Phillips v. Braham & Co.
Opinion
Heard on the question of priorities as between persons claiming mechanic’s liens and the Exposition Building & Loan Company, mortgagee.
The question for determination is, whether or not the said Portmann perfected his lien in accordance with the provisions of the mechanic’s lien law (103 O. L., 371), and particularly Section 3 thereof, now known as Section 8312, General Code.
Portmann filed his lien on November 2, 1914, in the office of the county recorder of this county, about at 3:55 p. M- This was the last day upon which he could file it in order to secure the protection of the said mechanic’s lien law in so far as that part of the work for which he is claiming a lien of $70 is concerned, the work having been finished on September 3, 1914. As to the work for which a lien of $110 is claimed, that was completed on September 14, 1914, and the sixty-day limitation in the- lien law would not have run against it until November 13, 1914. On November 2, 1914, at about 5:05 p. m., Portmann [231]*231served notice of his liens upon the owner, Braham, and also at the same hour and date delivered to Braham a sworn statement, in accordance with the provisions of the act.
The only question raised as to the validity of these liens is whether or not the sworn statement, which is claimed to be required by the provisions of Section 8312, General Code, should be served on the owner prior to the time of filing the lien in the office of the recorder.
It is conceded by counsel that inasmuch as the now existing Ohio mechanic’s lien law is substantially the same as the Michigan statute on the same subject, the decisions of the courts of the state of Michigan, construing the Michigan act and its operation, should largely control the court in the construction of ' the Ohio statute and its operation, under the familiar principle that when the statute of another state has been adopted into our legislation, the known and settled construction of such a statute by the courts of that state should be considered as silently incorporated into the local act (Favorite v. Boohers, 17 Ohio St., 548; Brice v. Myers, 5 Ohio, 121). And it is only when a different policy is required or the reasoning of the courts seem to be unsound, that the construction of the statutes of the other states by their own courts will be disregarded here.
If this principle be true, then this question has been squarely decided by the Supreme Court of Michigan in the case of Holliday v. Mathewson, 146 Mich., 336, wherein it is held as follows (first proposition of the syllabus) :
“Delay in serving upon the owner the statement required by Section 10713, 3 Comp. Laws, until after the claim of lien required by section 10714 has been filed in the office of the register of deeds, is not fatal to a mechanic’s lien, where the statement is served before the time to file a lien expires, the lien not becoming effective until the statement is served.”
The court held that there is nothing inconsistent with this holding in the various Michigan cases cited to the court, which were also cited to this court in the present instance.
[232]*232The mere fact that the office of the recorder closes at four o ’clock in this county, is not sufficient of itself to raise a different construction of the statute. It is a matter of common knowledge that regulations as to the closing of the recorder’s office differ in the various counties of the state; and the county recorder, in the present instance, in order to accomodate Portmann’s attorney, might have kept his office open until midnight and the filing of the affidavit would have been in time. Therefore, as the time in which the lien could have been perfected was until midnight of November 2, 1914, the decision in Holiday v. Mathewson, supra, may be regarded by .this court as controlling, and the lien will be sustained.
The statement was made that our own court of appeals has in effect held that it is not necessary for a sub-contractor to file the kind of statement that has been discussed herein.
It is not necessary for me, in view of the conclusion I have come to, to pass upon the matter, and I expressly disavow any intention to do so.
Therefore, the finding of the court is, that the lien of Portmann is prior to the lien of the building association, but that the attempted liens of Seilkop, Kramer and the Johns-Manville Company are not.