Philadelphia Veneer & Lumber Co. v. Garrison

169 S.W. 714, 160 Ky. 329, 1914 Ky. LEXIS 436
CourtCourt of Appeals of Kentucky
DecidedOctober 16, 1914
StatusPublished
Cited by10 cases

This text of 169 S.W. 714 (Philadelphia Veneer & Lumber Co. v. Garrison) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Philadelphia Veneer & Lumber Co. v. Garrison, 169 S.W. 714, 160 Ky. 329, 1914 Ky. LEXIS 436 (Ky. Ct. App. 1914).

Opinion

Opinion of the Court by

Judge Miller

Reversing.

This is an action at law filed by the appellee, Wiley Garrison, against the Philadelphia Veneer & Lumber Co., a Pennsylvania corporation, to recover the balances due under certain logging contracts. A somewhat detailed statement of those contracts, in their chronologic cal order, is necessary to fully understand the case. _

(a) Appellant owns a boundary of land and the ber trees standing thereon, situated on the waters of. Little Clear Creek near Carlsbad Station in Bell County, Kentucky; it also operates a saw mill at Knoxville, Tennessee. Eor the purpose of having the trees cut down and sawed into logs and loaded upon cars at Carlsbad Station, appellant entered into a written contract on May 8, 1907, with Z. B. Garrison, whereby Garrison agreed to cut and deliver the poplar timber, upon cars at Carlsbad Station, for $10.00 per thousand feet. The oak, chestnut, and other timber was to be delivered at [331]*331two designated saw mills in the neighborhood, and for that service the company agreed to pay $4.00 per thousand feet.

Garrison further agreed to complete the work within two years, and that 20 per cent of the contract price should be retained by the company as a forfeit “until the completion of the job,” it being further “distinctly understood and agreed that if the said Garrison should fail to complete his contract the said 20 per cent retained to be forfeited.” Garrison worked under the contract until some time in February, 1909, when, according to appellant, Garrison agreed to cancel the hardwood part of the contract upon the appellant paying Garrison the $2.00 per thousand feet which had been retained on all the hardwood timber gotten out by him to that date, and extending for one year the time for getting out the poplar timber. At that time Garrison had earned $3,409.87 in getting out hardwood timber, the retained portion thereof being $681.95. This last named amount was paid to him on February 26, 1909.

(b) During the spring and summer months of 1909, Z. B. Garrison did but little work, and failed to carry out the contract of May 8, 1907. In August, 1909, ha applied to Yost, the agent of appellant, to know if appellant would consider Garrison taking Granville Garrison in as a partner on the work he was doing. The company consented to the arrangement, but Granville Garrison would not agree to work under the contract of May 8, 1907; and, in order to induce Granville Garrison to undertake the work, Z. B. Garrison agreed to the cancellation of the contract of May 8, 1907, and to the making of a new contract on August 19, 1909, between the company as the party of the first part and Z. B. Garrison and Granville Garrison of the other part. Garrison’s retained money on poplar logs then amounted to $283.08.

Under this new contract the Garrisons agreed to cut and deliver on board the cars at Carlsbad Station all the poplar trees of a specified description on appellant’s said land for $10.00 per thousand feet. Of the contract price, 50 cents per thousand was to be paid to appellant for the use of its tramway; $4.50 thereof was to be paid when the logs were delivered at the end of the tram-road; $3.00 per thousand to be paid when the logs were measured and loaded on the cars and ready for shipment; and the remaining $2.00 of the contract price was to be paid when the Garrisons had completed their [332]*332work; and, in case they should fail to complete their work according to the terms of the contract, “the said $2.00 on each one thousand feet of said logs should be forfeited to and kept by the party of the first part.” Said contract of August 19, 1909, contained this final clause:

“In consideration of this contract, the party of the first part and Z. B. Garrison, of the second part, do hereby agree and declare that the written contract between them of date May 8, 1907, touching logs to be cut on the aforesaid land, and all subsequent written or parol modifications thereof, are no longer of any binding force, but are wholly merged in or superseded by this contract.”

