Pfotzer

652 F.2d 69, 28 Cont. Cas. Fed. 81,051, 226 Ct. Cl. 645, 1981 U.S. Ct. Cl. LEXIS 70
CourtUnited States Court of Claims
DecidedFebruary 6, 1981
DocketNo. 274-72
StatusPublished
Cited by1 cases

This text of 652 F.2d 69 (Pfotzer) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Pfotzer, 652 F.2d 69, 28 Cont. Cas. Fed. 81,051, 226 Ct. Cl. 645, 1981 U.S. Ct. Cl. LEXIS 70 (cc 1981).

Opinion

This is a government contract action in which the plaintiffs appear pro se on the parties’ cross-motions for summary judgment. Plaintiff contractors take the position that they were deprived of procedural due process when the Corps of Engineers Board of Contract Appeals (the Board) refused to grant an extension of their hearing date, and that this resulted in a failure to comply with the Wunder-lich Act, 41 U.S.C. §§ 321, 322. Defendant answers that the administrative decision is legally and factually correct, is supported by substantial evidence, and should be upheld by this court. For the reasons set forth below, we hold for defendant because we find, without need for oral argument, that there has been no violation of plaintiffs’ due process rights, and that the Board’s decision is in full compliance with Wunderlich Act standards.

Edmond Pfotzer and E. John Pfotzer are partners in a business which in 1949 was awarded a contract to construct some additional filters at the filtration plant of the Washington Aqueduct in and near the District of Columbia. After completion of the work, which was delayed past the [646]*646contract completion date, plaintiffs filed numerous claims with the Contract Appeals Board, relating inter alia to delays, liquidated damages and work quality. Some of these claims were the subject of the petition in the present case filed by plaintiffs in this court in 1972. As a result of discovery initiated by plaintiffs in the Court of Claims action, they were granted a stay of proceedings in this court, and thereupon petitioned the Board for a rehearing of its decisions based on alleged newly discovered evidence. This motion was granted by the Board, and plaintiffs filed twelve amended complaints with the Board by April 4, 1978. In response to several requests by plaintiffs that defendant file answers to the complaints, the Board informed the parties on June 22, 1978, that unless answers were received within 30 days, the Board would enter a general denial on the Government’s behalf, as provided for in Rule 6(b) of the Board’s Rules. By letter of July 14,1978 to the Board, the Government acquiesced in the issuance of a general denial, and so informed plaintiffs. In addition to this general denial, in October 1978, the defendant filed motions to dismiss the complaints, and by order of the Board on November 9,1978, the motions were considered as part of defendant’s answers. This order also required defendant to file more extensive answers within seven days of receipt of the order. These supplemental answers were filed on November 14, although plaintiffs allege that they did not receive them until November 27.

During August 1978, the rehearing, which had been originally scheduled at an earlier date and postponed severed times pursuant to requests of both parties, was finally set for December 5, 1978. Plaintiffs objected to this date as allowing them insufficient time to evaluate the Government’s motions and answers, and to prepare for the hearing, but they were unsuccessful in obtaining the three-month extension they sought. In addition to repeatedly denying plaintiffs’ extension request, the Board specifically informed plaintiffs on November 29,1978, that

[t]he unexcused absence of a party at the prehearing conference or at the hearing on 5 December 1978 will not be occasion for delay. In the event of such absence, the [647]*647hearing will proceed and the case will be regarded as submitted by the absent party as provided by Rule 11.

Notwithstanding this order, plaintiffs informed the Board that they would not appear at the December 5 hearing, that they did not waive a hearing, and that they urged the Board to reconsider its denial of an extension — a denial which plaintiffs contended was a deprivation of their procedural due process rights. Plaintiffs did not appear at the hearing, and on December 11, 1978, the Board wrote plaintiffs informing them that the hearing had been held, as scheduled, that their absence had been ruled to be unexcused, and that the case had been treated as being submitted for decision on the record, without an oral hearing for plaintiffs.

After evaluating the evidence before it, including the newly discovered evidence, the Board issued its opinion in August 1979. In it the Board denied most of plaintiffs’ claims, but granted at least partial relief to plaintiffs on two of their claims.1 In October 1979, the Board denied plaintiffs’ motion for reconsideration of its August opinion.

Plaintiffs’ current motion for judgment in this court is based on the sole ground that the administrative decision should be overturned because the Board’s actions with respect to the procedural aspects of the hearing violated their rights of due process under the Fifth and Fourteenth2 Amendments (as well as the Board’s rules, and the Disputes clause). This deprivation purportedly resulted, at least primarily, from the Board’s refusal to grant plaintiffs a three-month extension of their hearing date. This action, according to plaintiffs, was sufficient to deprive them of their constitutional right to a full-scale hearing and to render the Board’s decision invalid as being "capricious or arbitrary or so grossly erroneous as necessarily to imply bad faith * * 41 U.S.C. § 321. Plaintiffs also argue that the Board’s determination fails to meet the Wunderlich Act requirement that it be supported by substantial evidence. Id.

[648]*648We conclude, on full consideration, that the record provides no support for plaintiffs’ contention that they were denied procedural due process. While the exact requirements of due process may vary according to the particular circumstances of a case,

"there can be no doubt that at a minimum they require that deprivation of life, liberty or property by adjudication be preceded by notice and opportunity for hearing appropriate to the nature of the case.” * * * "The fundamental requisite of due process of law is the opportunity to be heard,” * * * a right that "has little reality or worth unless one is informed that the matter is pending and can choose for himself whether to . . . contest.” [Goss v. Lopez, 419 U.S. 565, 579 (1975) (citations omitted) (emphasis added).]

Accord, Boddie v. Connecticut, 401 U.S. 371, 377-78 (1971). This standard is appropriate to measure the due process challenge plaintiffs now make.

There is no doubt that these requirements of notice and an opportunity to be heard were fully granted to plaintiffs in this instance. As early as August 1978, plaintiffs were informed by the Board that the rehearing would be held on December 5,1978. In addition to this period of time between notice and hearing, plaintiffs had a five-year period between the 1973 suspension of proceedings in this court and the December 1978 Board hearing involved here in which to prepare their case.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pfotzer v. United States
231 Ct. Cl. 794 (Court of Claims, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
652 F.2d 69, 28 Cont. Cas. Fed. 81,051, 226 Ct. Cl. 645, 1981 U.S. Ct. Cl. LEXIS 70, Counsel Stack Legal Research, https://law.counselstack.com/opinion/pfotzer-cc-1981.