Phillip and Benita Young v. Emilio and Mary Sanchez

Court of Appeals of Texas·Decided October 12, 2011·No. 04-10-00845-CV·Published

Opinion

MEMORANDUM OPINION

No. 04-10-00845-CV

Phillip and Benita YOUNG, Appellants

v.

Emilio and Mary SANCHEZ,

Appellees

From the 45th Judicial District Court, Bexar County, Texas Trial Court No. 2003-CI-16473 Honorable Michael Peden, Judge Presiding

Opinion by: Phylis J. Speedlin, Justice

Sitting: Catherine Stone, Chief Justice Phylis J. Speedlin, Justice Marialyn Barnard, Justice

Delivered and Filed: October 12, 2011 AFFIRMED Phillip and Benita Young appeal the trial court’s summary judgment rendered in favor of Emilio and Mary Sanchez, claiming in part that the court had no jurisdiction to grant summary judgment. We affirm the trial court’s judgment.

FACTUAL AND PROCEDURAL BACKGROUND This case began in 2003 as a dispute between neighbors Phillip and Benita Young and Emilio and Mary Sanchez over a concrete patio extension built by the Sanchezes in a five-foot

easement between the parties’ zero lot line residences in Woodlake Country Club Estates. The Youngs claimed the patio extension interfered with their use of the easement and damaged their property. The Youngs filed a declaratory judgment suit seeking confirmation of the easement and requesting that the court order the Sanchezes to remove all fences, concrete slabs, and other materials located within the easement. The Sanchezes answered by asserting a general denial and several affirmative defenses; they claimed the Youngs were informed of the proposed patio extension and had raised no objection. The Sanchezes also counterclaimed for nuisance and invasion of privacy based on the Youngs’ construction of a balcony that overlooks the Sanchezes’ fenced patio and yard.

In August 2005, the parties mediated the dispute with the Honorable Henry Schuble and reached a settlement which was memorialized in a “Mediated Settlement Agreement” dated August 10, 2005 and signed by all parties (the “Settlement Agreement”). Paragraph 2 of the Settlement Agreement provides, “If any dispute arises with regard to the interpretation or performance of this agreement or any of its provisions . . . the parties agree to try to resolve the dispute by phone conference with the mediator who facilitated this settlement.” As part of the Settlement Agreement, the judge selected an independent engineer to assess whether the Sanchezes’ concrete patio extension was negatively affecting drainage of the Youngs’ property and whether their home’s foundation had been damaged, and, if so, the estimated cost of any necessary repairs; in addition, the parties both agreed to install gutters on their property bordering the easement and to provide a key to any gate on the easement. Paragraph 3 of the Settlement Agreement requires the parties to comply with the engineer’s recommendations within 45 days of the engineer’s report. The engineer’s September 26, 2005 report found that drainage improvements on the Sanchezes’ concrete patio were needed, and included an estimate

of $3,393 for the proposed drainage improvements by Lovell Construction Co. When the Sanchezes commenced work on the drainage project, the Youngs objected that the report did not address all the issues stated in the Settlement Agreement. In August 2006, the engineer conducted a second evaluation at the Youngs’ request and prepared a second report in which he found that the minor foundation movement on the Youngs’ property was caused by shifting of the clay soil, and could not be attributed to the neighboring patio slab.

Two years passed with no resolution of the dispute. On September 15, 2008, the Sanchezes filed a “Third Amended Answer and Counterclaims” in which they asserted a new counterclaim for breach of contract alleging the Youngs had breached the Settlement Agreement by failing to install gutters on their property as required by Paragraph 5, and by interfering with the Sanchezes’ ability to comply with the agreement by completing the drainage improvements. The Sanchezes asserted that they installed gutters on their home in November 2005, within 45 days of the engineer’s report in accordance with the Settlement Agreement, but that the Youngs had not installed gutters on their property as required by the agreement. The Sanchezes sought actual damages for the increased cost of completing the drainage project plus attorney’s fees. The Youngs did not file any pleading in response to the counterclaim.

In 2009, the Sanchezes proceeded with completion of the drainage work on their property. Lovell Construction’s cost to complete the project had increased by $907 from the original estimate. The drainage improvements on the Sanchez property were inspected by the engineer and found to be satisfactory on April 7, 2009.

On August 4, 2010, the Sanchezes moved for a no-evidence summary judgment on the Youngs’ suit and for a traditional summary judgment on their counterclaim for the Youngs’ breach of the Settlement Agreement and their request for attorney’s fees. The Youngs did not

respond. On August 27, 2010, the trial court granted summary judgment in favor of the Sanchezes, ordering that the Youngs take nothing by their suit and awarding the Sanchezes $907 in breach of contract damages and $9,201.57 in attorney’s fees, plus court costs. The court further ordered the Youngs to install gutters on their home along the zero lot line wall by October 31, 2010. 1 The Youngs now appeal.

