Philadelphia Rapid Transit Co. v. Public Service Commission

78 Pa. Super. 593, 1922 Pa. Super. LEXIS 169
CourtSuperior Court of Pennsylvania
DecidedApril 17, 1922
DocketAppeal, No. 31
StatusPublished
Cited by14 cases

This text of 78 Pa. Super. 593 (Philadelphia Rapid Transit Co. v. Public Service Commission) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Philadelphia Rapid Transit Co. v. Public Service Commission, 78 Pa. Super. 593, 1922 Pa. Super. LEXIS 169 (Pa. Ct. App. 1922).

Opinion

Opinion by

Linn, J.,

Complaint was made to the commission that certain rerouting of cars by appellant furnished inadequate service. The commission sustained the complaint in part, and this appeal by the transit company followed.

The appeal was by petition pursuant to article VI, section 17 as amended in 1915, P. L. 779. Section 18 requires the commission to certify to this court “the record of the said proceedings; which record shall include the evidence taken therein......” (1917, P. L. 808). Section 23 provides “and the notes of testimony taken before the commission or any of the members thereof, duly certified under its seal, and filed as aforesaid as a part of the record, shall be considered by the court as the testimony in the case.” Section 24 provides that if this court “upon the record, find that the order appealed from is unreasonable......or is otherwise not in conformity with law, it may......remand the record to the commission with directions to reconsider the matter and make such order as shall be reasonable and in conformity with law.”

It is alleged that the commission received the reports or opinions of two expert witnesses on the issues in[596]*596volved without permitting cross-examination by appellant. While the certified record shows that such evidence was taken, the reports are not in the record, and in its answer to the petition for appeal, the commission denies that its conclusions were predicated upon the reports. We do not doubt the accuracy of that answer, but in such circumstances, it is clear that merely requiring the record now before us to be supplemented by the addition of the omitted evidence, will not cure the error if the record supports the allegation that the evidence was so received, for who can tell what the cross-examination would have elicited or what countervailing proof might have been received in consequence?

The learned counsel for the commission informed us at bar that the commission referred the reports to its engineering bureau which may or may not have read them, in performing its duties to the commission in this case.

The record shows that after the testimony had been closed, briefs were submitted and the case was argued before the commission. Thereafter the commissioner who had taken the testimony, called a meeting of counsel for the parties to the proceedings, when witnesses were sworn and additional evidence was taken. Though the City of Philadelphia was not a party to the proceedings, an assistant city solicitor representing the Transit Department of the City of Philadelphia was present. The commissioner suggested that the assistant city solicitor obtain a representative of the City Transit Department to join with an expert representing complainants, and one representing appellant, “to study this record and go over this routing and make a report. If they cannot make a unanimous report, let them make individual reports,......Then I will take up those reports with our engineer, Mr. Jones, and go over them, and then I will make an order......” Later, he said, “That great department of City Transit must have someone familiar with routing......I want a man independent [597]*597of our commission. Our own engineers I want to keep out of it until I come to make the order, and then I want them. I thought possibly I could have studies from the standpoint of the City, by a city engineer......”

The record advises that the three experts failed to agree, whereupon separate and independent reports were prepared by two of them, one, by the engineer for complainants, and the other, by the engineer employed in the department of city transit; these reports made various recommendations and at least one of them was based in part upon investigation by the city transit department.

The record shows the following took place when the assistant city solicitor was asked by the commissioner for the report of the city engineer:

The Assistant City Solicitor: “Ás I understood it, you asked me to provide some one to help you in the formulation of your decree in this matter.

Commissioner: Not exactly that. Not in the formulation of my decree, but simply to give me additional light, so that when I came to write a decree I would have the benefit of the thought of the engineers of the City of Philadelphia.

Mr. Rosenbaum: You see, I do not want our man to be put in the position of being an additional expert witness in the case, who was not subject to cross-examination. That is a thing that ought to be avoided.

