Philadelphia Indemnity Insurance Company v. Blue Mountain Contractors, LLC

CourtDistrict Court, D. New Mexico
DecidedMay 23, 2022
Docket1:20-cv-01293
StatusUnknown

This text of Philadelphia Indemnity Insurance Company v. Blue Mountain Contractors, LLC (Philadelphia Indemnity Insurance Company v. Blue Mountain Contractors, LLC) is published on Counsel Stack Legal Research, covering District Court, D. New Mexico primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Philadelphia Indemnity Insurance Company v. Blue Mountain Contractors, LLC, (D.N.M. 2022).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW MEXICO

PHILADELPHIA INDEMNITY INSURANCE COMPANY,

Plaintiff,

v. Civ. No. 1:20-cv-01293 MIS/SCY

BLUE MOUNTAIN CONTRACTORS, LLC, ROGELIO AVILA, and NOIRA I. AVILA,

Defendants.

MEMORANDUM OPINION AND ORDER THIS MATTER comes before the Court on Plaintiff’s Request for Clerk’s Entry of Default Judgment (ECF No. 10) and Supplement to Request for Entry of Default Judgment (ECF No. 14). For the reasons explained below, the Court grants Plaintiff’s request in full and enters default judgment as to damages. BACKGROUND The facts relevant to Plaintiff’s request for default judgment are as follows.1 Plaintiff brought suit in this Court on December 14, 2020, alleging a single claim for breach of contract based on the General Indemnity Agreement executed January 16, 2018. ECF No. 1. Although service was timely effected on all Defendants, they neither responded to the complaint nor entered an appearance in the case. The Clerk filed an Entry of Default on February 11, 2021. ECF No. 8. On March 31, 2021, Plaintiff requested an entry of default judgment by the Clerk. ECF No. 10; see Fed. R. Civ. P. 55(b)(1). In a Memorandum Opinion and Order (“MOO”)

1 A thorough recitation of the facts was given in the Court’s prior Memorandum Opinion and Order, see ECF No. 12, and will not be repeated here but is incorporated by reference. issued on June 28, 2021, the Court granted Plaintiff’s request and entered default judgment as to liability. ECF No. 12. However, the Court denied Plaintiff’s request as to damages because it found that Plaintiff (1) had presented no evidence of the amount actually paid to complete Defendants’ work, and (2) did not cite a New Mexico statute authorizing prejudgment interest in the amount sought. Id. at 5–7. The Court ordered Plaintiff to supplement the record with evidence supporting its losses. ECF No. 13. Plaintiff timely complied.

On September 7, 2021, several months after the Court entered default judgment as to liability, Defendant Rogelio Avila filed a letter requesting an extension of time to obtain counsel. ECF No. 15. The Court granted an extension until January 25, 2022. ECF No. 20. A hearing was held on that date. ECF No. 21. Defendant Rogelio Avila appeared, informed the Court that Defendants had not succeeded in obtaining representation, and requested a further extension. In light of the lengthy extension already granted, his request was denied. ECF No. 22. Defendants Rogelio and Noira Avila2 neither filed a response nor sought an extension of time to respond to Plaintiff’s request for default judgment. The final disposition of this matter is now before the Court.

LEGAL STANDARD The Federal Rules of Civil Procedure define a two-step process for the entry of default judgment. First, “[w]hen a party against whom a judgment for affirmative relief is sought has failed to plead or otherwise defend . . . the clerk must enter the party’s default.”

2 As the Court explained in a prior Order, Defendant Blue Mountain Contractors, LLC, cannot proceed without an attorney. See ECF No. 20 at 2. It was therefore unable to respond, either pro se or through Defendants Rogelio and Noira Avila. Fed. R. Civ. P. 55(a). Second, the plaintiff must request an entry of default judgment. Fed. R. Civ. P. 55(b). If the plaintiff’s claim is for “a sum certain or a sum that can be made certain by computation” and the defendant is neither a minor nor incompetent, default judgment may be entered by the clerk. Fed. R. Civ. P. 55(b)(1). In all other instances, default judgment must be entered by the court. Fed. R. Civ. P. 55(b)(2). At this second stage, following the clerk’s entry of default, the court takes as true “all factual allegations in the complaint, except those pertaining to the amount of