In the spring of 1910, Z. B. Garrison, without consulting appellant, sold out his interest in the contract to Granville Garrison, who, in about July, 1910, abandoned the work and refused to further carry out his contract, although he was urged to do so by the appellant; and upon his failure to continue the work, appellant made other arrangements for the delivery of the logs called for by the contracts of May 8, 1907, and August 19,1909.

(c) Shortly after the abandonment of the contract of August 19, 1909, the appellant made a verbal contract in the month of September, 1910, -with the appellee Wiley Garrison, Z. B. Garrison, and J. H. Wyatt, by which the three named parties were to complete the delivery of certain logs found within a certain boundary which Granville Garrison had failed to deliver while working under the contract of August 19,1909. Under this verbal contract appellee claimed $72.56 was due him; and as the appellant expressly conceded this claim to be correct, nothing further need be said concerning it.

(d) The work which originally had been undertaken by the Garrisons under the contracts of May 8, 1907, and August 19, 1909, remaining unfinished, and appellant being desirous of completing it, it made another contract with the appellees Wiley Garrison and Z. B. Garrison on Septembér 30, 1910, whereby they were to deliver, on the cars at Carlsbad Station, all the poplar timber and logs which Granville Garrison had abandoned and left in the woods. For this they were to get an increased price of $12.00 per thousand feet, $2.00 more than the original contract price, and payable as follows: $5.00 [333]*333per thousand feet when the logs were delivered at the 'end of the tram-way; $5.00 per thousand feet when the logs were received at Knoxville; and the remaining $2.00 per thousand when the entire work was completed.

It is agreed by the parties that under this contract the Garrisons delivered 624 logs, aggregating 148,340 feet, at the end of the tram-way; but appellant stoutly denies that all of the 624 logs were ever received at Knoxville, and insists that only 605 logs, aggregating 117,531 feet, were ever received at Knoxville. The shortage of 19 logs is not accounted for. This transaction is made the basis of the first paragraph of the petition, wherein appellee sued for the balance of' $129.79 alleged to have been retained on 148,340 feet of logs; and in this paragraph appellee further sued to recover $341.22 alleged to be due him as the second payment of $5.00 per thousand feet on 64,244 feet of logs which they claimed had been delivered at Knoxville, but not paid for.

In its answer appellant traversed these two claims, and not only alleged that only 117,531 feet of logs had been delivered at Knoxville under the contract for which it had fully paid , but that, in order to have the remainder of the logs delivered according to the contract, it had been compelled-to go to an additional expense and sustained losses, aggregating $700.00, which it asserted as a counter-claim against the Garrisons.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Milford State Bank v. Parrish
53 P.2d 72 (Utah Supreme Court, 1935)
United Collieries, Inc. v. Martin
60 S.W.2d 125 (Court of Appeals of Kentucky (pre-1976), 1933)
Turner-Elkhorn Coal Co. v. Smith
56 S.W.2d 545 (Court of Appeals of Kentucky (pre-1976), 1932)
Reusch v. Hemmer
33 S.W.2d 618 (Court of Appeals of Kentucky (pre-1976), 1930)
Asher v. Golden
22 S.W.2d 411 (Court of Appeals of Kentucky (pre-1976), 1929)
Dejarnett v. Tutt
18 S.W.2d 968 (Court of Appeals of Kentucky (pre-1976), 1929)
Wallins Creek Collieries Company v. Saylor
282 S.W. 1095 (Court of Appeals of Kentucky (pre-1976), 1926)
Jones v. Stearns
260 S.W. 373 (Court of Appeals of Kentucky, 1924)
Coy v. King
250 S.W. 503 (Court of Appeals of Kentucky, 1923)
Power Grocery Co. v. Hinton
218 S.W. 1013 (Court of Appeals of Kentucky, 1920)

Cite This Page — Counsel Stack

Bluebook (online)
169 S.W. 714, 160 Ky. 329, 1914 Ky. LEXIS 436, Counsel Stack Legal Research, https://law.counselstack.com/opinion/philadelphia-veneer-lumber-co-v-garrison-kyctapp-1914.