Philip Carey Manufacturing Co. v. Viaduct Place

58 S.E. 274, 1 Ga. App. 707, 1907 Ga. App. LEXIS 85
CourtCourt of Appeals of Georgia
DecidedMay 3, 1907
Docket281
StatusPublished
Cited by13 cases

This text of 58 S.E. 274 (Philip Carey Manufacturing Co. v. Viaduct Place) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Philip Carey Manufacturing Co. v. Viaduct Place, 58 S.E. 274, 1 Ga. App. 707, 1907 Ga. App. LEXIS 85 (Ga. Ct. App. 1907).

Opinion

Russell, J.

Philip Carey Manufacturing Company brought suit to foreclose a materialman’s lien on' the property called the Yiaduct Place, in the city of Atlanta, against Steiner-Emery Company as owners and J. F. Clemmons -as contractor. By agreement of the parties his honor, FI. M. Reid, judge of the city court of Atlanta, without the intervention of a jury, rendered judgment in the case, upon the following agreed statement of facts: , The Philip Carey Manufacturing Company is a corporation of Ohio with a place of business in the city of Atlanta, and is a material-man. J. F. Clemmons was a contractor, and had contracted to improve the Yiaduct Place. Clemmons purchased of the Philip Carey Manufacturing Company certain material, part of which, amounting to $51.15, was used in improving the building of Yiaduct Place. Said material was furnished during the month of August, 1905. Philip Carey Mánufacturing Company filed its claim of lien in the office of the clerk of the superior court of Fulton county, October 7, 1905, and it was recorded October 10, 1905. The building improved is in Fulton County, Ga. The Philip Carey Manufacturing Company filed their suit on October 13, 1905, against J. F. Clemmons, contractor, and Steiner-Emery Company, now Yiaduct Place, owners. Both of said parties were served October 20, 1905. Clemmons was adjudicated a bankrupt on October 5, 1905. On the schedule of said bankrupt it appears that the Philip Carey Manufacturing Company was a creditor of [709]*709the bankrupt in the sum of $159.76; and it was admitted that said debt was scheduled in said bankruptcy proceedings, and the manufacturing companjr had notice of the bankruptcy proceedings, but never proved or attempted to prove their claim. The balance due Clemmons by Yiaduct Place was set apart to him as a homestead. The order of court confirming the homestead was dated July 18, 1906, and Clemmons was granted his final discharge in bankruptcy July 31, 1906.

Upon the above agreed statement of facts and the admissions of the pleadings the following judgment was rendered: “Upon the pleadings in said case and upon the agreed statement of facts submitted, the court finds for the defendant, J. F. Clemmons, on his plea of discharge in bankruptcy. As no judgment can be rendered against Clemmons as contractor, I find in favor of the other defendant; and judgment is rendered against the plaintiff for costs.” The plaintiff in error excepts upon the ground that the judgment is contrary to law and without authority of law; that the effect of said judgment is to hold that the discharge in bankruptcy of a contractor relieves the property improved of a material-man’s lien for material furnished to improve the same. The contention of the plaintiff in error is, that, while no general judgment can be obtained against the contractor after his discharge in bankruptcy, the bankrupt can be made a party for the purpose of fixing the amount of the debt, and that the debt so fixed thus becomes a lien against the property improved, and the contractor’s discharge in bankruptcy does not relieve the property improved ■of its lien.

We think the finding of the trial judge was manifestly correct, in view of the facts submitted. The contractor was adjudged a bankrupt on October 5/1905, two days before the plaintiff in error filed its claim of lien on the property of Yiaduct Place on account of the material in question. In the contractor’s schedule in bankruptcy it was shown that the plaintiff in error was a creditor of the contractor on this claim for material, and that the claim .was provable in bankruptcy. According to the agreement of facts, the plaintiff in error paid no attention to the proceedings in bankruptcy. It could have gone into the bankrupt court and have established the amount of its lien and identified the use to which its material was put.. It had notice that the bankrupt court was deal[710]*710ing with this debtor, the contractor, and all of his rights and liabilities. This case came on to be. tried November 30, 1906.. On July 21, 1906, the contractor, Clemmons, was given his final discharge in bankruptcy, and such discharge was set up by defendant in his plea. The amount due the contractor by Viaduct Place, as shown by the agreed statement of facts, had been set apart to Clemmons as part of his exemption. The discharge of the contractor relieved Viaduct Place, especially in view of the fact that the title of the indebtedness was vested in the defendant as part of his exemption. The plea of the defendant Viaduct Place, which is not denied, says that “demands had been made on this defendant by the trustee in bankruptcy for said J. F. Clemmons for the balance due by this defendant to said Clemmons on account of said work. This defendant shows that the exclusive jurisdiction of the assets of said J. F. Clemmons, part of which indebtedness of this defendant to said Clemmons on account of work done by him on said building, is vested in the United States District Court, sitting in bankruptcy; and if the plaintiff; has any claim to or lien upon said fund or any part .of it, the court of bankruptcy has full jurisdiction to adjudicate said claim.” The plea proceeded further to state that the defendant withheld the amount due, as shown by the affidavit of Clemmons, made in accordance with the statute, to wit, the sum of $51.15, which is mentioned in the agreed statement, of facts.

