Phillips v. Conrad, Unpublished Decision (12-20-2002)

CourtOhio Court of Appeals
DecidedDecember 20, 2002
DocketAppeal No. C-020302, Trial No. A-9803731.
StatusUnpublished

This text of Phillips v. Conrad, Unpublished Decision (12-20-2002) (Phillips v. Conrad, Unpublished Decision (12-20-2002)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Phillips v. Conrad, Unpublished Decision (12-20-2002), (Ohio Ct. App. 2002).

Opinion

DECISION.
{¶ 1} On May 17, 1999, plaintiff-appellant William W. Phillips filed an amended complaint against defendant-appellee James Conrad, Administrator of the Bureau of Workers' Compensation (hereinafter referred to as "BWC"), and defendants Electronic Controls Co. ("Electronic Controls") and John Doe. Phillips brought multiple claims against Electronic Controls and John Doe for product defects and negligence, and Phillips sought a declaratory judgment that House Bill 350 (the Tort Reform Act) was constitutional. Phillips also brought a claim against BWC challenging the constitutionality of R.C. 4123.931 and thereby seeking to negate any subrogation right alleged by BWC.

{¶ 2} On August 13, 1999, BWC filed an answer and cross-claim against Electronic Controls and John Doe for a subrogation lien pursuant to R.C. 4123.931.

{¶ 3} On December 22, 1999, Electronic Controls filed a third-party complaint against Carter Construction Co. for indemnification and reimbursement, which was subsequently dismissed with prejudice on February 27, 2002.

{¶ 4} On July 30, 2001, Phillips dismissed with prejudice all claims against Electronic Controls following mediation.

{¶ 5} August 7, 2001, BWC filed a motion to enforce a settlement agreement previously entered into between itself, Phillips, and Electronic Controls. On September 27, 2001, the trial court overruled BWC's motion to enforce the settlement, but granted BWC leave to file a supplemental answer and counterclaim for breach of contract.

{¶ 6} On September 27, 2001, BWC filed a supplemental answer and counterclaim against Phillips for breach of contract and enforcement of the settlement agreement.

{¶ 7} On November 13, 2001, BWC filed a motion for summary judgment on the breach-of-contract counterclaim and for attorney fees. Specifically, BWC argued that there were no genuine issues of material fact because the settlement agreement, which (according to BWC) was effective on May 29, 2001, was binding and enforceable. In support of its motion, BWC attached an affidavit of Malinda Langston (BWC's attorney) and a letter dated June 5, 2001, from Phillips's counsel, Mark Adams.

{¶ 8} Langston stated in her affidavit that a mediation hearing was conducted on May 29, 2001, between Phillips, Electronic Controls, Carter Construction Co., and BWC. According to Langston, Electronic Controls had offered Phillips $750,000 in exchange for full settlement of the claims, and Phillips agreed to accept this amount if BWC was willing to accept $150,000 as its share of the settlement. Langston stated that she relied on the representations of Adams that Phillips, Electronic Controls, and BWC had entered into a binding settlement as outlined in Adams's June 5, 2001, letter. She further stated that, immediately following the Supreme Court of Ohio's decision in Holeton v. CrouseCartage Company1 holding that R.C. 4123.931 was unconstitutional, Adams contacted BWC to establish what impact Holeton had on the proposed settlement between BWC and Phillips. In response, Langston sent a letter to Adams stating that BWC had filed a motion for reconsideration with the Ohio Supreme Court and that, in her opinion, Holeton had no effect on the settlement because the parties had entered into a binding contract at the mediation hearing, the month before the effective date of Holeton.

{¶ 9} On November 28, 2001, Phillips filed a motion to stay the case pending the outcome of Santos v. Ohio Bureau of Workers'Compensation.2 Phillips stated that a class-action lawsuit had been initiated in Cuyahoga County on October 15, 1999. He stated that he was a member of the class, which included all injured workers who either had paid money or were obligated to pay money to BWC under the now unconstitutional R.C. 4123.931, and that a motion for summary judgment had been filed in that case.

