Phillip A. Chisholm v. Uhp Projects, Incorporated, & Third Party v. Sealift, Incorporated Ultra Maritime, Incorporated Wilco Supply, Incorporated Spir Star, Incorporated Kutting, Incorporated Spir Star Druckschlauche Gmbh, Third Party

205 F.3d 731, 2000 A.M.C. 1050, 2000 U.S. App. LEXIS 3542
CourtCourt of Appeals for the Third Circuit
DecidedMarch 8, 2000
Docket99-1018
StatusPublished

This text of 205 F.3d 731 (Phillip A. Chisholm v. Uhp Projects, Incorporated, & Third Party v. Sealift, Incorporated Ultra Maritime, Incorporated Wilco Supply, Incorporated Spir Star, Incorporated Kutting, Incorporated Spir Star Druckschlauche Gmbh, Third Party) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Phillip A. Chisholm v. Uhp Projects, Incorporated, & Third Party v. Sealift, Incorporated Ultra Maritime, Incorporated Wilco Supply, Incorporated Spir Star, Incorporated Kutting, Incorporated Spir Star Druckschlauche Gmbh, Third Party, 205 F.3d 731, 2000 A.M.C. 1050, 2000 U.S. App. LEXIS 3542 (3d Cir. 2000).

Opinion

205 F.3d 731 (4th Cir. 2000)

PHILLIP A. CHISHOLM, Plaintiff-Appellant,
v.
UHP PROJECTS, INCORPORATED, Defendant & Third Party Plaintiff-Appellee,
v.
SEALIFT, INCORPORATED; ULTRA MARITIME, INCORPORATED; WILCO SUPPLY, INCORPORATED; SPIR STAR, INCORPORATED; KUTTING, INCORPORATED; SPIR STAR DRUCKSCHLAUCHE GMBH, Third Party Defendants.

No. 99-1018 (CA-96-578-2).

UNITED STATES COURT OF APPEALS, FOR THE FOURTH CIRCUIT.

Argued: November 30, 1999.
Decided: March 8, 2000.

Appeal from the United States District Court for the Eastern District of Virginia, at Norfolk.

Robert G. Doumar, Senior District Judge.

COUNSEL ARGUED: David Joel Berg, LATTI ASSOCIATES, L.L.P., Boston, Massachusetts, for Appellant. Temple Witt Cabell, SCHAFFER & CABELL, P.C., Richmond, Virginia, for Appellee. ON BRIEF: David H. Sump, CRENSHAW, WARE & MARTIN, Norfolk, Virginia, for Appellant.

Before WILKINSON, Chief Judge, KING, Circuit Judge, and Cynthia Holcomb HALL, Senior Circuit Judge of the United States Court of Appeals for the Ninth Circuit, sitting by designation.

Affirmed by published opinion. Senior Judge Hall wrote the majority opinion, in which Chief Judge Wilkinson joined. Judge King wrote a dissenting opinion.

OPINION

CYNTHIA HOLCOMB HALL, Senior Circuit Judge:

Philip Chisholm ("Chisholm") appeals the district court's order setting aside damages in the amount of $90,000 awarded against UHP Projects ("UHP") for breach of the warranty of workmanlike performance. We have jurisdiction pursuant to 28 U.S.C.§ 1291, and we affirm.

I.

UHP is a company that cleans tanks and holds for ocean vessels with ultra high pressure water jets. Sealift, Inc. ("Sealift") owned the ship S.S.ULTRAMAX which on July 1, 1994, was moored at Cargill South Terminal in Chesapeake, Virginia. On this particular day, Sealift had contracted with UHP to remove dust and scale from the ULTRAMAX's ballast tanks. The pump and hoses used to operate the ballast tank were owned by UHP. Chisholm was aboard the ULTRAMAX as a first assistant engineer.

Early that morning, as UHP employees were preparing to begin cleaning one of the ballast tanks, Patrick Courville, a UHP supervisor, noticed a leak in a connector between the two end fittings of the ultra high pressure hoses. He readjusted the connector to stop the leak and then directed another UHP employee to begin the blast. Within a few seconds of the jet reaching full power, the hose and/or a fitting failed causing the hose to blow apart from the end-fitting. The loose hose veered and struck Chisholm who was standing approximately 10 to 15 feet away from the ballast tank. Chisholm suffered a compound depressed skull fracture and a lacerated dura. Chisholm fully recovered from this serious injury and returned to work approximately 8 or 9 months later.