damages.” Archer v. Eiland, 64 F. App’x 676, 679 (10th Cir. 2003); see also Fed R. Civ. P. 8(b)(6) (“An allegation—other than one relating to the amount of damages—is admitted if a responsive pleading is required and the allegation is not denied.”). The court may conduct a hearing to determine the amount of damages. Fed. R. Civ. P. 55(b)(2)(B). However, the court may enter default judgment without a hearing “if the amount claimed is a liquidated sum or one capable of mathematical calculation.” Hunt v. Inter-Globe Energy, Inc., 770 F.2d 145, 148 (10th Cir. 1985). DISCUSSION I. COMPENSATORY DAMAGES Defendants agreed to indemnify Plaintiff from all damages arising from the

“investigation of claims or potential claims, procuring or attempting to procure the discharge of [the] Bond, or attempting to recover losses or expenses from [Defendants] or third parties.” ECF No. 1-4 at 6. Plaintiff claims $337,732.273 in compensatory damages. This total consists of $387,507.66 paid to subcontractors and suppliers for

3 These compensatory damages do not include Plaintiff’s claimed attorney fees, see ECF No. 14-1 at ¶ 9, which are addressed below. Plaintiff’s entitlement to prejudgment interest is also addressed below. amounts unpaid and to complete the project; $42,913.14 to construction consultants for an initial investigation and to complete the project; and $1,208.08 to inspect the project site and meet with the client, Fort Sumner Municipal Schools. ECF No. 14-1 at ¶¶ 7, 8, 10. These expenses totaled $431,628.88. Upon completion of the construction project, Fort Sumner Municipal Schools paid Plaintiff $93,896.61, which is subtracted from Plaintiff’s actual damages for a total of $337,732.27. Id. at ¶ 11. These amounts are supported by the Declaration of Robin Wilcox, Plaintiff’s

Claims Examiner, and by attached copies of all checks paid by Plaintiff to subcontractors, suppliers, and laborers to complete the project and satisfy Plaintiff’s duties under the Bonds. See ECF No. 14-1. Upon review of the documentary evidence, the Court finds the amount of Plaintiff’s damages is “a sum that can be made certain by computation.” Fed. R. Civ. P. 55(b)(1); see also Hunt, 770 F.2d at 148; Seme v. E & H Prof’l Sec. Co., 2010 U.S. Dist. LEXIS 48011, at *31 (D. Colo. Mar. 19, 2010) (“In ruling on a motion for default judgment, the court may rely on detailed affidavits or documentary evidence to determine the appropriate sum for the default judgment.”). A hearing is therefore unnecessary, and the Court will enter default judgment in the amount of $337,732.27 plus all applicable interest and fees.

II. PREJUDGMENT INTEREST Because Defendants were found liable for breach of contract, Plaintiff is statutorily entitled to prejudgment interest of “not more than fifteen percent.” N.M. Stat. § 56-8-3(A);4 Shaeffer v. Kelton, 619 P.2d 1226, 1232 (N.M. 1980). “Prejudgment interest is awarded

4 Section 56-8-3 regulates the rate of prejudgment interest “in the absence of a written contract fixing a different rate.” N.M. Stat. § 56-8-3.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Archer v. Eiland
64 F. App'x 676 (Tenth Circuit, 2003)
City of Farmington v. Amoco Gas Company
777 F.2d 554 (Tenth Circuit, 1985)
Gamble, Simmons & Company v. Kerr-Mcgee Corporation
175 F.3d 762 (Tenth Circuit, 1999)
Sunwest Bank of Albuquerque, N.A. v. Colucci
872 P.2d 346 (New Mexico Supreme Court, 1994)
Kueffer v. Kueffer
791 P.2d 461 (New Mexico Supreme Court, 1990)
Shaeffer v. Kelton
619 P.2d 1226 (New Mexico Supreme Court, 1980)
Budagher v. Sunnyland Enterprises, Inc.
603 P.2d 1097 (New Mexico Supreme Court, 1979)
Montoya v. Villa Linda Mall, Ltd.
793 P.2d 258 (New Mexico Supreme Court, 1990)
Smith v. McKee
859 P.2d 1061 (New Mexico Supreme Court, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
Philadelphia Indemnity Insurance Company v. Blue Mountain Contractors, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/philadelphia-indemnity-insurance-company-v-blue-mountain-contractors-llc-nmd-2022.