Phil W. Morris Co. v. Schwartz

673 P.2d 28, 138 Ariz. 90, 1983 Ariz. App. LEXIS 570
CourtCourt of Appeals of Arizona
DecidedSeptember 22, 1983
Docket1 CA-CIV 5960
StatusPublished
Cited by11 cases

This text of 673 P.2d 28 (Phil W. Morris Co. v. Schwartz) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Phil W. Morris Co. v. Schwartz, 673 P.2d 28, 138 Ariz. 90, 1983 Ariz. App. LEXIS 570 (Ark. Ct. App. 1983).

Opinion

OPINION

KLEIN SCHMIDT, Judge.

This is an appeal from an order of the trial court granting summary judgment in favor of the plaintiff, The Phil W. Morris Company, and against appellants, Jack J. and Shelia Schwartz. We affirm the judgment of the trial court.

The Phil W. Morris Company, a general contractor, entered into an agreement to remodel the Schwartz residence. As of May 2, 1980, the contractor had billed the homeowners a total of $228,667 and as of May 5, 1980, the homeowners had paid the contractor the sum of $193,840.80. About this time a dispute arose and the Schwartzes refused to make any further payments.

The contractor filed a verified complaint alleging a cause of action in contract and in quantum meruit for labor and materials furnished. The Schwartzes filed an unverified answer and counterclaim in which they admitted that the contractor had furnished labor and materials but alleged they had paid the contractor in excess of the value of the same. They also filed a counterclaim which sought reimbursement for the excess charges paid.

Thereafter, the contractor filed a motion for partial summary judgment on the contract claim. The motion was supported by the affidavit of Richard J. Morris, a vice president of the construction company who was responsible for the job on the Schwartz home. According to the affidavit, the company’s books and records relating to the job were kept in the usual course of business under his supervision and control. Based upon those records and his own knowledge, Morris swore that the company had provided labor and materials to the Schwartzes at their request. A summary of the record was attached to the affidavit, which Morris swore accurately reflected the work done and the amounts billed. Also attached to the affidavit were 517 other items consisting of invoices and records which provided the factual support for the summary of charges. The affidavit concluded that after *92 all credits were allowed there remained due and owing to the contractor the sum of $55,305.45.

The Schwartzes filed a response to the company’s. motion for partial summary judgment and a document entitled “Defendant’s Denial of Account Pursuant to 8 R.C.P. 8(c),” which read:

Jack J. Schwartz, being first duly sworn, deposes and says:
That he is a defendant in the above entitled action and that he hereby, under oath, denies that the account set forth in the amended complaint herein is just or true in whole or in part.

After filing their response the Schwartzes filed a request for production of documents seeking access to what they described as a wide range of documents relating to the construction work. The date specified in the request for production as the time by which the items were to be provided was after the time set for the hearing on the motion for summary judgment.

Following a hearing the trial court granted the company’s motion for summary judgment. Approximately three months later the Schwartzes filed a Motion for Reconsideration and Rehearing of Plaintiff’s Motion for Partial Summary Judgment. To this they attached the affidavits of Jack J. Schwartz and two other men who were familiar with the construction business. The affidavits raised numerous questions of fact as to the propriety of the contractor’s bill. The court reconsidered the matter on the record as it existed at the time the motion for summary judgment was granted and reaffirmed that decision.

THE CONTRACT

The Schwartzes urge that summary judgment should not have been granted because there was insufficient evidence of the existence of the contract and the company’s right to recover thereunder to give rise to a prima facie case. They first argue that it is improper to grant summary judgment when facts key to a recovery have not been determined and that the burden is on the one seeking recovery under a contract to establish all of its material conditions. We have no question but that the law is as appellants set it forth. What is more difficult to determine is whether there was anything lacking in plaintiff’s allegations and proof to render them insufficient to raise a prima facie case. The appellants point to three overlapping areas in which they say the plaintiff’s case was deficient:

1. The Morris affidavit did not sufficiently allege that a contract was in existence;
2. The Morris affidavit made no allegation that all work done and billed was done and billed pursuant to an agreement, and
3. The plaintiff never produced any proof that the “work was done in accordance with an agreement, or that the level of payment was the level of payment specified in the agreement, etc., etc., etc.....” They argue that the memorandum of points and authorities attached to plaintiff’s motion for summary judgment did not set forth any basis for a legal recovery under the contract.

The Morris affidavit was sufficient to raise a prima facie case as to the existence and terms of the contract. In the verified amended complaint the company alleged that it had “agreed to furnish labor, materials and other services to defendants for the remodeling and certain other construction of defendants’ residence” and that “defendants agreed to pay plaintiff for the labor, materials and services provided.” The company alleged that it had fully performed, that the Schwartzes refused to pay, and that a specific sum was due and owing. We think the appellee pleaded and presented the essential facts. In their counterclaim the Schwartzes conceded that the plaintiff had furnished labor and materials to the defendants and that they had paid it a specified sum. They alleged affirmative defenses of failure of consideration, payment and the statute of frauds except as to goods received and accepted and asserted that they had paid in excess of what the labor and materials were worth.

*93 The Schwartzes contend that the answer and counterclaim and their affidavit filed pursuant to Rule 8(c), Ariz.R.Civ.P., raised unresolved issues of fact so as to preclude a grant of summary judgment. The Schwartzes are wrong, because the answer and counterclaim was unverified and the affidavit was conclusory. Rule 56(e), Ariz.R.Civ.P., specifically requires that opposing affidavits must be made on personal knowledge and set forth facts that would be admissible in evidence and show affirmatively that the affiant is competent to testify as to the matters stated therein. It further requires that the party contesting a motion for summary judgment may not rest on mere allegations or denials of his pleadings but his response by affidavits or otherwise must set forth specific facts showing that there is a genuine issue for trial. This the appellants completely failed to do.

None of the law appellants cite changes our conclusion because the contextual differences between their cases and this one vary widely. Several of those cases are inapposite because they deal with the propriety of granting a motion for judgment on the pleadings, a completely different procedure from a motion for summary judgment and one which takes the challenge to a pleading as true. 1 The case of Chemical Foundation v. Universal-Cyclops Steel Corp., 2

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brody v. Polsinelli
Court of Appeals of Arizona, 2019
nur/ibrahim v. Scottsdale
Court of Appeals of Arizona, 2014
Cooper v. Ross
Court of Appeals of Arizona, 2014
Holland v. Hurley
212 P.3d 890 (Court of Appeals of Arizona, 2009)
Tilley v. Delci
204 P.3d 1082 (Court of Appeals of Arizona, 2009)
Heuisler v. Phoenix Newspapers, Inc.
812 P.2d 1096 (Court of Appeals of Arizona, 1991)
Wells Fargo Credit Corp. v. Smith
803 P.2d 900 (Court of Appeals of Arizona, 1990)
Wright v. Hills
780 P.2d 416 (Court of Appeals of Arizona, 1989)
Boy v. Fremont Indemnity Co.
742 P.2d 835 (Court of Appeals of Arizona, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
673 P.2d 28, 138 Ariz. 90, 1983 Ariz. App. LEXIS 570, Counsel Stack Legal Research, https://law.counselstack.com/opinion/phil-w-morris-co-v-schwartz-arizctapp-1983.