Commissioner: No. You are quite right about that. But I asked you for this report, and if I want to make it a part of the record then I can subpoena the engineers to come here and submit them to cross-examination by the counsel for the respondent company. If I do not want to make the report a part of the record, therefore it will not be necessary to have any cross-examination.

“Mr. Rosenbaum:......but I would like to make it plain that our Department of Transit, and our engineers, do not desire and do not feel that they have any power [598]*598to be put in the position of supervising the details of operation of the Philadelphia Rapid Transit Company.

“Commissioner: No. We do not want to have any misunderstanding about that. I agree with you that the Department of City Transit of the City of Philadelphia has nothing whatever to do with that, but I can call on their engineers, as I would call on any engineer, to give me information that would guide me in determining the particular matter. I do not mean to say that I would accept his report as verity, or that it would be conclusive with me, but it would be helpful in getting some independent man to give me his view on this subject. You may be sure that it will not be treated as a supervision by the Department of City Transit, or a determination of the question by the Department of City Transit at all, because, of course, I would not permit that as a commissioner. The commission hasn’t any right to do that. But they have a right to give me information, just as I might call on them to give me information from their statistical department.

“Mr. Rosenbaum:......but another thing that I should like to make perfectly clear is that we are not attempting to create here a precedent, by which we are to be made available for service in rendering decisions in cases such as the route 19 or the Sixty-ninth Street Terminal case.

“Commissioner: That will be so understood.

“Mr. Rosenbaum: With that understanding, if your Honor please, I take great pleasure in presenting to you the result of the study made by our engineer.” (Mr. Conroy.)

■******•«•**

“Mr. Ballard: Mr. Commissioner, do we understand from Mr. Rosenbaum that this comes from Mr. Conroy as an individual whom your Honor has called on to advise you, or give you additional data, and not from the City of Philadelphia or the Department of City Transit or the Director of Transit?

[599]*599“Commissioner: That is correct.

“Mr. Ballard: And, furthermore, with this understanding that if it is to be considered at all by the commission it will be made part of the record and subject to cross-examination? Is that right?

“Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vandergrift Borough v. Polito
156 A.2d 99 (Supreme Court of Pennsylvania, 1959)
Gottshall v. Batt
18 Pa. D. & C.2d 137 (Dauphin County Court of Common Pleas, 1958)
Greenville Dairy Co. v. Pennsylvania Milk Control Commission
68 Pa. D. & C. 597 (Mercer County Court of Common Pleas, 1949)
Bolivar Borough Appeal
65 A.2d 390 (Supreme Court of Pennsylvania, 1949)
Shenandoah Suburban Bus Lines, Inc., Case
46 A.2d 26 (Superior Court of Pennsylvania, 1945)
Patanyi v. Davis
9 A.2d 430 (Supreme Court of Pennsylvania, 1939)
Commonwealth v. Ziegler Dairy Co.
11 A.2d 669 (Superior Court of Pennsylvania, 1939)
Philadelphia Labor's Non-Partisan League Club's Application for Inc.
196 A. 22 (Supreme Court of Pennsylvania, 1937)
Cage v. Public Service Commission
189 A. 896 (Superior Court of Pennsylvania, 1936)
Latrobe Water Co. v. Public Service Commission
186 A. 294 (Superior Court of Pennsylvania, 1936)
Beatty v. P. S. C.
169 A. 21 (Superior Court of Pennsylvania, 1933)
Hoffman v. Public Service Commission
99 Pa. Super. 417 (Superior Court of Pennsylvania, 1930)
City of Philadelphia v. Public Service Commission
84 Pa. Super. 135 (Superior Court of Pennsylvania, 1924)
Erie City v. Public Service Commission
123 A. 471 (Supreme Court of Pennsylvania, 1924)

Cite This Page — Counsel Stack

Bluebook (online)
78 Pa. Super. 593, 1922 Pa. Super. LEXIS 169, Counsel Stack Legal Research, https://law.counselstack.com/opinion/philadelphia-rapid-transit-co-v-public-service-commission-pasuperct-1922.