 967, 881 N.Y.S.2d 714 (N.Y. Ct. App. 2009).

64 A.D.3d 967 (Phoenix Corp. v. U.W. Marx, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Del Gallo Country Pools, Inc. v. Kulbako
2019 NY Slip Op 4800 (Appellate Division of the Supreme Court of New York, 2019)
J. Triple S., Inc. v. Aero Star Petroleum, Inc.
141 A.D.3d 778 (Appellate Division of the Supreme Court of New York, 2016)
UTILITY SERVICES CONTRACTING, INC. v. MONROE COUNTY WATER AUTHORITY
Appellate Division of the Supreme Court of New York, 2011