{¶ 10} In reply to BWC's motion for summary judgment, Phillips argued that the settlement agreement was unenforceable pursuant toHoleton and that BWC should be equitably prevented from "gouging" him on the basis of an unconstitutional claim. Phillips argued that the settlement agreement, which was based on BWC's subrogation claim under R.C. 4123.931, was not valid because it had been signed by BWC one day after R.C. 4123.931 was held unconstitutional in Holeton v. CrouseCartage Co.3 And Phillips maintained that principles of equity precluded BWC from obtaining money to which it was never entitled. Finally, Phillips argued that resolution of the issue should be stayed pending the court's decision in Santos. Adams's affidavit was offered in support of this argument. It stated that BWC had been included in the May 29, 2001, negotiations because BWC had asserted a subrogation lien of over $600,000 against Phillips.

{¶ 11} The trial court granted BWC's motion for summary judgment in part and overruled it in part. The court ruled that the settlement agreement between Phillips and BWC was not based on BWC's subrogation rights pursuant to R.C. 4123.931, but rather on the desire to avoid further litigation of the issue. The court further ruled that both parties had assumed the risk of the pending Holeton decision. Thus, the court concluded that the invalidity of R.C. 4323.931 was immaterial and that the agreement was still binding. But the court also determined that Phillips's opposition to the motion was not frivolous, and BWC's request for attorney fees was accordingly denied.

{¶ 12} Phillips now asserts three assignments of error on appeal. Before we address the assignments, however, we must determine whether we possess jurisdiction over the appeal.

{¶ 13} R.C. 2505.02 confers upon appellate courts jurisdiction over "final order[s]."4 An order is "final" if it "affects a substantial right in an action that in effect determines the action and prevents a judgment."5

{¶ 14} When the trial court enters judgment with respect to fewer than all of the claims or all of the parties in a multi-claim, multi-party case, this court has no jurisdiction to entertain an appeal from that judgment in the absence of the trial court's certification, pursuant to Civ.R. 54(B), that "there is no just reason for delay." A Civ.R. 54(B) certification cannot transform a nonfinal order into an appealable order, but it can render appealable a final order entered in a single action involving multiple claims or parties and adjudicating fewer than all the claims or the rights and liabilities of fewer than all the parties.6 Without the certification, an order adjudicating fewer than all the claims does not ripen the action for appeal as to any of the claims or any of the parties.7

{¶ 15} This case involves multiple claims and multiple parties. Here, there is no doubt that the judgment being appealed is a "final order" as to BWC's breach-of-contract claim against Phillips. The question is whether, in the absence of Civ.R. 54(B) certification, the court's entry may be regarded as final as to the other claims and parties.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Whitaker-Merrell Co. v. Carl M. Geupel Construction Co.
280 N.E.2d 922 (Ohio Supreme Court, 1972)
State ex rel. Zellner v. Board of Education
297 N.E.2d 528 (Ohio Supreme Court, 1973)
Blakemore v. Blakemore
450 N.E.2d 1140 (Ohio Supreme Court, 1983)
Noble v. Colwell
540 N.E.2d 1381 (Ohio Supreme Court, 1989)
Burris v. Grange Mutual Companies
545 N.E.2d 83 (Ohio Supreme Court, 1989)
Wisintainer v. Elcen Power Strut Co.
617 N.E.2d 1136 (Ohio Supreme Court, 1993)
State v. Hochhausler
668 N.E.2d 457 (Ohio Supreme Court, 1996)
Holeton v. Crouse Cartage Co.
748 N.E.2d 1111 (Ohio Supreme Court, 2001)
Santos v. Ohio Bur. of Workers' Comp.
778 N.E.2d 1051 (Ohio Supreme Court, 2002)
Wisintainer v. Elcen Power Strut Co.
1993 Ohio 120 (Ohio Supreme Court, 1993)
Holeton v. Crouse Cartage Co.
2001 Ohio 109 (Ohio Supreme Court, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
Phillips v. Conrad, Unpublished Decision (12-20-2002), Counsel Stack Legal Research, https://law.counselstack.com/opinion/phillips-v-conrad-unpublished-decision-12-20-2002-ohioctapp-2002.