Chisholm presented a claim against the ship for maintenance and cure benefits, and for unseaworthiness, to which Sealift responded by tendering $29,025.93 for the maintenance and cure benefits. Sealift demanded that UHP participate in settlement negotiations with Chisholm and pay around $200,000 in indemnity. UHP refused Sealift's demand so Sealift filed suit against UHP in federal district court alleging causes of action arising under implied contractual indemnity and tort indemnity. Prior to summary judgment, UHP accepted that it had a duty to indemnify Sealift in accord with the admiralty warranty of workmanlike performance and agreed to tender Sealift the amount which Sealift settled with Chisholm. This amount was $200,000 plus the $29,025.93 in maintenance and cure benefits, a total payment by Sealift to Chisholm of $229,025.03. This exact amount was then tendered by UHP to Sealift as indemnity on or about December 11, 1996.

Meanwhile, on June 5, 1996, Chisholm filed a complaint against UHP pleading causes of action for negligence and an admiralty law claim for breach of the implied warranty of workmanlike performance. On cross-motions for summary judgment, the district court granted summary judgment for UHP on the negligence claim which left the admiralty claim as the sole surviving cause of action. See Chisholm v. UHP Projects, Inc., 30 F. Supp. 2d 928, 929 (E.D.Va. 1998). As a result, the district court concluded that Chisholm did not have a right to a jury trial but impaneled a jury anyway to function as an advisory body.1 See id. at 929-30. The admiralty claim proceeded to a two day trial in which the jury found liability and imposed $90,000 of damages against UHP. See id. at 930. The district court adopted the jury's verdict as its own and after post-trial briefing held that the prior settlement between Chisholm and Sealift, which exceeded the jury's award, operated to negate the award against UHP. See id. at 938-39. Consequently, the district court ordered this case dismissed on the merits and judgment entered in favor of UHP. See id. at 939. Chisholm appeals this ruling.

II.

Because this appeal is purely on a question of law, the standard of review is de novo. See United States v. Han, 74 F.3d 537, 540 (4th Cir. 1996). Chisholm's claim against Sealift arose under the doctrine of seaworthiness while his claim against UHP arose under the cause of action for breach of the implied warranty of workmanlike performance. The doctrine of seaworthiness arises by operation of law and states that a ship owner owes the seaman an absolute, non-delegable duty to provide a seaworthy vessel. See Mitchell v. Trawler Racer, Inc., 362 U.S. 539, 549-50 (1960) (seaworthiness is defined as a vessel that has a hull and equipment that are reasonably adequate in design and maintenance, and a crew that is of sufficient character to perform its intended function in the operation of the vessel). Liability for violation of the doctrine of seaworthiness is without fault. See id.

The implied warranty of workmanlike performance ensures that the stevedore will warrant the quality of his services while onboard the vessel. See Ryan Stevedoring Co. v. Pan-Atlantic Steamship Corp., 350 U.S. 124, 132-33 (1956) (overruled by Congress on different grounds, see Ducrepont v. Baton Rouge Marine Enterprises, Inc., 666 F. Supp. 882, 884-85 (1987) (stating that the congressional enactments sought to overrule only the damages aspect of the Ryan holding)). The warranty arises under operation of contract but extends to all foreseeable parties, including the employees of the shipowner. See Sanderlin v. Old Dominion Stevedoring Corp., 385 F.2d 79, 81-82 (4th Cir. 1967). Liability for the breach of the warranty of workmanlike performance arises without fault and appears to approach strict liability. See Salter Marine, Inc. v. Conti Carriers and Terminals, Inc., 677 F.2d 388, 390 (4th Cir. 1982).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bertram v. Freeport McMoran, Inc.
35 F.3d 1008 (Fifth Circuit, 1994)
Westinghouse Credit Corp. v. M/V New Orleans
39 F.3d 553 (Fifth Circuit, 1994)
Krieser Ex Rel. Krieser v. Hobbs
166 F.3d 736 (Fifth Circuit, 1999)
Mitchell v. Trawler Racer, Inc.
362 U.S. 539 (Supreme Court, 1960)
Waterman Steamship Corp. v. Dugan & McNamara, Inc.
364 U.S. 421 (Supreme Court, 1960)
United States v. Reliable Transfer Co.
421 U.S. 397 (Supreme Court, 1975)
McDermott, Inc. v. AmClyde
511 U.S. 202 (Supreme Court, 1994)
United States v. William H. Price, Jr.
288 F.2d 448 (Fourth Circuit, 1961)
Maritime Overseas Corporation v. United States
608 F.2d 1260 (Ninth Circuit, 1979)
Danny Bourque v. Diamond M. Drilling Company
623 F.2d 351 (Fifth Circuit, 1980)
United States v. Eldon Han
74 F.3d 537 (Fourth Circuit, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
205 F.3d 731, 2000 A.M.C. 1050, 2000 U.S. App. LEXIS 3542, Counsel Stack Legal Research, https://law.counselstack.com/opinion/phillip-a-chisholm-v-uhp-projects-incorporated-third-party-v-ca3-2000.