ANALYSIS

On appeal, the Youngs assert the trial court’s summary judgment must be reversed because: (1) there was a prior court ruling referring the matter back to mediation; (2) jurisdiction over the matter was vested in the mediator, not the trial court; (3) the Sanchezes’ summary judgment motion was barred by laches; (4) the Sanchezes failed to prove compliance with a condition precedent of the Settlement Agreement which required additional mediation; and (5) alternatively, the award of attorney’s fees is excessive as a matter of law.

Jurisdiction and Mediation In their first and second issues, the Youngs assert the trial court had no jurisdiction to grant summary judgment because any dispute was required to go back to mediation under Paragraph 2 of the Settlement Agreement, and the case had in fact been referred back to mediation by the trial court on April 13, 2006. The Youngs contend the Settlement Agreement and an April 13, 2006 court ruling “vested jurisdiction with the mediator not the trial court.” Although they assert that “the primary basis for this appeal is the lack of jurisdiction,” and “this case presents a clear cut issue of law,” the Youngs cite no legal authority in support of their argument. See TEX. R. APP. P. 38.1(i). Because subject matter jurisdiction cannot be waived, however, we will briefly address the issue of jurisdiction raised by the Youngs. See Tex. Ass’n of

Bus. v. Tex. Air Control Bd., 852 S.W.2d 440, 443-44 (Tex. 1993) (subject matter jurisdiction is 1 The Sanchezes’ brief notes the Youngs installed the gutters in November 2010.

never presumed and cannot be waived); see also Tex. Natural Res. Conservation Comm’n v. IT- Davy, 74 S.W.3d 849, 855 (Tex. 2002) (whether a trial court has jurisdiction is a question of law subject to de novo review).

Free access — add to your briefcase to read the full text and ask questions with AI

Phillip and Benita Young v. Emilio and Mary Sanchez, (Tex. Ct. App. 2011).

Phillip and Benita Young v. Emilio and Mary Sanchez (Phillip and Benita Young v. Emilio and Mary Sanchez) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Texas Natural Resource Conservation Commission v. IT-Davy
74 S.W.3d 849 (Texas Supreme Court, 2002)
McGuire v. McGuire
18 S.W.3d 801 (Court of Appeals of Texas, 2000)
Continental Homes of Texas, L.P. v. City of San Antonio
275 S.W.3d 9 (Court of Appeals of Texas, 2008)
Greathouse v. Charter National Bank-Southwest
851 S.W.2d 173 (Texas Supreme Court, 1992)
Hardman v. Dault
2 S.W.3d 378 (Court of Appeals of Texas, 1999)
Texas Ass'n of Business v. Texas Air Control Board
852 S.W.2d 440 (Texas Supreme Court, 1993)
Phifer v. Nacogdoches County Central Appraisal District
45 S.W.3d 159 (Court of Appeals of Texas, 2001)
Community Bank & Trust, S.S.B. v. Fleck
107 S.W.3d 541 (Texas Supreme Court, 2002)
In Re Barnes
127 S.W.3d 843 (Court of Appeals of Texas, 2003)
Chilton Insurance Co. v. Pate & Pate Enterprises, Inc.
930 S.W.2d 877 (Court of Appeals of Texas, 1996)
Kinnear v. Texas Commission on Human Rights Ex Rel. Hale
14 S.W.3d 299 (Texas Supreme Court, 2000)
Pickell v. Guaranty National Life Insurance Co.
917 S.W.2d 439 (Court of Appeals of Texas, 1996)
MBM Financial Corp. v. Woodlands Operating Co.
292 S.W.3d 660 (Texas Supreme Court, 2009)
Cordova v. Southwestern Bell Yellow Pages, Inc.
148 S.W.3d 441 (Court of Appeals of Texas, 2004)
Trevino v. Allstate Insurance Co.
651 S.W.2d 8 (Court of Appeals of Texas, 1983)
Betty Leavell Realty Co. v. Raggio
669 S.W.2d 102 (Texas Supreme Court, 1984)
Lehmann v. Har-Con Corp.
39 S.W.3d 191 (Texas Supreme Court, 2001)
Jim Rutherford Investment Inc. v. Terramar Beach Community Ass'n
25 S.W.3d 845 (Court of Appeals of Texas, 2000)
In Re Entergy Corp.
142 S.W.3d 316 (Texas Supreme Court, 2004)