Under the very letter of the bankrupt act the court could not enter judgment against Clemmons, because, he had been adjudicated a bankrupt and discharged. Being without power to render judgment against the contractor, the court could not render a general judgment against Viaduct Place. And the plaintiff’s only remedy Avas to enforce against the specific property, into which its material went, a previous or contemporaneous judgment' against the contractor, fixing the amount of the balance due the contractor by the property owner for material furnished. It is well settled that a special judgment, fixing a lien on the property of an owner in favor of one as to whom no privity of contract exists, can not be obtained until there is first a general judgment for the claim against the contractor. Lombard v. Trustees, 73 Ga 322; Castleberry v. Johnson, 92 Ga. 499; Clayton v. Farrar, 119 Ga. 37; Mauck v. Rosser, 126 Ga. 268. It is held in Klipstein v. Allen-[711]*711Miles Co., 136 Federal, 385, that even the process to secure an inchoate lien against one who is adjudged a bankrupt during the progress of the proceeding may be interrupted by bankruptcy proceedings. But this case is even stronger than the Klipstein case; for in the present case- Clemmons had been adjudged a bankrupt before any claim of lien was filed by the plaintiff in error. Before the claim of lien was filed, the debt was duly scheduled in bankruptcy, was provable in bankruptcy, and could be discharged in bankruptcy. For the plaintiff’s right of lien to be perfected, it was bound to file a suit within twelve months and to procure a judgment against the contractor. As bankruptcy proceedings were already pending, the suit was destined to be of no avail, unless the bankrupt failed to procure a discharge.' When the discharge was granted, and wasvpleaded' in the suit, the last chance for the establishment of the special lien was obliterated. In the Klipstein case, cited above, an effort was made to subject the property of a third person to garnishment proceedings. Before final judgment, affecting the rights of such third person, was rendered, there was no obligation as - to such third person.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tri-State Culvert Manufacturing, Inc. v. Crum
228 S.E.2d 403 (Court of Appeals of Georgia, 1976)
Victory Lumber Co. v. Ellison
97 S.E.2d 334 (Court of Appeals of Georgia, 1957)
Carter-Moss Lumber Co. v. Short
18 S.E.2d 61 (Court of Appeals of Georgia, 1941)
Smith v. Folsom
9 S.E.2d 824 (Supreme Court of Georgia, 1940)
Chambers Lumber Co. v. Gilmer
5 S.E.2d 84 (Court of Appeals of Georgia, 1939)
Cutler-Hammer, Inc. v. Wayne
101 F.2d 823 (Fifth Circuit, 1939)
Middle Georgia Lumber Co. v. Hunt
186 S.E. 714 (Court of Appeals of Georgia, 1936)
Ricks v. Smith
93 S.E. 116 (Court of Appeals of Georgia, 1917)
Carr & Co. v. Witt
73 S.E. 668 (Supreme Court of Georgia, 1912)
In re Goodrich
192 F. 746 (N.D. Georgia, 1911)
Pike Bros. Lumber Co. v. Mitchell
64 S.E. 998 (Supreme Court of Georgia, 1909)
Buck v. Tifton Manufacturing Co.
62 S.E. 107 (Court of Appeals of Georgia, 1908)
National Surety Co. v. Medlock
58 S.E. 1131 (Court of Appeals of Georgia, 1907)

Cite This Page — Counsel Stack

Bluebook (online)
58 S.E. 274, 1 Ga. App. 707, 1907 Ga. App. LEXIS 85, Counsel Stack Legal Research, https://law.counselstack.com/opinion/philip-carey-manufacturing-co-v-viaduct-place-gactapp-1907.